Purple Line Extension Updates on La Cienega and Rodeo Stations December 13, 2017
1
Agenda
2
• Project Overview
• Section 1 Construction Updates
• Wilshire/La Cienega Station
• La Cienega Decking
• Decking Overview
• Schedule
• Detours
• Upcoming Work - Summer 2018
• Safety
• Section 2 Pre-Construction Updates• Rodeo Drive Station
• Advance Utility Relocation (AUR)• SCE Phase I• SCE Phase II, future
power outage• SoCal Gas and AT&T
• Geotechnical Investigation• Demolition of former Ace
Gallery
• Business Interruption Fund
• Questions & Answers
Purple Line ExtensionProject Alignment
3
Sections 1, 2 & 3 Status
4
Forecasted Schedule
Section Section 1 Section 2 Section 3
Length 3.92 Miles 2.59 Miles 2.59 Miles
New Stations Wilshire/La Brea
Wilshire/Fairfax
Wilshire/La Cienega
Wilshire/Rodeo
Century City/
Constellation
Westwood/UCLA
Westwood/VA
Hospital
Pre-Construction
Activities
2014-2015 2016 - 2018 2016 – 2018
Construction 2015 - 2023 2018 – 2025 2018 – 2026
Operations 2023 2025 2026
*Subject to change. The PLE project team is working to deliver the project consistent with Measure M
Section 1Wilshire/La Cienega Station
5
Wilshire/La Cienega Station
6
Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr
Wilshire/La Cienega Station*As of December 2017, subject to change
7
Wilshire/La Cienega Station Decking Overview
8
• Construction of a concrete deck on Wilshire Bl, which will serve as a temporary roadway while construction proceeds underground. This construction spans the width of Wilshire Bl
• Location: Wilshire Bl between La Cienega Bl and San Vicente Bl, and in the Wilshire/La Cienegaintersection
• This work occurs under full weekend closures of Wilshire Bland La Cienega Bl
Wilshire/La Cienega DeckingWork zone
9
Approximate location of decking work zone at Wilshire Bl/La Cienega Bl
GALE LAYDOWN
YARDLA CIENEGALAYDOWN
YARD
Wilshire/La Cienega StationWeekend Closures Schedule
Wilshire Bl/La Cienega Bl Weekend Closures Schedule• Approximately 17 weekend closures• Scheduled in 3 phases• Started September 8, 2017
Phase 1: Wilshire Bl between La Cienega Bl and San Vicente Bl – COMPLETE
Phase 2: Wilshire/La Cienega intersection – COMPLETE• 4 weekends
Phase 3: Wilshire Bl between La Cienega Bl and San Vicente Bl• 11 weekends • Started November 3rd
10
Wilshire/La Cienega StationDecking Construction
11
Laying and welding deck beams across Wilshire Bl and Gale Dr
Phase 3: East/West DetourWilshire Bl between La Cienega Bl and San Vicente Bl
12
Closures:• Westbound Wilshire Bl
will be closed at San Vicente Bl
• Eastbound Wilshire Bl will be closed at Robertson Bl
Local Access:
• Maintained to Wilshire Bl,La Cienega Bl open during this phase
Detours:
• Eastbound: Wilshire Bl Robertson Bl Burton Way San Vicente Bl Wilshire Bl
• Westbound: Wilshire Bl San Vicente Bl Burton Way Robertson Bl Wilshire Bl
Bus DetoursWeekend Full Closures
Bus Detour Route will follow Traffic Detour:
• Eastbound: Wilshire Bl Robertson Bl Burton Way San Vicente Bl Wilshire Bl
• Westbound: Wilshire Bl San Vicente Bl Burton Way Robertson Bl Wilshire Bl
13
For information regarding changes to Metro service, please call 323.GoMetro or visit: https://www.metro.net/service/advisories/
720/20 Wilshire bus stops for Wilshire/La Brea, Wilshire/Fairfax and Wilshire/La Cienegahave been relocated to temporary locations away from the construction zone and will remain in place until construction is completed
Additional ParkingWilshire and La Cienega alignment
Repainting of existing red curbs into future grey curbs for added parking. Construction mitigation paid for by Metro.
