VALORIZACION DE OBRA: PUENTE ANTAJARANI - PUNO
Citation preview
CRONOGRAMA VALORIZADO DE AVANCE DE OBRA - CONSTRUCCIÓN DEL PUENTE ANTAJARANI Y ACCESOS
DESCRIPCIÓN Apr-14 May-14 Jun-14PUENTETRABAJOS PRELIMINARES
MOVILIZACION Y DESMOVILIZACION DE EQUIPOS 40,243.11 36,348.61 40,243.11TRAZO Y REPLANTEO 656.92 735.76 814.59DESBROCE Y LIMPIEZA 2,398.19ACCESO A CANTERAS, FUENTES DE AGUA DME 2,013.85MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL 3,833.30 3,462.33 3,833.30CISTERNA DE 12M3 8,128.64ESTRIBOS
8,162.56ENCOFRADO Y DESENCOFRADO CARA NO VISTO 31,304.82ACERO DE REFUERZO f'y=4200 Kg/cm2 107,464.00 53,732.00ENCOFRADO Y DESENCOFRADO CARA VISTO 10,441.42 14,617.99CONCRETO f'c=210 kg/cm2 EN SECO 237,576.91 12,504.05RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO 19,058.16TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE 3,109.31PILARES
3,264.00ENCOFRADO Y DESENCOFRADO CARA NO VISTO 5,577.00ACERO DE REFUERZO f'y=4200 Kg/cm2 2,890.26 52,024.74ENCOFRADO Y DESENCOFRADO CARA VISTO 8,797.19 1,759.44CONCRETO f'c=210 kg/cm2 EN SECO 45,295.64 40,766.07RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO 8,464.06TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE 952.05VIGAS DE CONCRETO PREESFORZADO
FALSO PUENTE 114,698.06ENCOFRADO Y DESENCOFRADO CARA VISTO
ENCOFRADO Y DESENCOFRADO CARA NO VISTO
ACERO DE REFUERZO f'y=4200 Kg/cm2
ACERO PRETENSADO fo=320 TN
CONCRETO f'c=280 kg/cm2
LOSA DE CONCRETO
ENCOFRADO Y DESENCOFRADO CARA NO VISTO
ENCOFRADO Y DESENCOFRADO CARA VISTO
ACERO DE REFUERZO f'y=4200 Kg/cm2
CONCRETO f'c=280 kg/cm2
LOSA DE APROXIMACION
ENCOFRADO Y DESENCOFRADO CARA VISTO
ACERO DE REFUERZO f'y=4200 Kg/cm2
CONCRETO f'c=210 kg/cm2
SELLANTE PLASTICO
DETALLE DE TABLERO
JUNTA DE EXPANSIÓN
BRUÑAS ROMPA AGUA EN LOSA
VEREDA ALIGERADA
ACABADO ENDURECIDO EN VEREDA ALIGERADA
TUBOS DE DRENAJE
DISPOSITIVOS DE APOYO EN ESTRIBOS
EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN, EN SECO
EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN, EN SECO
CONSORCIO RMG
DISPOSITIVOS DE APOYO EN PILARES 9,368.56TOPES LATERALES EN ESTRIBO Y PILARES 2,954.80TOPES LATERALES EN VIGAS
BARANDAS METALICAS INCLUYE PINTADO
RIEGO DE LIGA
CARPETA ASFALTICA EN FRIO
COSNTRUCCION DE LSO ACCESOS
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
DESBROCE Y LIMPIEZA
MOVIMIENTO DE TIERRAS
EXCAVACION EN EXPLANACIONES EN MATERIAL COMUN
CONFORMACION DE TERRAPLENES
BANQUETAS PARA RELLENOS
TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE
PAVIMENTOS
PERFILADO Y COMPACTADO DE SUBRASANTE
AFIRMADO
CUNETAS REVESTIDAS
OBRAS DE ARTE Y DRENAJE
ALCANTARILLA D24" KM 28+430
EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN SECO
ENCOFRADO Y DESENCOFRADO CARA NO VISTO
ENCOFRADO Y DESENCOFRADO CARA VISTO
TUBERIA CORRUGADO DE 24"
CONCRETO CICLOPEO f'c= 175 kg/cm2 +30% de PM
RELLENO DE ESTRUCTURAS EN MATERIAL COMUN EN SECO
EMBOQUILLADO DE PIEDRA E=0.15M
TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE
TUBERIA CR DE 12" KM 28+583
ALC. CR B=0.4 KM 28+294
EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN SECO
ENCOFRADO Y DESENCOFRADO CARA NO VISTO
ENCOFRADO Y DESENCOFRADO CARA VISTO
ACERO DE REFUERZO f'y=4200 Kg/cm2
CONCRETO f'c=175 kg/cm2
EMBOQUILLADO DE PIEDRA E=0.15M
TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE
SEÑALIZACION
SEÑALES PREVENTIVAS (0.75M x 0.75M)
SEÑALES INFORMATIVAS
MARCAS EN EL PAVIMENTO
ESTRUCTURA DE SOPORTE
BARRERA DE SEGURIDAD METALICA P3-BORDE LATERAL
SEÑALES REGLAMENTARIAS
CONSTRUCCION E LAS DEFENZAS RIBEREÑAS
ORBRAS DE PROTECCION
LIMPIEZA Y RECONFORMACION DE CAUCE 50,400.92 61,357.64 2,191.3436,824.8310,217.15
ENROCADO 167,321.66RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO 79,251.72RELLENO DE ESTRUCTURAS CON MATERIAL DE PRESTAMO
TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE
OBRAS D MITIGACION E IMPACTO AMBIENTAL
PROGRAMA DE MONITOREO AMBIENTAL
MONITOREO DE LA CALIDAD DEL AGUA 492.45 444.79 492.45
EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN BAJO AGUAEXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN EN SECO
MONITOREO DE CALIDAD DEL AIRE 492.45 444.79 492.45MONITOREO DE RUIDOS 239.40 216.23 239.40PROGRAMA DE ABANDONO DE OBRA
SUBPROGRAMA DE MANEJO DE INSTALACIONES AUXILIARES
RETIRO DEL TOP SOIL
REACONDICIONAMIENTO DE MATERIAL EXCEDENTE
REACONDICIONAMIENTO DE CANTERA
REACONDICIONAMIENTO DE PLANTA CONCRETERA
REACONDICIONAMIENTO DELA REA DE CAMPAMENTO
REACONDICIONAMIENTO DE PATIO DE MAQUINAS
REFORESTACION DEL DME
REFORESTACION AMBAS MARGENES DEL RIO
COSTO DIRECTO 286,800.48 508,016.87 553,797.12
GASTOS GENERALES VARIABLES (21.3622001440266%) 61,266.89 108,523.58 118,303.25
GASTOS GENERALES FIJOS (2.83211697125451%) 8,122.53 14,387.63 15,684.18
UTILIDAD (10%) 28,680.05 50,801.69 55,379.71
SUBTOTAL 384,869.95 681,729.77 743,164.26
IMPUESTO (IGV 18%) 69,276.59 122,711.36 133,769.57
TOTAL PRESUPUESTO DE OBRA (S/.) 454,146.54 804,441.13 876,933.83
AVANCE MENSUAL 6.45% 11.42% 12.45%
AVANCE ACUMULADO 6.45% 17.86% 30.31%
5.16% 14.29% 24.25%
SUB PROGRAMA DE COMPENSACION POR USO DE INSTALACIONES AUXILIARES
CRONOGRAMA VALORIZADO DE AVANCE DE OBRA - CONSTRUCCIÓN DEL PUENTE ANTAJARANI Y ACCESOS
Jul-14 Aug-14 set-14 Oct-14 Nov-14 TOTAL
