INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

1

2011 MDG-CGS PICTURES

BENUE STATE2ND STAGE

(GWER – WEST)

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

2

BN/GW/029

Primary Health Care Centre, Enger-Tongov, under construction

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

3

BN/GW/015

Construction of 1 block of 3 classrooms plus office in Ahula primary school , Ahula

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

4

BN/GW/018

Construction of 1 block of 3 classrooms at LGA Primary School, Atwerga, at roofing stage with wood nogging in place

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

5

BN/GW/016

Construction of 1 block of 3 classrooms at Mbaikyu primary school at roofing stage

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

6

BN/GW/031

PHC Orawe nearing completion

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

7

BN/GW/013

Construction of 1 block of 3 classrooms and office at Primary school Gbabi, at Lintel stage

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

8

2011MDG CGS

LOGO LOCAL GOVERNMENT

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

9

BN/LO/046

Completed 3 class room block at LGA primary School , Uwev

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

10

BN/LO/050

Hand-driven borehole at LGA pri. Sch. Uzer, completed and in use

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

11

Ambulances, procured, branded and in use

BN/LO/067 Ambulance Isaiah Tingir Memorial Clinic, Anyiin

BN/LO/066Ambulance at CHC Ugba

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

12

BN/LO/055A

Upgrading, LGHC Ayilamo, completed, awaiting branding and handover

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

13

BN/LO/0062-65Drugs and medical supplies procured and centrally stored at CHC Ugba pending the completion of the other health sentres

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

14

Drugs and hospital beds supplied 100%

BN/LO/062-65BN/LO/0062-65

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

15

BN/LO/069

Motorized borehole installed at NKST pri. Sch. Tyobam; completed , branded and in use

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

16

BN/LO/044

Block of 3 class rooms at LGA primary School Ashangu, completed and branded

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

17

2011 MDG-CGS ADO LOCAL GOVERNMENT

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

18

BN/AD/008Branded ambulance

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

19

BN/AD/006D

PHC at Ikpomolokpo in Ado LGA under renovation

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

20

BN/AD/007Procured drugs in storage (and in use )at the Local Government Central Store at Igumale in Ado LGA

INDEPENDENT PERFORMANCE MGT OF 2011 CGS - LG INTERVENTIONS

21

BN/AD/001

Branded exercise books kept in the Central Store at Igumale in Ado LGA