Time Knitwear PVT Ltd.Baraibogh, Enayetnagar, Narayangonj, Bangladesh

(23.617692N,90.481259E)04th June 2014

1

2

Observations

3

Problems Observed

Item No 1: Heavily loaded cantilever slabs.Item No. 2: Long span of R.C. slabs Item No. 3: Discrepancies between drawings and as built structure.Item No. 4: Water ingress.Item No. 5: Exposed Reinforcement.

4

Heavy loaded cantilever slabs.

5

1

À

2 3 4 5 6 7 8

B

C

D

E

Heavily Loaded Cantilevers.

6

Long span of R.C. slabs

7

1

À

2 3 4 5 6 7 8

B

C

D

E

Large Slab Spans

Slab spans appear long, some cracking noted in soffitsat all levels in these bays.

8

Discrepancies between drawings and as built structure.

9

1

À

2 3 4 5 6 7 8

B

C

D

E

Discrepancies between drawings and as built structure..

Stair Column is rotatedIn opposite directionTo that shown on drawing.

These columns are larger as built than proposed drawings indicate.

10

Water Ingress

11

Water from planter may affectstructural elementsthrough cracks in roof screed.

Water from air conditioning unitmay affect structural elementsthrough cracks in roof screed.

12

Exposed Reinforcement

13

14

Item No. Observation Recommended Action Plan Recommended Timeline

1Heavily Loaded Cantilever

slabsStructural engineer to check the capacity of the cantilevers for building loads.

6-weeks

2Heavily Loaded Cantilever

slabs

Engineer to Produce and actively manage a loading plan for all floor plates within the Building giving consideration to floor and column capacity.

6-weeks

3Heavily Loaded Cantilever

slabsContinue to implement the load management plan 6-months

4 Long span of R.C. slabsStructural engineer to confirm by calculation that the slabs are designed for the as constructed spans and are capable of carrying the building loads.

6-weeks

5Discrepancies between drawings and as built

structure.

Building engineer to update all drawings including load management plans to reflect the as built structure at each level.

6-months

6 Water ingressBuilding engineer to survey factory and identify areas of water ingress. Divert all water away from structure to protect the RC structures from direct contact with water

6-months

7 Exposed ReinforcementAll exposed reinforcement is to be protected from corrosion which may cause degradation of the concrete.

6-months

Recommended