38,944.94 40,243.11 38,944.94 40,243.13 27,261.46 302,472.41788.31 131.38 3,126.96
2,398.192,013.85
3,709.64 3,833.30 3,709.63 3,833.30 2,349.44 28,564.248,128.64
8,162.5631,304.82
161,196.0025,059.41
250,080.9619,058.16
3,109.31
3,264.005,577.00
54,915.0010,556.6386,061.71
8,464.06952.05
5,213.55 119,911.6138,074.54 38,074.5452,097.36 52,097.3660,669.00 60,669.00
141,772.80 354,432.00 496,204.8070,482.42 17,620.61 88,103.03
16,240.22 20,300.28 36,540.5017,272.24 58,293.80 75,566.04
11,453.49 85,901.17 37,223.84 134,578.50164,240.62 164,240.62
1,413.44 1,413.448,746.50 8,746.50
12,617.28 12,617.281,066.75 1,066.75
4,363.49 4,363.49398.53 1,345.03 1,743.56
11,993.80 17,990.70 29,984.504,124.12 4,124.12
4,271.76 4,271.765,664.56 5,664.56
9,368.562,954.80
3,445.36 3,445.36109,217.36 109,217.36
4,396.39 4,396.3925,985.23 25,985.23
2,629.07 7,170.20 6,094.67 15,893.941,652.08 1,652.08
0.006,170.77 6,170.77
633,413.56 633,413.561,004.29 1,004.29
6,826.47 6,826.47
6,386.41 6,386.4138,091.11 38,091.1119,623.60 14,717.70 34,341.30
65.79 65.791,737.79 1,737.79
856.01 856.014,849.11 4,849.113,152.10 3,152.101,150.51 1,150.51
818.60 818.6078.13 78.13
2,139.36 2,139.36
505.34 505.342,141.57 2,141.57
369.26 369.26790.97 790.97
2,108.31 2,108.316,057.04 6,057.04
600.10 600.10
2,619.72 2,619.721,710.30 1,710.30
373.69 373.694,423.88 4,423.88
185,499.72 185,499.721,571.14 1,571.14
113,949.9036,824.8310,217.15
78,739.61 246,061.2779,251.72 81,893.45 18,492.07 258,888.96
128,684.67 39,164.90 167,849.5731,181.13 31,181.13
476.56 492.45 476.56 492.45 238.29 3,606.00
476.56 492.45 476.56 492.45 238.29 3,606.00231.68 239.40 231.68 239.40 115.85 1,753.04
10,440.00 10,440.0027,785.67 27,785.6716,893.33 33,786.67 50,680.00
408.00 408.001,740.00 1,740.00
348.00 348.00
3,078.49 3,078.494,155.96 4,155.96
604,839.68 1,309,677.96 323,495.22 603,343.62 259,817.01 4,449,787.96
129,207.06 279,776.03 69,105.70 128,887.47 55,502.63 950,572.61
17,129.77 37,091.61 9,161.76 17,087.40 7,358.32 126,023.20
60,483.97 130,967.80 32,349.52 60,334.36 25,981.70 444,978.80
811,660.48 1,757,513.39 434,112.20 809,652.85 348,659.66 5,971,362.57
146,098.89 316,352.41 78,140.20 145,737.51 62,758.74 1,074,845.26
957,759.36 2,073,865.81 512,252.40 955,390.36 411,418.40 7,046,207.83
13.59% 29.43% 7.27% 13.56% 5.84% 100.00%
43.90% 73.33% 80.60% 94.16% 100.00%
35.12% 58.67% 64.48% 75.33% 80.00% 0.00%
0.54
RESUMEN DE METRADOS - VALORIZACIÓN DE OBRA N° 03 - JUNIO 2,014
OBRA : CONSTRUCCIÓN DEL PUENTE ANTAJARANI Y ACCESOS
ENTIDAD : PROVIAS DEPARTAMENTAL
CONTRATISTA : C&C CONSUL EJEC. CONTRATISTAS GRALES SRL
N° DE CONTRATO : Nº 269-2013-MTC/21, 18 DE DICIEMBRE 2013
SUPERVISIÓN : CONSORCIO RMG
N° DE CONTRATO : Nº 101-2013-MTC/21, 10 DE MAYO 2013
UBICACIÓN : DEPARTAMENTO : PUNO PROVINCIA: HUANCANE DISTRITO: VILQUECHICO
ITEM DESCRIPCIÓN Und. Metrado
´01 CONSTRUCCIÓN DEL PUENTE01.01 TRABAJOS PRELIMINARES
01.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 0.17 0.06 0.7701.01.02 TRAZO Y REPLANTEO m2 1,212.00 1,212.00 0.00 0.0001.01.03 DESBROCE Y LIMPIEZA ha 0.90 0.90 0.00 0.0001.01.04 ACCESO A CANTERAS, FUENTES DE AGUA DME km 0.57 0.57 0.00 0.0001.01.05 mes 8.00 1.00 1.00 6.0001.01.06 CISTERNA DE 12M3 und 2.00 0.00 2.00 0.00
01.02 ESTRIBOS01.02.01 m2 1,275.40 754.36 472.91 48.1301.02.02 ENCOFRADO Y DESENCOFRADO CARA NO VISTO kg 420.99 0.00 0.00 420.9901.02.03 ACERO DE REFUERZO f'y=4200 Kg/cm2 m2 30,704.00 5,519.84 0.00 25,184.1601.02.04 ENCOFRADO Y DESENCOFRADO CARA VISTO m3 283.67 0.00 0.00 283.6701.02.05 CONCRETO f'c=210 kg/cm2 EN SECO m3 463.80 0.00 0.00 463.8001.02.06 m3 866.28 0.00 0.00 866.2801.02.07 m3 409.12 409.12 0.00 0.00
01.03 PILARES01.03.01 m3 510.00 484.50 25.50 0.0001.03.02 ENCOFRADO Y DESENCOFRADO CARA NO VISTO m2 75.00 0.00 37.50 37.5001.03.03 ACERO DE REFUERZO f'y=4200 Kg/cm2 kg 10,460.00 4,479.00 0.00 5,981.0001.03.04 ENCOFRADO Y DESENCOFRADO CARA VISTO m2 119.50 0.00 0.00 119.5001.03.05 CONCRETO f'c=210 kg/cm2 EN SECO m3 159.61 0.00 0.00 159.6101.03.06 m3 384.73 0.00 0.00 384.7301.03.07 m3 125.27 125.27 0.00 0.00
01.04 VIGAS DE CONCRETO PREESFORZADO01.04.01 FALSO PUENTE m 91.00 0.00 0.00 91.0001.04.02 ENCOFRADO Y DESENCOFRADO CARA VISTO m2 431.00 0.00 0.00 431.0001.04.03 ENCOFRADO Y DESENCOFRADO CARA NO VISTO m2 700.61 0.00 0.00 700.6101.04.04 ACERO DE REFUERZO f'y=4200 Kg/cm2 kg 11,556.00 0.00 0.00 11,556.0001.04.05 ACERO PRETENSADO fo=320 TN t/m 116,480.00 0.00 0.00 116,480.0001.04.06 CONCRETO f'c=280 kg/cm2 m3 131.80 0.00 0.00 131.80
01.05 LOSA DE CONCRETO01.05.01 ENCOFRADO Y DESENCOFRADO CARA NO VISTO m2 491.40 0.00 0.00 491.4001.05.02 ENCOFRADO Y DESENCOFRADO CARA VISTO m2 855.40 0.00 0.00 855.4001.05.03 ACERO DE REFUERZO f'y=4200 Kg/cm2 kg 25,634.00 0.00 0.00 25,634.0001.05.04 CONCRETO f'c=280 kg/cm2 m3 245.70 0.00 0.00 245.70
01.06 LOSA DE APROXIMACION01.06.01 ENCOFRADO Y DESENCOFRADO CARA VISTO m2 16.00 0.00 0.00 16.0001.06.02 ACERO DE REFUERZO f'y=4200 Kg/cm2 kg 1,666.00 0.00 0.00 1,666.0001.06.03 CONCRETO f'c=210 kg/cm2 m3 23.40 0.00 0.00 23.4001.06.04 SELLANTE PLASTICO m 14.40 0.00 0.00 14.40