Locations of Re-Painting:• Hamilton Dr• Gregory Wy• Gale Dr• Tower Dr
N
Wilshire/La CienegaUpcoming Work, June 2018
15
• Work zone removal on Wilshire Bl between La Cienega Bl and San Vicente Bl is anticipated in June 2018
• The current work zone on the north side of Wilshire Bl with concrete barriers, fencing and noise mitigation blankets will be substantially removed
• Wilshire Bl traffic lanes will be substantially returned to three lanes in each direction
• Left turn movements on Wilshire Bl are anticipated to return at Hamilton Dr and Gale Dr
Location of the current work zone on Wilshire Bl between La Cienega Bl and San Vicente Bl
Wilshire/La CienegaUpcoming Work, June 2018
16
• Work zone set-up for jet grouting construction on Wilshire Bl between Carson Rd and La Cienega Bl anticipated in June 2018
• Center median work zone will be installed with concrete barriers, fencing and noise mitigation blankets for 8-12 weeks
• Work zone: Center lanes of Wilshire Bl, with two lanes of traffic on Wilshire Bl maintained in both directions
• Left turn and thru movements will be restricted from Stanley Dr and Le Doux Dr at Wilshire Bl
• Work hours: 7am-8pm for drilling activities and 8pm -10pm for support activities such as concrete pours and cleanup
• Intermittent off-peak hour weekday closures and weekend directional closures are anticipated
• Bus stops will be temporarily relocated and parking will be temporarily restricted on Wilshire Bl between Carson Rd and La Cienega Bl Location of the new work zone that will
be installed on Wilshire Bl between Carson Rd and La Cienega Bl
Wilshire/La CienegaJet grouting example
17
Example of jet grouting from San Vicente Bl and Wilshire Bl
Help Us Keep You Safe
18
Purple Line Extension24/7 Project Hotline - 213.922.6934Email – purplelineext@metro.net
On Metro TransitSee Something, Say Something888-950-SAFE (7233)
Construction Safety Awareness ProgramGlyssa Alcazar, Community Relations OfficerEmail: alcazarg@metro.netPhone: 323.900.2192
City of Beverly HillsPurpleLine@beverlyhills.orgPublic Works Customer Service: (310) 285-2467
Section 2Wilshire/Rodeo Station
1919
Purple Line ExtensionSection 2 Agenda
20
• Rodeo Drive Station• Advance Utility Relocation (AUR)
• SCE Phase I• SCE Phase II, future power outage• SoCal Gas and AT&T
• Geotechnical Investigation• Demolition of former Ace Gallery
Purple Line ExtensionSection 2 Alignment
21
Wilshire/Rodeo Station
Rendering shows length of the underground station box on Wilshire Bl from Canon Dr to Beverly Dr
22
Advanced Utility Relocation
Southern California EdisonRed=power
Wayfinding Signage
25
Start Dates:
• SCE Phase 1: September 5, 2017
• SCE Phase 2: January 2018
• SCG: February 2018
• AT&T: February 2018
Advanced Utility RelocationWilshire/Rodeo Station
Rendering of AUR work26
• Sunday 10am-6pm, Monday-Friday 9am-4pm
• Sun – Wed: Wilshire with turn restrictions
• Thurs-Fri: Reeves or Wilshire with no turn restrictions
• City of Beverly Hills/Metro traffic engineers will monitor traffic
• Local Access Only signs
• Signal and crosswalk timing adjustments
• Traffic Control Officers (TCO)
• Beverly Hills Police Department support
• Any other adjustments as needed to work plans, traffic plans or detours
• Monitor bus stops and zones
SCE Advanced Utility RelocationMonitoring and Adjustment
27
• Cable Pulling: 3 weeks, anticipated January 2018
• Utility Interruption: Two 8-hour outages per circuit
• Anticipated January 2018
• 3 separate circuits impacted
• Direct engagement to impacted businesses and one
residential unit
• Same traffic plans as SCE Phase 1
SCE Phase 2
28
*Pending City Council Approval
SCG and AT&T Utility RelocationCombined Traffic Control
Starting January 2018
• SCG and AT&T will work simultaneously within work zone• Will reduce overall duration of work• Work is scheduled from February through August 2018
• Stage 1-3 will look similar to SCE• Work is set up in morning and taken down each night• Will accommodate awards season
• Stage 4 -8 will take place behind K-rail• K-rail to remain 24/7 and work will take place behind it during approved
working hours• Set up will take place after awards season (March 5, 2018)
29
*Pending City Council Approval
SCG and AT&T Utility RelocationStage 1: 16 days / Sun.: 10am-6pm, Mon.-Wed.: 9am-4pm
30
SCG and AT&T Utility RelocationStage 4-7 Traffic Proposal
• Medians and parking removed from work zone
• Buses relocated outside of work zone-Metro is with the City of Beverly Hills to determine the new locations.
