Ramón Cerero ES Session 3 - Block2 -
Barcelona 12-15 May 2003
Integration of Control Centre and Power Quality Information at IBERDROLA
Ramón Cerero
Ana Gzlez Bordagaray
Mikel Abendaño
2
Barcelona 12-15 May 2003
Ramón Cerero ES Session 3 - Block2 -
Iberdrola: Company introductionIberdrola: Company introduction Need for iPODACNeed for iPODAC Interfaces with other systemsInterfaces with other systems Architectural DesignArchitectural Design User InterfaceUser Interface Conclusions and further developments Conclusions and further developments
Index
3
Barcelona 12-15 May 2003
Ramón Cerero ES Session 3 - Block2 -
Company Introduction
VALLADOLID
VALENCIA
BILBAO
MADRIDCACERES
TOLEDO ALICANTE
MURCIA
9,3 Million Customers.
8 Control centres distributed along Spanish territory
(formerly 37 in 1997)
50.000 MV outages, 20.000 planned jobs
900 Substations (all telecontrolled)+ 2000 telecontrolled locations in MV Feeders.
Transformation Capacity : 11.900 MW (MV) + 25.200 MVA(LV)
6.000 HV/MV Feeders
78.000 MV/LV Transformers.
Main numbers:
4
Barcelona 12-15 May 2003
Ramón Cerero ES Session 3 - Block2 -
General reingeneering. Grouping of control centres and systems, Implementation of
new systems (DMS, Maintenance) and demand for information all around the
company
Need for Integration (SCADA/DMS, AM/FM/GIS, MAINTENANCE/RELIABILITY,
CIS)
Need for real time information (Maintenance, operation) and historical data
(planning, maintenance, operation, management).
Web technologies: Corporate access from anywhere, small bandwidth requirement,
friendliness.
New regulation requirements (exoneration, customer discounts, auditability, etc..)
Why was iPODAC needed?
5
Barcelona 12-15 May 2003
Ramón Cerero ES Session 3 - Block2 -
WEB ACCESS toiPODAC through the
Browser
Outages, calls,Quality of service
information...
Outages Information for Bill Discounts
Field OrdersMeasurements
Counters(SCADA/DMS/EMS)
GIS/AM/FM(Sigrid system)
CIS(Customer Bills)
SAP environment
RELIABILITY AND MAINTENANCE(GAMAD system)
Network Model&
Inventory
iPODAC Interfaces
Real time Data
Outages/jobs history
Quality of service indexes
Other Statistical reports
iPODAC
6
Barcelona 12-15 May 2003
Ramón Cerero ES Session 3 - Block2 -
Architectural Design
SharedDisks
Communication with otherSystems (DMS, CIS,AM/FM/GIS, MAINT)
Server 1
Disk Master
Database Server
Fail Safe configuration ofserver1 and server 2
BackupTape
USER Interface throughHTML/JSP
Server 1
Disk Master
JSP Server
BackupDisks
7
Barcelona 12-15 May 2003
Ramón Cerero ES Session 3 - Block2 -
User InterfaceWeb Based Aproach user interface:
Easy to access from anywhere inside/outside the company
User Friendly interface.
Future oriented (mobile access, internet,…)
Flexible design.
Currently Following Functionality implemented:
Real time outages (Maintenance, operation).
Historic outages (planning, maintenanace, operation, management).
Quality of service indexes (Indexes such as TIEPI, NIEPI, individual Quality of
Service)
Tracking of exoneration
Other general statistical reports (number of outages, Calls. Response times,
expected & quality tendency, etc…)
SMS sending.
8
Barcelona 12-15 May 2003
Ramón Cerero ES Session 3 - Block2 -
9
Barcelona 12-15 May 2003
Ramón Cerero ES Session 3 - Block2 -
10
Barcelona 12-15 May 2003
Ramón Cerero ES Session 3 - Block2 -
Final Conclusions
Success Based in User experiences and comments
True improvements: systems management and maintenance, flexibility for
changes, users satisfaction with solution.
Future objectives:
Mobile access, planned outages, graphic visualization of results (map like),
improvements based on new quality of service regulation requirements
Connection with other Web systems (SCADA alarms, Maintenance reports,
etc..)
11
Barcelona 12-15 May 2003
Ramón Cerero ES Session 3 - Block2 -
Contact Information
Ramón Cerero ramon.cerero@iberdrola.es +34944664303
Ana Gzlez. Bordagaray ana.gb@iberdrola.es +34944663551
Mikel Abendaño mabendano@iberdrola.es +34944664957