01.07 DETALLE DE TABLERO01.07.01 JUNTA DE EXPANSIÓN m 14.40 0.00 0.00 14.4001.07.02 BRUÑAS ROMPA AGUA EN LOSA m 182.00 0.00 0.00 182.0001.07.03 VEREDA ALIGERADA m 182.00 0.00 0.00 182.0001.07.04 ACABADO ENDURECIDO EN VEREDA ALIGERADA m 182.00 0.00 0.00 182.0001.07.05 TUBOS DE DRENAJE und 36.00 0.00 0.00 36.0001.07.06 DISPOSITIVOS DE APOYO EN ESTRIBOS und 8.00 0.00 0.00 8.0001.07.07 DISPOSITIVOS DE APOYO EN PILARES und 8.00 0.00 0.00 8.0001.07.08 TOPES LATERALES EN ESTRIBO Y PILARES und 8.00 0.00 0.00 8.00
Metrado Anterior
Metrado Actual
Saldo de Metrado
MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL
EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN, EN SECO
RELLENO DE ESTRUCTURAS CON MATERIAL PROPIOTRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE
EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN, EN SECO
RELLENO DE ESTRUCTURAS CON MATERIAL PROPIOTRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE
Mz. "H" Lt. 21 URB. DEL INGENIERO I - CHICLAYOTEL. 074-208078 979907878 RPM #343586
E-mail : rmunoz_11@yahoo.es LAMBAYEQUE – PERU
CONSORCIO RMG
01.07.09 TOPES LATERALES EN VIGAS und 8.00 0.00 0.00 8.00
ITEM DESCRIPCIÓN Und. Metrado
01.07.10 BARANDAS METALICAS INCLUYE PINTADO m 202.00 0.00 0.00 202.0001.07.11 RIEGO DE LIGA m2 655.20 0.00 0.00 655.2001.07.12 CARPETA ASFALTICA EN FRIO m2 655.20 0.00 0.00 655.20
02 CONSTRUCCIÓN DE LOS ACCESOS02.01 TRABAJOS PRELIMINARES
02.01.01 TRAZO Y REPLANTEO m2 6,160.44 1,300.00 1,780.26 3,080.1802.01.02 DESBROCE Y LIMPIEZA ha 0.62 0.20 0.42 0.00
2.02 MOVIMIENTO DE TIERRAS02.02.01 m3 898.22 0.00 90.00 808.2202.02.02 CONFORMACION DE TERRAPLENES m3 15,505.84 0.00 1,111.02 14,394.8202.02.03 BANQUETAS PARA RELLENOS m3 78.83 0.00 0.00 78.8302.02.04 m3 898.22 0.00 90.00 808.22
02.03 PAVIMENTOS02.03.01 PERFILADO Y COMPACTADO DE SUBRASANTE m2 1,744.92 0.00 0.00 1,744.9202.03.02 AFIRMADO m3 869.66 0.00 0.00 869.6602.03.03 CUNETAS REVESTIDAS m 315.00 0.00 0.00 315.00
02.04 OBRAS DE ARTE Y DRENAJE02.04.01 ALCANTARILLA D24" KM 28+430
02.04.01.01 m3 10.28 0.00 0.00 10.2802.04.01.02 ENCOFRADO Y DESENCOFRADO CARA NO VISTO m2 23.37 0.00 0.00 23.3702.04.01.03 ENCOFRADO Y DESENCOFRADO CARA VISTO m2 9.69 0.00 0.00 9.6902.04.01.04 TUBERIA CORRUGADO DE 24" m 14.87 0.00 0.00 14.8702.04.01.05 m3 8.06 0.00 0.00 8.0602.04.01.06 m3 20.41 0.00 0.00 20.4102.04.01.07 EMBOQUILLADO DE PIEDRA E=0.15M m2 10.67 0.00 0.00 10.6702.04.01.08 m3 10.28 0.00 0.00 10.2802.04.01.09 TUBERIA CR DE 12" KM 28+583 m 24.00 0.00 0.00 24.00
02.04.02 ALC. CR B=0.4 KM 28+29402.04.02.01 m3 78.96 0.00 0.00 78.9602.04.02.02 ENCOFRADO Y DESENCOFRADO CARA NO VISTO m2 28.80 0.00 0.00 28.8002.04.02.03 ENCOFRADO Y DESENCOFRADO CARA VISTO m2 4.18 0.00 0.00 4.1802.04.02.04 ACERO DE REFUERZO f'y=4200 Kg/cm2 kg 150.66 0.00 0.00 150.6602.04.02.05 CONCRETO f'c=175 kg/cm2 m3 4.18 0.00 0.00 4.1802.04.02.06 EMBOQUILLADO DE PIEDRA E=0.15M m2 78.95 0.00 0.00 78.9502.04.02.07 m3 78.96 0.00 0.00 78.96
02.05 SEÑALIZACION02.05.01 SEÑALES PREVENTIVAS (0.75M x 0.75M) und 4.00 0.00 0.00 4.0002.05.02 SEÑALES INFORMATIVAS und 2.00 0.00 0.00 2.0002.05.03 MARCAS EN EL PAVIMENTO m2 24.25 0.00 0.00 24.2502.05.04 ESTRUCTURA DE SOPORTE und 2.00 0.00 0.00 2.0002.05.05 m 567.00 0.00 0.00 567.0002.05.06 SEÑALES REGLAMENTARIAS und 2.00 0.00 0.00 2.00
03 CONSTRUCCIÓN E LAS DEFENSAS RIBEREÑAS03.01 ORBRAS DE PROTECCION
03.01.01 LIMPIEZA Y RECONFORMACION DE CAUCE m3 15,870.46 14,663.75 0.00 1,206.7103.01.02 m3 3,191.06 0.00 0.00 3,191.0603.01.03 m3 1,596.43 0.00 0.00 1,596.4303.01.04 ENROCADO m3 2,026.53 0.00 0.00 2,026.5303.01.05 m3 11,767.68 10,610.68 0.00 1,157.0003.01.06 m3 2,977.64 2,115.00 0.00 862.6403.01.07 m3 4,102.78 3,052.07 0.00 1,050.71
04 OBRAS DE MITIGACIÓN E IMPACTO AMBIENTAL04.01 PROGRAMA DE MONITOREO AMBIENTAL
04.01.01 MONITOREO DE LA CALIDAD DEL AGUA und 2.00 0.00 0.00 2.0004.01.02 MONITOREO DE CALIDAD DEL AIRE und 2.00 0.00 0.00 2.0004.01.03 MONITOREO DE RUIDOS und 8.00 0.00 0.00 8.00
04.02 PROGRAMA DE ABANDONO DE OBRA04.02.01
04.02.01.01 RETIRO DEL TOP SOIL m2 6,000.00 0.00 0.00 6,000.0004.02.01.02 m3 5,624.63 5,443.80 0.00 180.8304.02.01.03 REACONDICIONAMIENTO DE CANTERA m2 14,000.00 0.00 0.00 14,000.0004.02.01.04 m2 150.00 0.00 0.00 150.0004.02.01.05 m2 1,000.00 0.00 0.00 1,000.0004.02.01.06 m2 200.00 0.00 0.00 200.00
04.02.02 0.00
Metrado Anterior
Metrado Actual
Saldo de Metrado
EXCAVACION EN EXPLANACIONES EN MATERIAL COMUN
TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE
EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN SECO
CONCRETO CICLOPEO f'c= 175 kg/cm2 +30% de PM
RELLENO DE ESTRUCTURAS EN MATERIAL COMUN EN SECO
TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE
EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN SECO
TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE
BARRERA DE SEGURIDAD METALICA P3-BORDE LATERAL
EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN BAJO AGUAEXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN EN SECO
RELLENO DE ESTRUCTURAS CON MATERIAL PROPIORELLENO DE ESTRUCTURAS CON MATERIAL DE PRESTAMOTRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE
SUBPROGRAMA DE MANEJO DE INSTALACIONES AUXILIARES
REACONDICIONAMIENTO DE MATERIAL EXCEDENTE
REACONDICIONAMIENTO DE PLANTA CONCRETERAREACONDICIONAMIENTO DELA REA DE CAMPAMENTOREACONDICIONAMIENTO DE PATIO DE MAQUINAS
SUB PROGRAMA DE COMP. POR USO DE INST. AUX.
