Vanderbilt Beach Road Extension Project
Recommendation to approve the revised alignment of Vanderbilt Beach Road Extension from Collier Boulevard to 16th Street NE. (Project No. 60168).
BCC Meeting October 22, 2019 – Item 11.F.
1
Jay Ahmad, P.E., Director Transportation Engineering
• June 26, 2018: Public Information Meeting: 30% conceptual design
• Sept 25, 2018: Board discussed frontage road connections; approved shifting VBRX northward and relocating Cypress Canal to the south.
• December 2018: Greyhawk community asked for revised alignment (preserve the original 2-lane VBR as a frontage road, straighten VBRX)
• May 22, 2019: Public Information Meeting: alternative alignment
2
Vanderbilt Beach Road Extension Project:
4
Revised alignment removing “S” curve is safer, requires purchase of 2 homes – see item 11.G.:
163FEE 164FEE
6
VCC’s sale to County provides ~ 1 mile of western half of property needed for future Massey Street project:
~ to Tree Farm Rd
PROJECT SCHEDULE
7
60% PLANS: 05/2020
90% PLANS: 09/2020
100% PLANS: 12/2020
TARGET BID START: 05/2021
TARGET CONSTRUCTION START: 12/2021
TARGET CONSTRUCTION COMPLETION: 05/2024
Recommended