Step 1: Site Survey

Step 2: Leveling of site

Step 3:Site after leveling

Step 4:Marking of mounting structure

Step 5:Drilling Holes for Foundations

Step 6:Solar Foundations

Step 7:Adjusted frame of solar panel

Step 8:Fitting of Module & Alignment

Step 9:DC Cable laying and conduit dressing

Step 10:Control Room

Step 11:Measure of tilt angle

Step 12:Transmission line for solar plant

Step 12:Transmission line