T H E L I V I N G W A L L
T H E L I V I N G W A L LPhase IObjective
Phase IIModularization
Phase IIIStructure
Phase IVPre Fabrication
Phase VRe assembly
Phase I
Design and fabricate a structure that accomodates at least three people with a basic and minimal dwelling
unit.
Individual units must be adjacent to one another and share boundaries. Each unit will need A Parti-Wall
with adjoining structures where unique structural and programmatic interlocking situations begin to evolve.
Have a clear design strategy and a maximum of two moves, the original volume of 6 x 6 x 8 ft must be registered in the development process and the final
outcome.
w
w
Objective
ROOF
ROOF
ENTRANCE
Exploring different ways of creating a roof and entrance using various shifts and moves in the massing.
ROOF
ENTRANCE
Finally, a space that would allow for a desired 6’6” clearance was achieved by raising a portion of the original mass upwards, which resulted in a roof that provided protection as well as headroom.
Also, an interesting entrance was created by pulling the middle of the mass backwards, which al-lowed for an entrance in the front and created a social balcony space in the back of the design.
Plan A - Sections A + B
Roof Entrance Social Balcony
Bedspaces
West (Entry) Elevation
Phase 1 Review100 design proposals
Phase II
Consolidate your efforts and schemes into a collab-orative scheme. An added goal in this phase is to be able to disassemble and pack each unit as blocks and consider the transportation of units in fragments.
Develop and refine the proposed units. Develop strate-gies to break down and rejoin blocks using mechanical connections. Explore the relationship between blocks,
hierarchy of materials and their thickness
Modularization
Modularization Scheme
Connection details for proposed modules
West (Entry) Elevation
Phase 2 Exhibition and Review28 Projects
Phase III
Reduce weight and projections of the structures.Finalize structure, modules, detailing and joinery.
Configure a roof pitch for drainage.
Structure
Exploring Pitched Cantilever
West (Entry) Elevation
Phase 3 Review14 Projects
Phase IV
Collaborative full scale construction2 x 6 floors and roof2 x 3 everything else1/2” ply for the floor3/8” ply everything else
The structures will be completely fabricated on campus in the Parker Hall Shop, then transported to Griffis
Sculpture Park and reassembled on site.
Claire Achtyl - Chris Belfiore - Sylvia Choi - Jeremy Cournyea -Andrew Delle Bovi - Vincent Ribeiro - Sobit Sarvantov
Pre Fabrication
Assembly of Modules A-F
Mod-A-Floor
Mod-A+B+C
Mod-C+D
Mod-C+D+E
Mod-F-Roof
Bolting Diagrams
Module A Amount Module D AmountNumber of 2”x3”x8’ 0 Number of 2”x3”x8’ 21Number of 2”x6”x8’ 8 Number of 2”x6”x8’ 0Sheets of Plywood(4’x8’x3/8”) 0 Sheets of Plywood(4’x8’x3/8”) 2Sheets of Plywood(4’x8’x1/2”) 2 Sheets of Plywood(4’x8’x3/8”) 2Number of Bolts 28 Number of Bolts 18 Number of nuts 28 Number of Nuts 18 Number of Washers 56 Number of Washers 36 Number of Screws 52 Number of Screws 156 Total weight 205.83 Total Weight 247.117 Module B Amount Module E AmountNumber of 2”x3”x8’ 14 Number of 2”x3”x8’ 16Number of 2”x6”x8’ 0 Number of 2”x6”x8’ 0Sheets of Plywood(4’x8’x3/8”) 4 Sheets of Plywood(4’x8’x3/8”) 3Sheets of Plywood(4’x8’x1/2”) 2 Sheets of Plywood(4’x8’x1/2”) 3Number of Bolts 20 Number of Bolts 18 Number of Nuts 20 Number of Nuts 18 Number of Washers 40 Number of Washers 36 Number of Screws 126 Number of Screws 104 Total Weight 205.83 Total Weight 203.588 Module C Amount Module F AmountNumber of 2”x3”x8’ 8 Number of 2”x3”x8’ 2Number of 2”x6”x8’ 0 Number of 2”x6”x8’ 4Sheets of Plywood(4’x8’x3/8”) 1 Sheets of Plywood(4’x8’x3/8”) 2Sheets of Plywood(4’x8’x1/2”) 0 Sheets of Plywood(4’x8’x1/2”) 1Number of Bolts 16 Number of Bolts 14Number of Nuts 16 Number of Nuts 14 Number of Washers 32 Number of Washers 28 Number of Screws 56 Number of Screws 84 Total Weight 89.376 Total Weight 199.948
Number of Bolts/Nuts 92 Number of Washers 184 Number of Screws 536 Number of 2x3 61 Number of 2x6 10 Number of 3/8” 14 Number of 1/2” 10
Total Weight - 1152 lbs
2x3 Weight(lbs) 2’x6’ Weight(lbs) 3/8” Ply Weight(lbs) 1/2”Ply Weight(lbs)1’ 0.94 1’ 2 1’x1’ 1.32 1’x1’ 1.752’ 1.88 2’ 4 2’x2’ 5.26 2’x2’ 73’ 2.82 3’ 6 3’x3’ 11.88 3’x3’ 15.754’ 3.76 4’ 8 2’x6’ 15.84 2’x6’ 215’ 4.7 5’ 10 4’x8’ 42.24 4’x8’ 566’ 5.64 6’ 12 1”x1” 0.009 1”x1” 0.0121” 0.11 1” 0.156
Phase V
Transportation, Re-Assembly + Evaluation
Polyurethane was added to water seal all projects. Fork-lift rails were installed underneath each project and temporary bracing was added in order to provide structure for shipping. Finally, all projects were shrink wrapped to protect them during the transportation procedure.
On Sunday April 18th, all 14 projects were shipped to Griffis Sculpture Park in East Otto, New York.
UB Reporter - UB Students Create Interactive Wall
Buffalo News - Page 03 - Sunday May 2nd
Springville Journal - Submitted Images and Text
Flickr Page - The Living Wall
http://www.architizer.com/en_us/projects/view/the-living-wall/7588/
Blog - http://thelivingwall.blogspot.com
Recommended