Punjab Cities Governance Improvement Project (PCGIP)

City District Government Rawalpindi

ANNUAL PLANNING WORKSHOP FOR YEAR 3

August 8-9, 2014

ELIGIBLE EXPENDITURES

The Project money can be spent on Eligible Expenditure items only:

Repair of machinery, equipment, roads, buildings, water supply drainage

Power energy needed for machinery, operations for asset maintenance & service delivery

There will be no new infrastructure, however, money saved from

these heads to be used for achievement of program objectives

2

Progress Year 1

12 August 2014

PLC:SC

3

Nos Cost PKR mil

Total Schemes 26 195

NCB 5 75.1

Shoping 21 119.9

Progress of Year 1

PKR. mil Physical Progress %

Total funds 195 100

Repair & Maintance of Road 192.039 100

Repair & Maintance of Road

Making machinary Machinary 2.961 100

12 August 2014

PLC:SC

4

Dr. Qadeer Road,

During execution

Dr. Qadeer Road,

After Completion

Kalma Chowk Harley Street

Girja Road

Girja Harley Street Kalma Chowk

8

Working Area

Islamabad Expressway

Muree Road

I.J.P Road

Airport Road

Peshawar Road

IMPLEMENTATION OF ENVIRONMENTAL &

SOCIAL MANAGEMENT FRAMEWORK (ESMF)

CDGR

EEPs Schemes

26

ADP Schemes

44

12 August 2014

PLC:SC

9

The total schemes of CDGR (EEPs+ADP) was 70. ESMF was applied on 26 schemes of EEPs. Hence 30 % target (21 schemes) for 2nd year has been achieved from EEP’s schemes only.

For Whole ESMF Implementation Process, following steps were involved:

Environmental & Social Screening of all EEPs schemes

Preparation of Environmental & Social Management Plans (ESMPs) of

E-2 categorized schemes

Approval of ESMPs from Environmental Protection Department, Lahore

Site visits regarding implementation of ESMPs

Preparation of Environmental & Social Compliance Reports etc.

Third Party Validation of implementation of ESMF

10

Procurement Plan for 2014-15

CITY DISTRICT GOVERNMENT RAWALPINDI

PROCUREMENT PLAN 2014-15

A. WORKS

Sl. No. Description Amount in

Million

1 Road Sector 140.00

2 Building Sector 100.00

12 August 2014

PLC:SC

11

12 August 2014

PLC:SC

12

Sl. No. NAME OF SCHEME Cost in Million

1 2 3

1

Repair / Rehabilitation of Road From Chaklala Scheme-III

(Shell Pump to High Court upto G.T. Road) Length = 4.30 KM

Rawalpindi

46.176

2 Repair / Rehabilitation of Missing Link Between Defense Road

and Morgah Length = 2.00 KM Rawalpindi 21.667

3

Repair / Rehabilitation of Road from Airport Housing Society

to Underpass / Muhallah Noorani along the Railway Line

Length = 2.10 KM Rawalpindi

17.467

4 Repair / Rehabilitation of Road from Dheri Chowk to Dhamial

Road (Jhawra Road) Length = 1.30 KM Rawalpindi 14.193

5 Repair / Rehabilitation of Rawal Road Length 4.00 KM Tehsil

Rawalpindi 20.335

6 Repair / Improvement of Link Road Chakri Road To Girja Road

Length = 1.80 Km Rawalpindi 19.083

Sl. No. NAME OF SCHEME Cost in Million

1 2 3

1 Special Repair/ Improvement of Government Offices in Urban

Area. 34.800

2 Special Repair/ Improvement of Government Residences in

Urban Area 30.891

3

Special Repair/ Improvement of Other Works Pertaining to Such

as External Development, tube Wells & Masjid Etc With

Government Buildings in Urban Area

28.870

4

Special Repair/Improvement of (5 Nos) Vehicles & Pol Charges

, Telephone Exchange, Ups Batteries, Computer, Printer, Fax

Machine, Photo State Machine

1.780

Work Plan for implementation of ESMF 2014-2015

15

Recommended