Stream Stabilization – Phase 2

Public Meeting

Yeader Creek https://easterlake.org/

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Yeader Creek Phase 2 - Introductions

City of Des Moines Staff

Bruce Rydberg – Project Contact

Right of Way Personnel

HR Green Staff

Other Watershed Partners

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Easter Lake Watershed Partners

https://easterlake.org/

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Easter Lake Watershed

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Yeader Creek Phase 2 - Project Purpose

Bank Stabilization

Targeted in 2012 Watershed Management Plan

Approximately 60% of total sediment load

In-lake Improvement Longevity

Stream Water Quality

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Yeader Creek Phase 2 - Project Purpose

An Engaged Public

People usually put forth their own effort when they see

effort by others

If things are already clean, people tend to keep things

clean and picked up

Don’t feed the algae – Switch to phosphorus free

fertilizer!

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Yeader Creek Phase 2 - Project Status

Field & Desktop Assessment - Completed

Conceptual Plans - Completed

Public Comment – Current

Design & Permitting – Through Fall 2018

Construction – Fall 2018 through Fall 2019

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Field & Desktop Assessment

Almost 3 miles assessed

Active toe erosion

Bank height

Infrastructure proximity

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Field Review: Stream Bank Erosion

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Field Review: Stream Bank Erosion

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Field Review: Sanitary Sewer at Risk

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Field Review: Phase 1 Project – YC 14

After Construction

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Prioritization Matrix

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Prioritization Map

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Example Concept Map

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Example Concept – Toe Rock & Bendway Weirs

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Example Concept – Toe Rock & Bendway Weirs

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Example Concept – Toe Rock & Bendway Weirs

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Example Concept – Toe Rock & Bendway Weirs

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Example Concept – Rock Riffle

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Vegetation Expectations

Trees

Save as many as we can

There will be some significant removal

Native Grasses & Forbs

Usually 15% to 20% germination within 18 months

The other species within 24 to 36 months

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Public

Concept Review

Tabletops • Concept Maps

• Comment Forms

Yeader Creek Stabilization – Phase 2 | Des Moines, Iowa

Project Contact Information

Bruce Rydberg, P.E. 400 Robert D. Ray Drive Des Moines | Iowa | 50309 Phone: 515.283.4074 E-Mail: bkrydberg@dmgov.org

https://easterlake.org/