04.02.02.01 REFORESTACION DEL DME ha 0.60 0.00 0.00 0.6004.02.02.02 REFORESTACION AMBAS MARGENES DEL RIO ha 0.81 0.00 0.00 0.81
OBRA : CONSTRUCCIÓN DEL PUENTE ANTAJARANI Y ACCESOS
CLIENTE PROVIAS DEPARTAMENTAL
CONTRATISTAC&C CONSUL EJEC. CONTRATISTAS GRALES SRL
CONTRATO N° 269-2013-MTC/21, del 18 de diciembre del 2013
SUPERVISION RMG INGENIEROS
CONTRATO N° 101-2013-MTC/21, del 10 de mayo del 2013
UBICACIÓN PUNO - HUANCANE - VILQUECHICO
PLANILLA DE VALORIZACIÓN DE OBRA PRINCIPAL Nº 03 - AL 30 DE JUNIO DEL 2,014
ITEM DESCRIPCION Und. Metrado P.U S/. Parcial S/.ACUMULADO ANTERIOR VALORIZACION ACTUAL - JUNIO 2014 ACUMULADO ACTUAL SALDO
METRADO IMPORTE % AVANCE METRADO IMPORTE %AVANCE METRADO IMPORTE %AVANCE METRADO IMPORTE %AVANCE
´01 CONSTRUCCION DEL PUENTE
01.01 TRABAJOS PRELIMINARES 346,704.29 62,529.84 18.04% 29,847.51 8.61% 92,377.35 26.64% 254,326.94 73.36%
01.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 302,472.41 302,472.41 0.17 51,420.31 17.00% 0.060 18,148.34 6.00% 0.230 69,568.65 23.00% 0.77 232,903.76 77.00%
01.01.02 TRAZO Y REPLANTEO m2 1,212.00 2.58 3,126.96 1,212.00 3,126.96 100.00% 0.00 0.00 0.00% 1,212.00 3,126.96 100.00% 0.00 0.00 0.00%
01.01.03 DESBROCE Y LIMPIEZA ha 0.90 2,664.65 2,398.19 0.90 2,398.19 100.00% 0.00 0.00 0.00% 0.90 2,398.19 100.00% 0.00 0.00 0.00%
01.01.04 ACCESO A CANTERAS, FUENTES DE AGUA DME km 0.57 3,533.07 2,013.85 0.57 2,013.85 100.00% 0.00 0.00 0.00% 0.57 2,013.85 100.00% 0.00 0.00 0.00%
01.01.05 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL mes 8.00 3,570.53 28,564.24 1.00 3,570.53 12.50% 1.00 3,570.53 12.50% 2.00 7,141.06 25.00% 6.00 21,423.18 75.00%
01.01.06 CISTERNA DE 12M3 und 2.00 4,064.32 8,128.64 0.00 0.00 0.00% 2.00 8,128.64 100.00% 2.00 8,128.64 100.00% 0.00 0.00 0.00%
01.02 ESTRIBOS 497,971.22 36,916.37 7.41% 3,026.62 0.61% 39,943.00 8.02% 458,028.22 91.98%
01.02.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN, EN SECO m2 1,275.40 6.40 8,162.56 754.36 4,827.90 59.15% 472.91 3,026.62 37.08% 1,227.27 7,854.53 96.23% 48.13 308.03 3.77%
01.02.02 ENCOFRADO Y DESENCOFRADO CARA NO VISTO kg 420.99 74.36 31,304.82 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 420.99 31,304.82 100.00%
01.02.03 ACERO DE REFUERZO f'y=4200 Kg/cm2 m2 30,704.00 5.25 161,196.00 5,519.84 28,979.16 17.98% 0.00 0.00 0.00% 5,519.84 28,979.16 17.98% 25,184.16 132,216.84 82.02%
01.02.04 ENCOFRADO Y DESENCOFRADO CARA VISTO m3 283.67 88.34 25,059.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 283.67 25,059.41 100.00%
01.02.05 CONCRETO f'c=210 kg/cm2 EN SECO m3 463.80 539.20 250,080.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 463.80 250,080.96 100.00%
01.02.06 RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO m3 866.28 22.00 19,058.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 866.28 19,058.16 100.00%
01.02.07 TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m3 409.12 7.60 3,109.31 409.12 3,109.31 100.00% 0.00 0.00 0.00% 409.12 3,109.31 100.00% 0.00 0.00 0.00%
01.03 PILARES 169,790.45 27,567.60 16.24% 2,951.70 1.74% 30,519.30 17.97% 139,271.15 82.03%
01.03.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN, EN SECO m3 510.00 6.40 3,264.00 484.50 3,100.80 95.00% 25.50 163.20 5.00% 510.00 3,264.00 100.00% 0.00 0.00 0.00%
01.03.02 ENCOFRADO Y DESENCOFRADO CARA NO VISTO m2 75.00 74.36 5,577.00 0.00 0.00 0.00% 37.50 2,788.50 50.00% 37.50 2,788.50 50.00% 37.50 2,788.50 50.00%
01.03.03 ACERO DE REFUERZO f'y=4200 Kg/cm2 kg 10,460.00 5.25 54,915.00 4,479.00 23,514.75 42.82% 0.00 0.00 0.00% 4,479.00 23,514.75 42.82% 5,981.00 31,400.25 57.18%
01.03.04 ENCOFRADO Y DESENCOFRADO CARA VISTO m2 119.50 88.34 10,556.63 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 119.50 10,556.63 100.00%
01.03.05 CONCRETO f'c=210 kg/cm2 EN SECO m3 159.61 539.20 86,061.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 159.61 86,061.71 100.00%
01.03.06 RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO m3 384.73 22.00 8,464.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 384.73 8,464.06 100.00%
01.03.07 TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m3 125.27 7.60 952.05 125.27 952.05 100.00% 0.00 0.00 0.00% 125.27 952.05 100.00% 0.00 0.00 0.00%
01.04 VIGAS DE CONCRETO PREESFORZADO 855,060.34 0.00 0.00% 0.00 0.00% 0.00 0.00% 855,060.34 100.00%
01.04.01 FALSO PUENTE m 91.00 1,317.71 119,911.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.00 119,911.61 100.00%
01.04.02 ENCOFRADO Y DESENCOFRADO CARA VISTO m2 431.00 88.34 38,074.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 431.00 38,074.54 100.00%
01.04.03 ENCOFRADO Y DESENCOFRADO CARA NO VISTO m2 700.61 74.36 52,097.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 700.61 52,097.36 100.00%
01.04.04 ACERO DE REFUERZO f'y=4200 Kg/cm2 kg 11,556.00 5.25 60,669.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11,556.00 60,669.00 100.00%
01.04.05 ACERO PRETENSADO fo=320 TN t/m 116,480.00 4.26 496,204.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 116,480.00 496,204.80 100.00%
01.04.06 CONCRETO f'c=280 kg/cm2 m3 131.80 668.46 88,103.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 131.80 88,103.03 100.00%
01.05 LOSA DE CONCRETO 410,925.66 0.00 0.00% 0.00 0.00% 0.00 0.00% 410,925.66 100.00%
01.05.01 ENCOFRADO Y DESENCOFRADO CARA NO VISTO m2 491.40 74.36 36,540.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 491.40 36,540.50 100.00%
01.05.02 ENCOFRADO Y DESENCOFRADO CARA VISTO m2 855.40 88.34 75,566.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 855.40 75,566.04 100.00%
01.05.03 ACERO DE REFUERZO f'y=4200 Kg/cm2 kg 25,634.00 5.25 134,578.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 25,634.00 134,578.50 100.00%
01.05.04 CONCRETO f'c=280 kg/cm2 m3 245.70 668.46 164,240.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 245.70 164,240.62 100.00%
01.06 LOSA DE APROXIMACION 23,843.97 0.00 0.00% 0.00 0.00% 0.00 0.00% 23,843.97 100.00%
01.06.01 ENCOFRADO Y DESENCOFRADO CARA VISTO m2 16.00 88.34 1,413.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.00 1,413.44 100.00%
01.06.02 ACERO DE REFUERZO f'y=4200 Kg/cm2 kg 1,666.00 5.25 8,746.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,666.00 8,746.50 100.00%
01.06.03 CONCRETO f'c=210 kg/cm2 m3 23.40 539.20 12,617.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.40 12,617.28 100.00%
01.06.04 SELLANTE PLASTICO m 14.40 74.08 1,066.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.40 1,066.75 100.00%
