MEMORANDUM

Date: May 18, 2009

To: Professor Amy Hornat-Kaval

From: Ben Dahl, President

Benny Leung, Chief Technology Officer 

Tony James, Chief Network Security Officer 

Subject: Security Manual Progress Report

1)  ACCOMPLISHED

a.  Project Proposal Information•  First topic (Penetration testing) rejected due to time and scope constraints

•  Second topic (Wireless Security) accepted and approved 

 b.  Audience Analysis Information

•  Address the target audience for the Security Manual

•  Select a medium for the best results

•  Vantage Point Computing chose Security Manual

•  Vantage Point Computing explored digital option

•  Decided client will need to have basic computer knowledge

•  Address the need for the Security Manual

c.  Progress Report Information

•  Document what has been created.

•  Document all revisions

•  Verify all issues have been resolved before presentation

•  Update Professor with progress of project

d.  Usability Testing of Manual

•  90% of test subjects found technical manual useful

•  Subjects found pictures helpful

•  20% of subjects wanted an index page

•  Subjects would like a Table of Contents

•  Information about specific settings was requested 

•  Page numbers need to be revised e.  Security Manual

•  First draft finished (5/05/2009)

•  First revision (5/07/2009)

•  Second revision after usability testing (5/14/09)

•  Final Security Manual (6/01/09)

•  Final presentation (6/02/09)

7/27/2019 Vantage Point Computing Progress Report

http://slidepdf.com/reader/full/vantage-point-computing-progress-report 2/2

 Vantage Point Computing  202 69th Street, Darien, IL, 60561

(630)887.8980 

Vantage Point Computing Progress Report Page 2

2)  PROJECTS AIM AND GOAL

f.  Proposal Revision

•  First project proposal rejected due to time constraint and scope.

•  Focused on a specific router for security set up. Too many routers are available, so we

chose the most common.

•  Our focus is to have the client set up their own secured wireless network.

g.  Audience Analysis

•  Minor changes to specify what was required of the client.

•  The target is to small business owners in their mid 20’s - 40’s.

h.  Usability Test

•  Positive feedback with Usability Testing. Most test subjects found manual complete and 

informative.

•  Our aim is to have clients with little computer knowledge set up their own secure

wireless network. 

•  Add index and reference page. 

•  Our goal is 100% approval from all test subjects. 

i.  Technical Manual

•  First draft of manual had too much white space.

•  Revised format to be smaller and more convenient. 

•  Second draft included pictures to make the manual easier to follow.

•  Final draft includes Table of Contents and Reference. 

•  Our goal is for the manual to be the only reference for router setup. 

3)  DEPLOYMENT DAY

 j.  Usability Test

•  More test subjects needed for unbiased results. 

•  All suggestions considered 

•  Usability Test completion (5/14/09)

k.  Security Manual

•  Added Table of Contents and Reference (5/15/09) 

• Revisions completed (5/31/09) l.  Completion Dates

•  Usability Test Information completed by two group members (5/14/09) 

•  Completed Index and reference page for Security Manual (5/15/09) 

•  Group meeting to review material for errors. 

•  All revisions completed (6/1/09) 

•  Final Security Manual and presentation (6/2/09) 

Recommended