Merancas Classroom Building

Weekly Update May 10, 2019

Merancas Campus

Meetings & Milestones

• This Week:

• Begin work on Area C Concrete Footings

• Continue Underground Plumbing Work

• Begin Underground Electrical Work

• Subcontractor Meeting

• 05/07/19 at 10:00AM

• OACG Meeting

• 05/07/19 at 1:30PM

Meetings & Milestones

• Next Week:

• Continue Foundation Work

• Continue Underground Plumbing Work

• Continue Underground Electrical Work

• Subcontractor Meeting

• 05/14/19 at 10:00AM

• State Construction Meeting

• 05/14/19 at 1:30PM

Progress Photos

Underground

Plumbing in Area C

Progress Photos

Underground

Plumbing at

Elevator Pit

Progress Photos

Laying Out Electrical

Conduit in Area A

Progress Photos

Placed Footing

Reinforcement

Along Column

Line N

Progress Photos

Placed Concrete

Footing

Reinforcement at

Elevator Pit

Progress Photos

Placed Concrete

Footings Along

Column Line N

Progress Photos

Placed Concrete

Footings Along

Column Line 22

Conclusion of Weekly Update 05/10/2019