01.07 DETALLE DE TABLERO 205,519.69 0.00 0.00% 0.00 0.00% 0.00 0.00% 205,519.69 100.00%
01.07.01 JUNTA DE EXPANSIÓN m 14.40 303.02 4,363.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.40 4,363.49 100.00%
01.07.02 BRUÑAS ROMPA AGUA EN LOSA m 182.00 9.58 1,743.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 182.00 1,743.56 100.00%
01.07.03 VEREDA ALIGERADA m 182.00 164.75 29,984.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 182.00 29,984.50 100.00%
01.07.04 ACABADO ENDURECIDO EN VEREDA ALIGERADA m 182.00 22.66 4,124.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 182.00 4,124.12 100.00%
01.07.05 TUBOS DE DRENAJE und 36.00 118.66 4,271.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.00 4,271.76 100.00%
01.07.06 DISPOSITIVOS DE APOYO EN ESTRIBOS und 8.00 708.07 5,664.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 5,664.56 100.00%
01.07.07 DISPOSITIVOS DE APOYO EN PILARES und 8.00 1,171.07 9,368.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 9,368.56 100.00%
01.07.08 TOPES LATERALES EN ESTRIBO Y PILARES und 8.00 369.35 2,954.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 2,954.80 100.00%
01.07.09 TOPES LATERALES EN VIGAS und 8.00 430.67 3,445.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 3,445.36 100.00%
01.07.10 BARANDAS METALICAS INCLUYE PINTADO m 202.00 540.68 109,217.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 202.00 109,217.36 100.00%
01.07.11 RIEGO DE LIGA m2 655.20 6.71 4,396.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 655.20 4,396.39 100.00%
01.07.12 CARPETA ASFALTICA EN FRIO m2 655.20 39.66 25,985.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 655.20 25,985.23 100.00%
02 CONSTRUCCION DE LOS ACCESOS 771,199.92 3,886.93 0.50% 52,399.69 6.79% 56,286.62 7.30% 714,913.30 92.70%
02.01 TRABAJOS PRELIMINARES 17,546.02 3,886.93 22.15% 5,712.22 32.56% 9,599.15 54.71% 7,946.86 45.29%
CONSORCIO RMG
Mz. "H" Lt. 21 URB. DEL INGENIERO I - CHICLAYOTEL. 074208078 979907878 RPM # 343586
E-mail : rmunoz_11@yahoo.es LAMBAYEQUE – PERU
02.01.01 TRAZO Y REPLANTEO m2 6,160.44 2.58 15,893.94 1,300.00 3,354.00 21.10% 1,780.26 4,593.07 28.90% 3,080.26 7,947.07 50.00% 3,080.18 7,946.86 50.00%
02.01.02 DESBROCE Y LIMPIEZA ha 0.62 2,664.65 1,652.08 0.20 532.93 32.26% 0.42 1,119.15 67.74% 0.62 1,652.08 100.00% 0.00 0.00 0.00%
ITEM DESCRIPCION Und. Metrado P.U S/. Parcial S/.ACUMULADO ANTERIOR VALORIZACION ACTUAL - JUNIO 2014 ACUMULADO ACTUAL SALDO
METRADO IMPORTE % AVANCE METRADO IMPORTE %AVANCE METRADO IMPORTE %AVANCE METRADO IMPORTE %AVANCE
2.02 MOVIMIENTO DE TIERRAS 647,415.09 0.00 0.00% 46,687.47 7.21% 46,687.47 7.21% 600,727.63 92.79%
02.02.01 EXCAVACION EN EXPLANACIONES EN MATERIAL COMUN m3 898.22 6.87 6,170.77 0.00 0.00 0.00% 90.00 618.30 10.02% 90.00 618.30 10.02% 808.22 5,552.47 89.98%
02.02.02 CONFORMACION DE TERRAPLENES m3 15,505.84 40.85 633,413.56 0.00 0.00 0.00% 1,111.02 45,385.17 7.17% 1,111.02 45,385.17 7.17% 14,394.82 588,028.40 92.83%
02.02.03 BANQUETAS PARA RELLENOS m3 78.83 12.74 1,004.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 78.83 1,004.29 100.00%
02.02.04 TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m3 898.22 7.60 6,826.47 0.00 0.00 0.00% 90.00 684.00 10.02% 90.00 684.00 10.02% 808.22 6,142.47 89.98%
02.03 PAVIMENTOS 78,818.82 0.00 0.00% 0.00 0.00% 0.00 0.00% 78,818.82 100.00%
02.03.01 PERFILADO Y COMPACTADO DE SUBRASANTE m2 1,744.92 3.66 6,386.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,744.92 6,386.41 100.00%
02.03.02 AFIRMADO m3 869.66 43.80 38,091.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 869.66 38,091.11 100.00%
02.03.03 CUNETAS REVESTIDAS m 315.00 109.02 34,341.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 315.00 34,341.30 100.00%
02.04 OBRAS DE ARTE Y DRENAJE 27,419.99 0.00 0.00% 0.00 0.00% 0.00 0.00% 27,419.99 100.00%
02.04.01 ALCANTARILLA TMC D24" KM 28+430 14,847.40 0.00 0.00% 0.00 0.00% 0.00 0.00% 14,847.40 100.00%
02.04.01.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN SECO m3 10.28 6.40 65.79 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.28 65.79 100.00%
02.04.01.02 ENCOFRADO Y DESENCOFRADO CARA NO VISTO m2 23.37 74.36 1,737.79 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.37 1,737.79 100.00%
02.04.01.03 ENCOFRADO Y DESENCOFRADO CARA VISTO m2 9.69 88.34 856.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.69 856.01 100.00%
02.04.01.04 TUBERIA CORRUGADO DE 24" m 14.87 326.10 4,849.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.87 4,849.11 100.00%
02.04.01.05 CONCRETO CICLOPEO f'c= 175 kg/cm2 +30% de PM m3 8.06 391.08 3,152.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.06 3,152.10 100.00%
02.04.01.06 RELLENO DE ESTRUCTURAS EN MATERIAL COMUN EN SECO m3 20.41 56.37 1,150.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.41 1,150.51 100.00%
02.04.01.07 EMBOQUILLADO DE PIEDRA E=0.15M m2 10.67 76.72 818.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.67 818.60 100.00%
02.04.01.08 TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m3 10.28 7.60 78.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.28 78.13 100.00%
02.04.01.09 TUBERIA CR DE 12" KM 28+583 m 24.00 89.14 2,139.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.00 2,139.36 100.00%
02.04.02 ALC. CR B=0.4 KM 28+294 12,572.59 0.00 0.00% 0.00 0.00% 0.00 0.00% 12,572.59 100.00%
02.04.02.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN SECO m3 78.96 6.40 505.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 78.96 505.34 100.00%
02.04.02.02 ENCOFRADO Y DESENCOFRADO CARA NO VISTO m2 28.80 74.36 2,141.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 28.80 2,141.57 100.00%
02.04.02.03 ENCOFRADO Y DESENCOFRADO CARA VISTO m2 4.18 88.34 369.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.18 369.26 100.00%
02.04.02.04 ACERO DE REFUERZO f'y=4200 Kg/cm2 kg 150.66 5.25 790.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 150.66 790.97 100.00%
02.04.02.05 CONCRETO f'c=175 kg/cm2 m3 4.18 504.38 2,108.31 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.18 2,108.31 100.00%
02.04.02.06 EMBOQUILLADO DE PIEDRA E=0.15M m2 78.95 76.72 6,057.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 78.95 6,057.04 100.00%
02.04.02.07 TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m3 78.96 7.60 600.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 78.96 600.10 100.00%
02.05 SEÑALIZACION 196,198.45 0.00 0.00% 0.00 0.00% 0.00 0.00% 196,198.45 100.00%
