Quality analysis of hmc

Preview:

Citation preview

Quality analysis of Machine Shop (HMC)

Presenting:

GROUP # 01

Abu Bakar Siddique ME123009

Shahid Hussain ME123019

Muhammad Ifraheem ME123022

Fahad Akhter ME123082

Introduction of HMC

• Leading enterprise in a country.

• Two main Production unit

• Mechanical works

• Foundry & Forge works

• Mechanical works starts 1971

Machine Shop

• Most Important Shop

• Contributes major part in income of industry

• Divided in three categories

• Small Bay

• Medium Bay

• Heavy Bay

• Batch Production

TurningDrawing Reading

Dimension Correct

Facing

Dimension CorrectMilling

Dimension CorrectDrilling

Store

Dimension Correct

If YES

If YES

• If NO

If YES

If NO

If NO

If NO

If NO If NO

If YES

Flow Chart

Turning Data

Turning 1 2 3 4 Avg Dia Range

1 420.2 419.6 419.8 420.1 419.925 0.6

2 419.9 420.3 420.1 419.9 420.05 0.4

3 420.8 420.2 420.5 420.3 420.45 0.6

4 420 419.9 419.8 420 419.925 0.2

5 420.4 420 420.3 420.1 420.2 0.4

6 419.5 420.2 419.9 420.1 419.925 0.7

7 420.4 419.8 420.2 419.9 420.075 0.6

8 420.2 419.9 420 420.1 420.05 0.3

9 420.3 419.9 420.2 419.9 420.075 0.4

10 420.2 419.6 420.1 419.7 419.9 0.6

Charts and Capability

Cp= 0.574 Cpk=

1 2 3 4 5 6 7 8 9 10419419.2419.4419.6419.8

420420.2420.4420.6

X- Bar Chart

Avg. Diameter MeanUCL LCL

Dia

met

er (

mm

)

1 2 3 4 5 6 7 8 9 100

0.2

0.4

0.6

0.8

1

1.2

R-Chart

Range R UCL(R) LCL(R)

Rang

e

Facing Data

Facing 1 2 3 4 Avg. Width Range

1 36.4 35.8 36.2 35.9 36.075 0.6

2 35.8 36.2 36 36.1 36.025 0.4

3 36.5 35.5 36.2 35.3 35.875 1.2

4 36.3 35.9 36.1 35.8 36.025 0.5

5 35.7 36.2 35.9 36 35.95 0.5

6 35 36.5 36.4 36.1 36 1.5

7 35.8 36.4 36.2 35.9 36.075 0.6

8 36.2 35.7 35.9 36.2 36 0.5

9 36.8 36.4 35.9 36 36.275 0.9

10 35.6 36.3 36.3 35.8 36 0.7

Charts and Capability

Cp= 1.66 Cpk=

1 2 3 4 5 6 7 8 9 1034.8

35.2

35.6

36

36.4

36.8

X- Bar Chart

Avg, Width MeanUCL LCL

Wid

th (

mm

)

1 2 3 4 5 6 7 8 9 1000.20.40.60.8

11.21.41.61.8

R-Chart

Range R UCL(R) LCL(R)

Rang

e

Milling DataMilling 1 2 3 4 Avg Depth Range

1 24.4 23.8 24.2 23.7 24.025 0.7

2 24.6 24.2 24.3 24.6 24.425 0.4

3 23.7 24.2 24.1 23.9 23.975 0.5

4 24.4 23.6 23.9 24.2 24.025 0.8

5 24.2 23.9 23.9 24.1 24.025 0.3

6 23.9 24.7 24.5 23.9 24.25 0.8

7 24.2 23.7 23.9 24 23.95 0.5

8 24.3 23.7 23.9 24.1 24 0.6

9 23.8 24.1 24 23.9 23.95 0.3

10 24.5 23.6 23.7 24.4 24.05 0.9

Charts and Capability

Cp= 1.15 Cpk=

1 2 3 4 5 6 7 8 9 1023.223.423.623.8

2424.224.424.6

X- Bar Chart

Avg. Depth MeanUCL LCL

Dep

ht (

mm

)

1 2 3 4 5 6 7 8 9 1000.20.40.60.8

11.21.4

R-Chart

Range R UCL(R) LCL(R)

