Wates CBE Learning. Build: Plant interactive. What is needed and when?. Building the new school will take place in stages Each slide gives you information about one stage Work out how long each stage will last Decide which machine is needed for which task - PowerPoint PPT Presentation
Citation preview
www.cbelearning.com
Wates CBE LearningBuild: Plant interactive
www.cbelearning.com
Building the new school will take place in stages
Each slide gives you information about one stage
Work out how long each stage will last
Decide which machine is needed for which task
Write down how long each one will be needed, and its weekly cost
What is needed and when?
www.cbelearning.com
Digging away uneven ground 2 weeksTHEN
Levelling the surface 1 weekTHEN
Creating a firm surface 1 weekPLUS
Removing waste materials During last 2 weeks
Dumper: £850 Grader: £950 Excavator: £1,250 Compactor: £900
1. Ground work
www.cbelearning.com
Digging trenches 2 weeksTHEN
Pouring concrete 1 week
Dumper: £850 Grader: £950 Excavator: £1,250 Mixer: £2,000
2. Foundations
www.cbelearning.com
3. Structure and roof
Lifting steel beams into place 2-6 weeks
Hydraulic crane: £6,000 Forklift: £850 Piledriver: £1,500
Hint: How could you make this 2 weeks and not 6?
www.cbelearning.com
Re-shape grounds 2 weeksPLUS
Remove waste During re-shaping
Dumper: £850 Grader: £950 Excavator: £1,250 Compactor: £900
4. Landscaping
www.cbelearning.com
Use your notes to make a simple spreadsheet
Work out:
- the total time for the build
- how much each piece of plant will cost
Use a simple formula to help you add up times and costs
Work out the time and costs