Wates CBE Learning. Build: Plant interactive. What is needed and when?.  Building the new school will take place in stages  Each slide gives you information about one stage  Work out how long each stage will last  Decide which machine is needed for which task - PowerPoint PPT Presentation

Citation preview

Page 1: Wates CBE Learning

www.cbelearning.com

Wates CBE LearningBuild: Plant interactive

Page 2: Wates CBE Learning

www.cbelearning.com

Building the new school will take place in stages

Each slide gives you information about one stage

Work out how long each stage will last

Decide which machine is needed for which task

Write down how long each one will be needed, and its weekly cost

What is needed and when?

Page 3: Wates CBE Learning

www.cbelearning.com

Digging away uneven ground 2 weeksTHEN

Levelling the surface 1 weekTHEN

Creating a firm surface 1 weekPLUS

Removing waste materials During last 2 weeks

Dumper: £850 Grader: £950 Excavator: £1,250 Compactor: £900

1. Ground work

Page 4: Wates CBE Learning

www.cbelearning.com

Digging trenches 2 weeksTHEN

Pouring concrete 1 week

Dumper: £850 Grader: £950 Excavator: £1,250 Mixer: £2,000

2. Foundations

Page 5: Wates CBE Learning

www.cbelearning.com

3. Structure and roof

Lifting steel beams into place 2-6 weeks

Hydraulic crane: £6,000 Forklift: £850 Piledriver: £1,500

Hint: How could you make this 2 weeks and not 6?

Page 6: Wates CBE Learning

www.cbelearning.com

Re-shape grounds 2 weeksPLUS

Remove waste During re-shaping

Dumper: £850 Grader: £950 Excavator: £1,250 Compactor: £900

4. Landscaping

Page 7: Wates CBE Learning

www.cbelearning.com

Use your notes to make a simple spreadsheet

Work out:

- the total time for the build

- how much each piece of plant will cost

Use a simple formula to help you add up times and costs

Work out the time and costs