Rate Analysis n Responsibility Chart

Preview:

DESCRIPTION

office management

Citation preview

M/s.______________ITEM DESCRIPTION

1

a Basic Rate of Strandsb Excise Duty 12.50% -

Total - c VAT @ 5% 5.00% -

Total - d Transporte Crane Charges

Landed Cost of Strands -

2

a -

b

c

d

e

f

g Design and Shop Drawings

h

I Overheads

j Profit Margin

TOTAL -

Rate Analysis for Design, Supply, Installation, Stressing & Grouting for Post Tensioning work for

podium slab for Residential Towers at My City - Dombivali.

HT Strands including WastageAnchorage Set - Guide, Bearing, WedgesSheathing Pipe (GI Ducts Flat)

Consumables including Additives (Cebex) and Painting, Adhesive Tape, Thermocol, Cutting Wheel

Equipment & AccessoriesMachinery Tools and Plants

Labour - Manpower (Staff and Labour)Accomodation for LaboursEngineers and Technicians

Freight, travel, insurance, site expenses, conveyance, accommodation etc

DETAIL RESPONSIBILITY

ITEMS DESCRIPTION OF WORK RESPONSIBILITY

1 Supply of High Tensile Steel (12.7 mm dia Strand)

2

3

4

5

6

7 Supply of Cement for grouting at slab level

8 Supply & fabrication and fixing of Bursting Links

9 Supply fabrication of Chairs for Tendon supports

10 Fixing of Tendon supports

11

12 Filling of end Recess pockets left out for stressing.

13

14

15

16 Providing Potable Water for Grouting

17

18

19

20 CAR and Third Party liability insurance.

21 Slab Soffit low point marking for tendons.

22

Supply of Post Tensioning Anchorages, Gl Ducts/Sheating, Barrels, Wedges with Consumables.

Installation (Cutting and Profiling) of Strands, Ducts, Anchor blocks and Wedges.

Stressing of Tendons with PT Contractors's equipments.

Grouting of the Tendons with Utracon's Grouting Pump

Providing required Qualified Engineers, Technicians for PT Works

Supply of Admixtures for Grouting(Fosrock-cebex100)

Covered space for storing the PT materials and Equipments

Providing working platform for stressing and grouting (Min.750 mm from the face)

Power supply as per Contractor's requirement in all working areas at site, equipments and stores. (15 HP)

Design of slabs for gravity loads and submission of shop drawings to consultant

Submission of as built drawings on completion of work

Insurance for Contractor's workmen, Equipments and Materials

Lifting arrangement for for Men/Materials and Equipments.

23 Space provision for Labour Accomodation