• Wilshire Bl two lanes each direction from west of Beverly Dr to east of Canon Dr
Example on Wilshire Bl
31
SCG and AT&T Utility RelocationStage 4: 34 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm
32
K-Rail 24/7
Purpose of Memorandum of Agreement (MOA)
• Establish conditions and procedures for construction
• Minimize impacts to the Community
• Establish compliance monitor and enforcement process
33
34
Key Terms of the Design-Build MOA
• Enforcement of Conditions
• Independent Compliance Monitor
• Allowable Work Hours
• Holiday Moratorium
• Service Interruptions
• Traffic Impacts
• Construction Aesthetics
• On-Street Parking
• Noise Standards
• Light Mitigation
• Traffic Mitigation Conditions
• Business Mitigation Assistance
• Notifications Process
• N. Canon Drive Traffic Study
*City Council action Summer 2018
MOA – Design-BuildHoliday Moratorium
• New Year’s Day
• Martin Luther King Jr. Day
• President’s Day
• Mother’s Day
• Memorial Day
• Father’s Day
• Easter Sunday
• The First Two Days of Passover
35
• Independence Day
• Labor Day
• Rosh Hashanah
• Yom Kippur
• Thanksgiving Day
• The Friday after Thanksgiving
• Christmas Day
MOA – Design-BuildBusiness Mitigation Assistance (BMA)
36
• 24/7 Hotline with live-person
• Advertising
• Eat Shop Play Beverly Hills
• Coordination with BH Chamber of Commerce and My Beverly Hills campaign
• Coordination with BH Tourism and Visitors Bureau and Love Beverly Hills campaign
• Parking Mitigation
• Banners and signage (Aesthetic Treatment)
• Communications, Outreach and Engagement
8
• Gather additional soil information to validate existing data and characterize subsurface conditions for the design and construction of stations, tunnels, and cross passages• Cross passages connect the two tunnels and house mechanical and electrical
equipment along the alignment
• Install groundwater monitoring wells and gas probes to be used for monitoring prior to and during construction
Geotechnical Site InvestigationPurpose of Investigation
Geotechnical Site InvestigationSchedule
• Began work on Monday November 27, 2017
• Completion of work by February 2018
• Schedule: 3 to 5 days per boring location
• Each shift: 2 to 3 hours spent on set-up and breakdown (including traffic control and noise mitigation efforts)
• Proposed work hours:
• Nighttime: 8pm – 6am
• Daytime: 9am – 4pm
38
Geotechnical Site InvestigationTraffic Control
ALL TURN LANES OPEN FOR USE
Typical Traffic Control for Work Zone in Outside Lanes
39
Demolition of 9430 Wilshire BlFormer Ace Gallery, future Construction Staging Yard
40
Demolition of 9430 Wilshire BlFormer Ace Gallery
Site Address: 9430 Wilshire Blvd
• 2-Story Building on the corner of Wilshire Bl and Reeves Dr
Schedule
• Anticipated Start in March 2018
• Estimated Duration of Demolition Activities: 5-7 weeks
Traffic Impacts
• Temporary Lane Closure along Wilshire Bl (approximately 2 weeks)
• Temporary Turn Restriction on Reeves Dr
• Sidewalk/Partial Lane Closure along Reeves Dr (duration of demolition)
• Pedestrian protection to be installed
41
*Pending City Council Approval
Dust Mitigation• Water used to spray demo
area
Noise Mitigation• Equipment installed with
low-noise mufflers and noise blankets on fencing around work area
Protection of the Park• Fencing/barrier around work
area including noise control measures.
Demolition of 9430 Wilshire BlFormer Ace Gallery
Example of noise mitigation blanket
42
Next StepsWilshire/Rodeo Station
43
City Council anticipated in March 2018
• Ace Gallery Demo permit
Notification process
• Hand delivered, email, website, social media
Continued Outreach and Communication
• Monthly meeting – 2nd Wednesday of each month at City of Beverly Hills City Hall
• “Traffic Alert” in local newspapers
• Construction notices
• Online and social media ads
Helping local businesses as we build.Update as of 12/8/17
BIF Information and Eligibility
> Financial assistance to small “mom & pop” businesses with 25 or fewer employees directly impacted by Metro Rail construction along three project areas
> Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements
> Grant amount determined by loss of business revenue related to period of construction disruption
> To date, more than $11.9 million awarded to 260 small businesses along all three project areas
BIF Grant Award Update
> Purple Line Extension, Section 1
> BIF Grants Awarded: 132
> BIF Grant Amount Awarded: $3,134,571.58
> Number of small businesses awarded: 55
> BIF Business Advisor: Brian Lazo, PCR, 213.739.2999
> Purple Line Extension, Section 2
> BIF Business Advisor: Darrell Smith, PCR, 213.739.2999
Updates on La Cienega and Rodeo Stations
Wednesday, January 10
6:30pm – 8pm
Beverly Hills City HallMunicipal Gallery455 N Rexford Dr
Beverly Hills, CA 90210
47
Next Community MeetingBeverly Hills
Section 1: Construction Community Meeting
Thursday, January 18
6pm – 7:30pm
Petersen Automotive Museum
6060 Wilshire BlLos Angeles, CA 90036
48
Next Community MeetingSection 1
Stay in Touch
49