Wind Turbine Taskforce: Update and Lessons Learned from Zambia Test Deployment

Preview:

DESCRIPTION

Wind Turbine Taskforce: Update and Lessons Learned from Zambia Test Deployment. Engineers without Borders Chapter Meeting 21 September 2011 Seattle, WA Henry Louie * , Steve Szablya * , Vincent Van Acker ** *Seattle University, ** Alstom Grid. Chikuni Jesuit Mission. Goal. - PowerPoint PPT Presentation

Citation preview

Wind Turbine Taskforce: Update and Lessons Learned from Zambia Test Deployment

Engineers without Borders Chapter Meeting21 September 2011

Seattle, WAHenry Louie*, Steve Szablya*, Vincent Van Acker**

*Seattle University, **Alstom Grid

1

Dr. Henry Louie

2

Chikuni Jesuit Mission

Goal

Determine technical and economic feasibility of using wind power for rural electrification of impoverished communities

3

Funding Sources

• SU Global Grant: $9,524• SU Endowed Mission Fund: $6,000• Community Solutions Initiative: $3,000• Professionals without Boundaries: $3,000

Total Funding: $21,524

Dr. Henry Louie

4

Approach• Assemble volunteer team

Industry, academia, students • Start with existing Do-It-Yourself wind turbine

design• Build prototypes in Seattle• Assess feasibility and field test in rural

community• Redesign, refine and retest

5

Case Study: Zambia +12 million people

• 25% have electricity• per capital energy use: 3.3% of USA

+8 million live in rural communities 50% of rural population have electronic devices

• 4% have access to electricity

6

7

Case Study: Zambia

8

Dr. Henry Louie

9

N

N

NN

N

N S

S

S

S

S

S

12

Dr. Henry Louie

13

rotors

stator

hub

Dr. Henry Louie

14

Field Testing

• On-site in Chikuni, Zambia• Work with Jesuit Mission• Bring generator parts• Build tower and wind turbine blades

15

ZAMBIA

Dr. Henry Louie

17

Wind Speed Measurements• Near continuous

readings from 8am to 6pm for 2 days

• Did not record during evening Safety Generally low wind

speed• July/August: highest

wind speeds

18

anemometer

100

inch

es

Dr. Henry Louie

19

X Chikuni

Lusaka

Livingstone

230 miles

Dr. Henry Louie

20

X450 ft

Wind turbine location

Prevailing Wind

21

Wind Speed Measurements

22

0 5 10 15 20 250

2

4

6

8

10

12

14

instantaneous wind speed (mph)

occu

rrenc

esInstantaneous Values

Very highwind speeds!

Dr. Henry Louie

23

Dr. Henry Louie

24

100 inches

Dr. Henry Louie

25

Dr. Henry Louie

26

4 foot blades vs. 5 foot blades

Dr. Henry Louie

27

312

pAP C v

5 ft

4 ft

Dr. Henry Louie

28

Dr. Henry Louie

29

Generator

Blades

Hub

Dr. Henry Louie

30

Dr. Henry Louie

31

Generator assembly

Dr. Henry Louie

32

Dr. Henry Louie

33

Dr. Henry Louie

34

cows

Dr. Henry Louie

35

Dr. Henry Louie

36

Furled Position Facing into the Wind

Performance Data

• Idle Speed: 11 mph• Cut-in (battery charging): 15 mph• Max RPM tested: 330 • Maximum instantaneous power output: 75 W• Continuous power output: 5 W• Blades were wrong size for generator

37

The Market for Electricity• Cell Phone Charging:

With charger: 1000 Kwacha (US$ 0.20) With shop charger: 1500 Kwacha (US$ 0.30)

• Car Battery Charging: 2500 Kwacha (US$ 0.50) Charged overnight

• LI cellular phone battery capacity: 5 Wh Cost per Wh: US$ 0.04

38

Back-of-envelope calculation:• Village size: 1000 people• Percent with cellular phones: 15• Charge Frequency: 1/week• Charges per day: 21• Energy required: 105 Wh per day• Wind turbine capacity factor: 15%• Wind turbine size: 30 W• Income: US$4.20/day• Payback time on $500 investment: 120 days

39

700W Wind Turbine Costs• Pipe: $78• Wood: $13• Wire: $0.32/m x 250m = $80 • Magnets*: 24 x $15 = $360 • Resin*: $80 • Hardware*: $130• Rectifier*: $7• Battery: $125• Metal Parts*: $450• Electrical*: $20

40

* Price in the U.S.

Total: US $1343

Cost Considerations

• Does not include tools, labor• Price of rare earth magnets increasing and

volatile• Resins, magnets not easy to find• Too big, expensive• Micro loans generally are $500 or less

41

Lessons Learned• Very location dependent

Best energy source Prices/availability Expertise Economics Tower

• Most components can be found locally, prices are usually more expensive than in U.S.

• Feasibility of blade and tower construction

42

Future Plans• Design 100 W wind turbine• Engineer safe, secure tower solution• Work with local community• Promote as a business opportunity

43

0.00 5.00 10.00 15.00 20.00 25.00 30.00Time [ms]

-20.00

-15.00

-10.00

-5.00

0.00

5.00

10.00

15.00

20.00

Y1

[V]

0.00

25.00

50.00

75.00

100.00

125.00

Mov

ing1

.Pos

ition

[deg

]

Maxwell3DDesign2XY Plot 1 ANSOFT

Curve Info Y Axis

Moving1.Position Moving1.Position

InducedVoltage(A_Phase) Y1

InducedVoltage(B_Phase) Y1

InducedVoltage(C_Phase) Y1

Acknowledgements• Fr. Bert Otten, S.J.• Steve Szablya, PE• Carmen Cejudo• Dino Go• Ayesha Pirbhai• Josh Peavler• Karim Farraj• Byron Lynch

Dr. Henry Louie

44

Questions?45

Learn More

• Become involved! Email: vincent.van.acker@alstom.com Email: louieh@seattleu.edu Email: szablyst@seattleu.edu

• http://communitysolutionsinitiative.org/

46

S C I E N C E A N DE N G I N E E R I N G

Henry Louie, PhDAssistant Professor

Department of Electrical andComputer Engineering901 12th Avenue, Bannan 219P.O. Box 222000Seattle, WA 98122-1090www.seattleu.edu

Tel: (206) 398-4619Fax: (206) 296-5962louieh@seattleu.edu

COLLEGE OF

Videos• Raising The Turbine in Chikuni, Zambia(255.5M)• http://www.youtube.com/watch?v=6qOQk6gl7O8 • Wind Turbine and Electrical Setup in Chikuni, Zambia(27.1M)• http://www.youtube.com/watch?v=EO38Mo_WJdk • The Wind Turbine Spinning in Chikuni, Zambia(57.87M)• http://www.youtube.com/watch?v=OQ9U7uz8onk • Electric Braking During High Speed Operation in Chikuni, Zambia(59.45M)• http://www.youtube.com/watch?v=faBwLgE4NE0 • Alternate View of the Turbine Configuration from the bottom of Dam in

Chikuni, Zambia(53.72M)• http://www.youtube.com/watch?v=1qv4B7zy08w

Dr. Henry Louie

48