02.05.01 SEÑALES PREVENTIVAS (0.75M x 0.75M) und 4.00 654.93 2,619.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 2,619.72 100.00%
02.05.02 SEÑALES INFORMATIVAS und 2.00 855.15 1,710.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 1,710.30 100.00%
02.05.03 MARCAS EN EL PAVIMENTO m2 24.25 15.41 373.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.25 373.69 100.00%
02.05.04 ESTRUCTURA DE SOPORTE und 2.00 2,211.94 4,423.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 4,423.88 100.00%
02.05.05 BARRERA DE SEGURIDAD METALICA P3-BORDE LATERAL m 567.00 327.16 185,499.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 567.00 185,499.72 100.00%
02.05.06 SEÑALES REGLAMENTARIAS und 2.00 785.57 1,571.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 1,571.14 100.00%
03 CONSTRUCCION DE DEFENZAS RIBEREÑAS 864,972.81 481,138.97 55.62% 0.00 0.00% 481,138.97 55.62% 383,833.85 44.38%
03.01 OBRAS DE PROTECCION 864,972.81 481,138.97 55.62% 0.00 0.00% 481,138.97 55.62% 383,833.85 44.38%
03.01.01 LIMPIEZA Y RECONFORMACION DE CAUCE m3 15,870.46 7.18 113,949.90 14,663.75 105,285.73 92.40% 0.00 0.00 0.00% 14,663.75 105,285.73 92.40% 1,206.71 8,664.18 7.60%
03.01.02 EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN BAJO AGUA m3 3,191.06 11.54 36,824.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,191.06 36,824.83 100.00%
03.01.03 EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN EN SECO m3 1,596.43 6.40 10,217.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,596.43 10,217.15 100.00%
03.01.04 ENROCADO m3 2,026.53 121.42 246,061.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,026.53 246,061.27 100.00%
03.01.05 RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO m3 11,767.68 22.00 258,888.96 10,610.68 233,434.96 90.17% 0.00 0.00 0.00% 10,610.68 233,434.96 90.17% 1,157.00 25,454.00 9.83%
03.01.06 RELLENO DE ESTRUCTURAS CON MATERIAL DE PRESTAMO m3 2,977.64 56.37 167,849.57 2,115.00 119,222.55 71.03% 0.00 0.00 0.00% 2,115.00 119,222.55 71.03% 862.64 48,627.02 28.97%
03.01.07 TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m3 4,102.78 7.60 31,181.13 3,052.07 23,195.73 74.39% 0.00 0.00 0.00% 3,052.07 23,195.73 74.39% 1,050.71 7,985.40 25.61%
04 OBRAS DE MITIGACION DE IMPACTO AMBIENTAL 107,601.16 26,892.37 24.99% 0.00 0.00% 26,892.37 24.99% 80,708.79 75.01%
04.01 PROGRAMA DE MONITOREO AMBIENTAL 8,965.04 0.00 0.00% 0.00 0.00% 0.00 0.00% 8,965.04 100.00%
04.01.01 MONITOREO DE LA CALIDAD DEL AGUA und 2.00 1,803.00 3,606.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 3,606.00 100.00%
04.01.02 MONITOREO DE CALIDAD DEL AIRE und 2.00 1,803.00 3,606.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 3,606.00 100.00%
04.01.03 MONITOREO DE RUIDOS und 8.00 219.13 1,753.04 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 1,753.04 100.00%
04.02 PROGRAMA DE ABANDONO DE OBRA 98,636.12 26,892.37 27.26% 0.00 0.00% 26,892.37 27.26% 71,743.75 72.74%
04.02.01 SUBPROGRAMA DE MANEJO DE INSTALACIONES AUXILIARES 91,401.67 26,892.37 29.42% 0.00 0.00% 26,892.37 29.42% 64,509.30 70.58%
04.02.01.01 RETIRO DEL TOP SOIL m2 6,000.00 1.74 10,440.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6,000.00 10,440.00 100.00%
04.02.01.02 REACONDICIONAMIENTO DE MATERIAL EXCEDENTE m3 5,624.63 4.94 27,785.67 5,443.80 26,892.37 96.79% 0.00 0.00 0.00% 5,443.80 26,892.37 96.79% 180.83 893.30 3.21%
04.02.01.03 REACONDICIONAMIENTO DE CANTERA m2 14,000.00 3.62 50,680.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14,000.00 50,680.00 100.00%
04.02.01.04 REACONDICIONAMIENTO DE PLANTA CONCRETERA m2 150.00 2.72 408.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 150.00 408.00 100.00%
04.02.01.05 REACONDICIONAMIENTO DELA REA DE CAMPAMENTO m2 1,000.00 1.74 1,740.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,000.00 1,740.00 100.00%
04.02.01.06 REACONDICIONAMIENTO DE PATIO DE MAQUINAS m2 200.00 1.74 348.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 200.00 348.00 100.00%
04.02.02 SUB PROGRAMA DE COMPENSACION POR USO DE INSTALACIONES AUXILIARES 7,234.45 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00% 7,234.45 100.00%
04.02.02.01 REFORESTACION DEL DME ha 0.60 5,130.82 3,078.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.60 3,078.49 100.00%
04.02.02.02 REFORESTACION AMBAS MARGENES DEL RIO ha 0.81 5,130.82 4,155.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.81 4,155.96 100.00%
TOTAL COSTO DIRECTO S/. 4,449,787.96 638,932.08
14.3
6%
88,225.52
1.98
%
727,157.61
16.3
4%
3,722,630.34
83.6
6%
GASTOS GENERALES VARIABLES 21.36220014% S/. 950,572.61 136,489.95 18,846.91 155,336.86 795,235.74
GASTOS GENERALES FIJOS 2.83211697% 126,023.20 18,095.30 2,498.65 20,593.95 105,429.25
UTILIDAD 10.00000000% S/. 444,978.80 63,893.21 8,822.55 72,715.76 372,263.03
SUB-TOTAL S/. 5,971,362.57 857,410.54 118,393.63 975,804.18 4,995,558.37
I.G.V : 18.00 % 18.0000000% S/. 1,074,845.26 154,333.90 21,310.85 175,644.75 899,200.51
TOTAL PRESUPUESTO S/. 7,046,207.83 1,011,744.44 139,704.48 1,151,448.93 5,894,758.88
document.xlsPOLINÓMICA
OBRA : CONSTRUCCIÓN DEL PUENTE ANTAJARANI Y ACCESOS
ENTIDAD : PROVIAS DEPARTAMENTAL
CONTRATISTA : C&C CONSUL EJEC. CONTRATISTAS GRALES SRL
N° DE CONTRATO : Nº 269-2013-MTC/21, 18 DE DICIEMBRE 2013
SUPERVISIÓN : CONSORCIO RMG
N° DE CONTRATO : Nº 101-2013-MTC/21, 10 DE MAYO 2013
UBICACIÓN : DEPARTAMENTO : PUNO PROVINCIA: HUANCANE DISTRITO: VILQUECHICO
FÓRMULA POLINÓMICA
FECHA PRESUPUESTO : Junio 2013
K = 0.170 * (Jr / Jo) + 0.125 * (CMr / CMo) + 0.072 * (Ar / Ao) + 0.125 * (Dr /Do) + 0.241 * (EQr / EQo) + 0.267 * (GGr / GGo)
MONOMIO FACTOR PORCENTAJE SÍMBOLO ÍNDICE DESCRIPCIÓN
1 0.170 100.000 J 47 MANO DE OBRA INCLUIDO LEYES SOCIALES
2 0.125 72.800 CM 21 CEMENTO PORTLAND TIPO I
27.200 43 MADERA NACIONAL PARA ENCOFOFRADO Y CARPINTERÍA
3 0.072 100.000 A 03 ACERO DE CONSTRUCCION CORRUGADO
4 0.125 100.000 D 30 DÓLAR (GENERAL PONDERADO)
5 0.241 100.000 EQ 49 MAQUINARIA Y EQUIPO IMPORTADO
6 0.267 100.000 GG 39 ÍNDICE GENERAL DE PRECIOS AL COSUMIDOR
CONSORCIO RMG
Mz. "H" Lt. 21 URB. DEL INGENIERO I - CHICLAYOTEL. 074208078 979907878 RPM # 343586
E-mail : rmunoz_11@yahoo.es LAMBAYEQUE – PERU
document.xlsFACTOR K
CÁLCULO DEL COEFICIENTE "K" DE REAJUSTE
FECHA PRESUPUESTO : Junio 2013
K = 0.170 * (Jr / Jo) + 0.125 * (CMr / CMo) + 0.072 * (Ar / Ao) + 0.125 * (Dr /Do) + 0.241 * (EQr / EQo) + 0.267 * (GGr / Ggo)
SÍMBOLO I.U. DESCRIPCION COEF.BASE
INDICES UNIFICADOS DE PRECIOS (I.U.P.)