Rang

e

Drilling Data

Drilling 1 2 3 4 Avg. Depth Range

1 15.8 16 15.9 15.8 15.875 0.2

2 16.4 16.5 16.1 16.2 16.3 0.4

3 15.9 16 16 16 15.975 0.1

4 16.5 16.2 16.3 16.4 16.35 0.3

5 15.8 15.9 16 15.9 15.9 0.2

6 15.8 15.9 15.9 15.9 15.875 0.1

7 16.1 15.8 15.9 16.1 15.975 0.3

8 16.3 16.1 16.2 16.1 16.175 0.2

9 16 16 15.9 15.9 15.95 0.1

10 16.4 16.1 16.3 16.4 16.3 0.3

Charts and Capability

Cp= 0.877 Cpk=

1 2 3 4 5 6 7 8 9 101515.215.415.615.8

1616.216.416.6

X-Chart

Avg. Dia UCL LCL Mean

Dia

met

er

1 2 3 4 5 6 7 8 9 1000.10.20.30.40.50.6

R-Chart

Range UCL(R) LCL(R) R

Rang

e

Cause and effect diagram

Flow Process ChartProcesses Time ⃝� → □ D ∇

Drawing Reading 05 min √        

Transfer to Turning machine 02 min   √      

Machine checking 02 min     √    

Turning 12 min √        

Transfer to Grinding machine 02 min   √      

Tool Grinding 01 min √        

Check dimensions 02 min     √    

Transfer to another machine for facing 03 min   √      

Facing 10 min √        

Check dimensions 02 min     √    

Transfer to Grinding machine 01 min   √      

Tool Grinding 01 min √        

Supervisor inspection 05 min     √    

Transfer to Milling 02 min   √      

Wait for completing job 14 min       √  

Milling 40 min √        

Check dimensions 05 min     √    

Supervisor inspection 05 min     √    

Transfer to Drilling 02 min   √      

Drilling 10 min √        

Check dimensions 02 min     √    

Transfer to QC Department 05 min   √      

Quality Inspection 07min     √    

Transfer to store 05 min   √      

Store ----         √

Calculations

Total Time= 143 min

Operation Time= 79 min, Transport Time=22 min, Inspection Time= 30 min,

Delay Time =14 min

Efficiency % = =%

Questionnaire

Questions SA A N D SD

Material quality of HMC products is good enough. 1 5 2 2 1

Dimensional accuracy is within specified limits. 2 4 3 1 1

HMC is able to ship out products in a given time period. 2 4 1 3 1

Are all design reviewed tested and verified? 1 3 5 2 0

HMC products are reliable. 3 5 3 0 0

HMC manufacture products are low cost as compared to other firms. 4 2 2 2 1

latest technology is being used in HMC. 0 3 4 4 0

HMC has a good benchmark for other relevant firms. 1 4 5 0 1

HMC is meeting all customer requirements. 3 5 3 0 0

Is HMC fulfilling ISO standards? 2 2 1 4 2

19 37 29 18 7

Importance Performance Matrix

IMPORTANCE

HIGHHMC 

LOW

   

 LOW HIGH

PERFORMANCE

Total Value=

11x (1+2+3+4+5+6+7+8+9+10)x5=3025

Total obtained=2071

Our Target Value =3

On scale 5=

Cost per Month

Labor cost 104,000 Rs 36.62%

Electricity 150,000 Rs 89.70%

Maintenance 20,000 Rs 96.57%

Others 10,000 Rs 100.00%

Total 284,000 Rsele

ctricit

y

labor

cost

mainten

ance

others

020000400006000080000

100000120000140000160000

0.00%

20.00%

40.00%

60.00%

80.00%

100.00%

120.00%

Cost per Month

Cost of Quality

Years External Cost

Internal Cost

Prevention Cost

Appraisal Cost

Total Quality Cost

1 4.5 2 1 0.55 8.05

2 4.5 2.5 1.2 0.55 8.75

3 4.25 3 1.2 0.54 8.99

4 3.75 3.5 1.3 0.53 9.08

5 2.75 3 1.6 0.52 7.87

6 2.5 2.7 1.5 0.51 7.21

7 2 2.5 1.25 0.5 6.25

Note: Each cost * 100,000 Rs

0 1 2 3 4 5 6 7 802468

10

Cost Of QualityExternal Cost Internal CostPrevention Cost Apperasial CostTotal Quality Cost

Years

Cost

Current Sigma Level

Number of units Nu 5,000Number of opportunities No 04

Number of defects Nd 85

Number of defective units Ndu 53

• 4250 defects per million opportunities.• This corresponds to the 3.2 sigma level.

ISO Standard

• ISO 9001 certified

• Authorized to use 4 ASME stamps U, U2, S & PP for equipment manufacturing

Conclusion

HMC management has to take some decisions.

• Buy new machinery

• Shift machines from manual to Computer Numerical Control

• Hire highly skilled people

• Follow Six sigma principles

Questions???