ABR. 2,014 MAY. 2,014 JUN. 2,014 JUL. 2,014 AGO. 2,014 SEP. 2,014 OCT. 2,014 NOV. 2,014
J 47 MANO DE OBRA INC. LEYES SOCIALES 0.170 100.000% 471.44 498.10 498.10 498.10 0.00 0.00 0.00 0.00 0.00
0.170 0.180 0.180 0.180 0.000 0.000 0.000 0.000 0.000
21 CEMENTO PORTLAND TIPO I 0.125 72.800% 410.96 410.96 410.96 410.96 0.00 0.00 0.00 0.00 0.00
CM
43 MADERA NACIONAL P/ENCOFRADO Y CARP. 27.200% 856.32 870.17 876.04 872.59 0.00 0.00 0.00 0.00 0.00
0.125 0.126 0.126 0.126 0.000 0.000 0.000 0.000 0.000
A 3 ACERO DE CONSTRUCCION CORRUGADO 0.072 100.000% 463.77 477.82 470.04 473.03 0.00 0.00 0.00 0.00 0.00
0.072 0.074 0.073 0.073 0.000 0.000 0.000 0.000 0.000
D 30 DÓLAR GENERAL PONDERADO 0.125 100.000% 372.66 383.93 384.75 385.05 0.00 0.00 0.00 0.00 0.00
0.125 0.129 0.129 0.129 0.000 0.000 0.000 0.000 0.000
EQ 49 MAQUINARIA Y EQUIPO IMPORTADO 0.241 100.000% 243.07 249.75 248.50 248.06 0.00 0.00 0.00 0.00 0.00
0.241 0.248 0.246 0.246 0.000 0.000 0.000 0.000 0.000
GG 39 INDICE GENERAL DE PRECIOS CONSUMIDOR 0.267 100.000% 387.61 397.88 399.44 400.34 0.00 0.00 0.00 0.00 0.00
0.267 0.274 0.275 0.276 0.000 0.000 0.000 0.000 0.000
COEFICIENTE DE REAJUSTE ( K ) 1.000 1.031 1.029 1.030 0.000 0.000 0.000 0.000 0.000
INCIDENCIA ESPECÍFICA
CONSORCIO RMG
Mz. "H" Lt. 21 URB. DEL INGENIERO I - CHICLAYOTEL. 074208078 979907878 E-mail : rmunoz_11@yahoo.es
LAMBAYEQUE – PERU
document.xlsREAJUSTE
CÁLCULO DE REAJUSTE DE LA VALORIZACIÓN Nº 03 - JUNIO 2,014
OBRA : CONSTRUCCIÓN DEL PUENTE ANTAJARANI Y ACCESOS
CONTRATISTA : C&C CONSUL EJEC. CONTRATISTA GRALES SRL
PROPIETARIO : PROVIAS DEPARTAMENTAL - MTC
SUPERVISION : CONSORCIO RMG
CONTRATO Nº : 101-2013-MTC/21, de 10 de mayo del 2013
UBICACIÓN : PUNO - HUANCANE- VILQUECHICO
DESCRIPCIÓN VALORIZACIÓN MENSUAL (V) K R = V * (K - 1)
VALORIZACION N° 03 118,393.63 1.030 3,551.81
118,393.63 TOTAL REAJUSTE S/. 3,551.81
Dónde:
R = Reajuste del componente en S/. de la Valorización mensual.
V = Monto del componente en S/. de la valorización mensual.
K = Coeficiente de reajuste obtenido por la aplicación de la fórmula polinómica.
CONSORCIO RMG
Mz. "H" Lt. 21 URB. DEL INGENIERO I - CHICLAYOTEL. 074208078 979907878 E-mail : rmunoz_11@yahoo.es
LAMBAYEQUE – PERU
OBRA : CONSTRUCCION DEL PUENTE ANTAJARANI Y ACCESOS
CLIENTE : PROVIAS DEPARTAMENTAL - MTC
CONTRATISTA : C&C CONSUL EJEC. CONTRATISTA GRALES SRL
N° DE CONTRATO : 269-2013-MTC/21, del 18 de diciembre del 2013
SUPERVISIÓN : CONSORCIO RMG
N° DE CONTRATO : 101-2013-MTC/21, de 10 de mayo del 2013
UBICACIÓN : DEPARTAMENTO : PUNO PROVINCIA: HUANCANE DISTRITO: VILQUECHICO
1) REGULARIZACIÓN REAJUSTE DE LA VALORIZACIÓN Nº 01 - ABRIL 2,014
Rr = Vn * ( K - 1 ) - Rn
DONDE: Rr = Regularización del reajuste del componente en S/. de la Valorización anterior
Vn = Monto del componente en S/. de la valorización anterior.
K = Coeficiente de reajuste obtenida por la aplicación de la fórmula polinómica.
Rn = Reajuste del componente en S/. de la Valorización anterior.
Vn = 308,786.22K = 1.029
Rn = 9,572.37
Rr = -617.57
2) REGULARIZACIÓN REAJUSTE DE LA VALORIZACIÓN Nº 02 - MAYO 2,014
Rr = Vn * ( K - 1 ) - Rn
CONSORCIO RMG
Mz. "H" Lt. 21 URB. DEL INGENIERO I - CHICLAYOTEL. 074208078 979907878 E-mail : rmunoz_11@yahoo.es
LAMBAYEQUE – PERU
DONDE: Rr = Regularización del reajuste del componente en S/. de la Valorización anteriorVn = Monto del componente en S/. de la valorización anterior.K = Coeficiente de reajuste obtenida por la aplicación de la fórmula polinómica.Rn = Reajuste del componente en S/. de la Valorización anterior.
Vn = 548,624.33K = 1.030
Rn = 15,910.11
Rr = 548.62
OBRA : CONSTRUCCION DEL PUENTE ANTAJARANI Y ACCESOS
CLIENTE : PROVIAS DEPARTAMENTAL - MTC
CONTRATISTA : C&C CONSUL EJEC. CONTRATISTA GRALES SRL
N° DE CONTRATO : 269-2013-MTC/21, del 18 de diciembre del 2013
SUPERVISIÓN : CONSORCIO RMG
N° DE CONTRATO : 101-2013-MTC/21, de 10 de mayo del 2013
UBICACIÓN : DEPTO : PUNO PROV: HUANCANE DIST: VILQUECHICO
CONTROL DE REAJUSTES
VALORIZACIÓN FECHA
FACTOR REAJUSTE REAJUSTEREAJUSTE RECONOCIDO
K PROGRAMADO (1) x (K-1) EJECUTADO (2) x (K-1)
(1) (2) (3) PARCIAL ACUMULADO PARCIAL ACUMULADO PARCIAL ACUMULADO
01 Apr-14 384,869.95 308,786.22 1.029 11,161.23 11,161.23 8,954.80 8,954.80 8,954.80 8,954.80
02 May-14 681,729.77 548,624.33 1.030 20,451.89 31,613.12 16,458.73 25,413.53 16,458.73 25,413.53
03 Jun-14 743,164.26 118,393.63 1.030 22,294.93 53,908.05 3,551.81 28,965.34 3,551.81 28,965.34
04 Jul-14 811,660.48
05 Aug-14 1,757,513.39
06 Sep-14 434,112.20
07 Oct-14 809,652.85
08 Nov-14 348,659.66
Acumulado : 53,908.05 28,965.34 28,965.34
AVANCE PROGRAMADO
AVANCE EJECUTADO
CONSORCIO RMG
Mz. "H" Lt. 21 URB. DEL INGENIERO I - CHICLAYOTEL. 074208078 979907878 E-mail : rmunoz_11@yahoo.es
LAMBAYEQUE – PERU
ACUMULADO
OBRA : CONSTRUCCION DEL PUENTE ANTAJARANI Y ACCESOS
CLIENTE : PROVIAS DESCENTRALIZADO
CONTRATISTA : C&C CONSUL EJEC. CONTRATISTA GRALES SRL
N° DE CONTRATO : 269-2013-MTC/21, del 18 de diciembre del 2013
SUPERVISIÓN : CONSORCIO RMG
N° DE CONTRATO : 101-2013-MTC/21, de 10 de mayo del 2013
UBICACIÓN : DEPTO : PUNO PROV: HUANCANE DIST: VILQUECHICO
PLANILLA DE CÁLCULO DE AMORTIZACIÓN DEL ADELANTO DIRECTO
ADELANTO DIRECTO (c/IGV) 1,409,241.57 Presupuesto Referencial (con IGV)ADELANTO DIRECTO (s/IGV) 1,194,272.51 Presupuesto Referencial (sin IGV)
FECHA VALORIZACIÓN MONTO VALORIZADO (MV)
S/. 1,194,272.51 30.04.2014 1 308,786.22 S/. 61,757.24
31.05.2014 2 548,624.33 S/. 109,724.87
30.06.2014 3 118,393.63 S/. 23,678.73
975,804.18 195,160.84
NOTA: Los montos indicados no incluyen I.G.V
% AVANCE DE OBRA: 16.34%
ADELANTO OTORGADO S/. (AO)
AMORTIZACIÓN MV* AO/SV
CONSORCIO RMG
Mz. "H" Lt. 21 URB. DEL INGENIERO I - CHICLAYOTEL. 074208078 979907878 E-mail : rmunoz_11@yahoo.es
LAMBAYEQUE – PERU
DIST: VILQUECHICO
PLANILLA DE CÁLCULO DE AMORTIZACIÓN DEL ADELANTO DIRECTO
7,046,207.83
5,971,362.57
1,132,515.27
1,022,790.40
999,111.67
999,111.67
SALDO POR AMORTIZAR
Mz. "H" Lt. 21 URB. DEL INGENIERO I - CHICLAYOTEL. 074208078 979907878 E-mail : rmunoz_11@yahoo.es
LAMBAYEQUE – PERU
OBRA : CONSTRUCCION DEL PUENTE ANTAJARANI Y ACCESOS
CLIENTE : PROVIAS DESCENTRALIZADO
CONTRATISTA : C&C CONSUL EJEC. CONTRATISTA GRALES SRL
N° DE CONTRATO : 269-2013-MTC/21, del 18 de diciembre del 2013
SUPERVISIÓN : CONSORCIO RMG
N° DE CONTRATO : 101-2013-MTC/21, de 10 de mayo del 2013
UBICACIÓN : DEPTO : PUNO PROV: HUANCANE DIST: VILQUECHICO
DEDUCCIÓN DEL REAJUSTE GENERADO POR EL ADELANTO DIRECTO
VALORIZACIÓN DE OBRA N° 03 - JUNIO 2,014
D = ( A * V / C ) * ( K / Ka - 1 )
DONDE: D = Regularización de la deducción del reajuste generado por el adelanto directo.A = Monto del adelanto en efectivo concedido al Contratista V = Monto del componente en S/. de la valorización mensualK = Coeficiente de reajuste que corresponde al mes de la valorización de obraC = Saldo del contrato por valorizar a la fecha de pago del adelanto Ka = Coeficiente reajuste que corresponde al mes en que se pagó adelanto directo
A = 1,194,272.51V = 118,393.63K = 1.030C = 5,971,362.57Ka = 1.020
Dr = 232.14
CONSORCIO RMG
document.xlsD.R.Q.N.C.V. ANTERIOR
OBRA : CONSTRUCCION DEL PUENTE ANTAJARANI Y ACCESOS
CLIENTE : PROVIAS DESCENTRALIZADO
CONTRATISTA : C&C CONSUL EJEC. CONTRATISTA GRALES SRL
N° DE CONTRATO : 269-2013-MTC/21, del 18 de diciembre del 2013
SUPERVISIÓN : CONSORCIO RMG
N° DE CONTRATO : 101-2013-MTC/21, de 10 de mayo del 2013
UBICACIÓN : DEPTO : PUNO PROV: HUANCANE DIST: VILQUECHICO
REGULARIZACION DE LA DEDUCCIÓN DEL REAJUSTE GENERADO POR EL ADELANTO DIRECTO
VALORIZACIÓN Nº 02 (MAYO 2,014)
D = ( A * Vn / C ) * ( K / Ka - 1 ) - Dn
DONDE: Dr = Regularización de la deducción del reajuste generado por el adelanto directo.A = Monto del adelanto en efectivo concedido al Contratista Vn = Monto del componente en S/. de la valorización anteriorK = Coeficiente de reajuste que corresponde al mes de la valorización de obraC = Saldo del contrato por valorizar a la fecha de pago del adelanto Ka= Coeficiente reajuste que corresponde al mes en que se pagó adelanto directo Dn= Deducción del reajuste de la valorización anterior
A = 1,194,272.51Vn = 548,624.33K = 1.030C = 5,971,362.57Ka = 1.020Dn = 968.16
Dr = 107.57
CONSORCIO RMG
Mz. "H" Lt. 21 URB. DEL INGENIERO I - CHICLAYOTEL. 074-208078 979907878 RPM #343586
E-mail : rmunoz_11@yahoo.es LAMBAYEQUE – PERU
document.xlsD.R.Q.N.C.V. ANTERIOR
OBRA : CONSTRUCCION DEL PUENTE ANTAJARANI Y ACCESOS
CLIENTE : PROVIAS DESCENTRALIZADO
CONTRATISTA : C&C CONSUL EJEC. CONTRATISTA GRALES SRL
N° DE CONTRATO : 269-2013-MTC/21, del 18 de diciembre del 2013
SUPERVISIÓN : CONSORCIO RMG
N° DE CONTRATO : 101-2013-MTC/21, de 10 de mayo del 2013
UBICACIÓN : DEPTO : PUNO PROV: HUANCANE DIST: VILQUECHICO
REGULARIZACION DE LA DEDUCCIÓN DEL REAJUSTE GENERADO POR EL ADELANTO DIRECTO
VALORIZACIÓN Nº 01 (ABRIL 2,014)
D = ( A * Vn / C ) * ( K / Ka - 1 ) - Dn
DONDE: Dr = Regularización de la deducción del reajuste generado por el adelanto directo.A = Monto del adelanto en efectivo concedido al Contratista Vn = Monto del componente en S/. de la valorización anteriorK = Coeficiente de reajuste que corresponde al mes de la valorización de obraC = Saldo del contrato por valorizar a la fecha de pago del adelanto Ka= Coeficiente reajuste que corresponde al mes en que se pagó adelanto directo Dn= Deducción del reajuste de la valorización anterior
A = 1,194,272.51Vn = 308,786.22K = 1.029C = 5,971,362.57Ka = 1.020Dn = 666.01
Dr = -121.09
CONSORCIO RMG
Mz. "H" Lt. 21 URB. DEL INGENIERO I - CHICLAYOTEL. 074-208078 979907878 RPM #343586
E-mail : rmunoz_11@yahoo.es LAMBAYEQUE – PERU
document.xlsRESUMEN
OBRA : CONSTRUCCION DEL PUENTE ANTAJARANI Y ACCESOS
CLIENTE : PROVIAS DESCENTRALIZADO
CONTRATISTA : C&C CONSUL EJEC. CONTRATISTA GRALES SRL
N° DE CONTRATO : 269-2013-MTC/21, del 18 de diciembre del 2013
SUPERVISIÓN : CONSORCIO RMG
N° DE CONTRATO : 101-2013-MTC/21, de 10 de mayo del 2013
UBICACIÓN : PUNO - HUANCANE - VILQUECHICO
RESUMEN DE LA VALORIZACIÓN DE OBRA Nº 03 - JUNIO 2,014
CONCEPTO S/.
Monto valorizado en el presente mes : 118,393.63 . Valorización Nº 03 118,393.63
Reajustes de las Valorizaciones : 3,482.86 . Reajuste de la valorización Nº 03 3,551.81 . Regularizacion del Reajuste Valorización Nº 02 548.62 . Regularizacion del Reajuste Valorización Nº 01 (617.57)
Amortización en el presente mes de adelantos otorgad (23,678.73) . Del adelanto directo (23,678.73) . Del adelanto para materiales 0.00
Deducción del reajuste que no corresponde : -218.63 . Por adelanto directo en la Val. Nº 03 -232.14 . Por adelanto directo en la Val. Nº 02 -107.57 . Por adelanto directo en la Val. Nº 01 121.09
Otros 0.00 Multa por atraso de obra 0.00
I .- MONTO FACTURABLE (Sin I.G.V.) 97,979.13
Monto retenido por Fondo de Garantía 0.00 . Fondo G. Valorización No. 03 0.00 . Fondo G. Reajuste de la valorización Nº 01 0.00 . Fondo G. Regul.Reajuste de la valorización Nº 01 0.00
Otros 0.00 Otros (Servicios) 0.00
II .- TOTAL RETENCIÓN 0.00
II .- MONTO LÍQUIDO A PAGAR ( I ) 97,979.13
III .- I.G.V. ( 18,00% DE I ) 17,636.24
IV .- MONTO A FACTURAR ( I + III ) 115,615.37
CONSORCIO RMG
Mz. "H" Lt. 21 URB. DEL INGENIERO I - CHICLAYOTEL. 074-208078 979907878 RPM #343586
E-mail : rmunoz_11@yahoo.es LAMBAYEQUE – PERU