Loraine Independent School District

Preview:

DESCRIPTION

Loraine Independent School District. Campus Improvements Construction Update February 21 , 2012. PROJECT STATUS. PLANS. PLANS. SCHEDULE. SCHEDULE STATUS. Gymnasium Slab is Complete Steel Erection is Near Completion Masonry is Complete In Locker Room Areas - PowerPoint PPT Presentation

Citation preview

Loraine IndependentSchool District

• Campus Improvements• Construction Update• February 21, 2012

PROJECT STATUS

Budgeted Amount

Cost Savings

GMP Total

Amount Billed

Through December

% Comp

Owner's Contingency

Contractor Contingency

$10,800,000 $83,599 $10,716,401 $3,554,443   33% $104,540 $214,328

 

PLANS

PLANS

SCHEDULE

Gymnasium Slab is Complete Steel Erection is Near Completion Masonry is Complete In Locker Room Areas CMU is Continuing at Gymnasium Exterior Brick Veneer Has Begun Interior and Exterior Framing is Progressing Well Mechanical and Electrical Rough-in Has Begun Roofing Has Begun / HS~JH~Lab is Dried-in Bus Barn is Erected

SCHEDULE STATUS

Masonry at Gymnasium

Gymnasium Steel Structure

Cafeteria and Stage Steel

Framing at Kitchen and Administration

Roof of Science Wing

Brick and CMU Masonry Will Continue Steel Erection Will Be Complete - Crane Will be Removed Exterior Drywall Framing And Sheathing Will Continue MEP Wall And Ceiling Rough-In Will Follow CMU And

Drywall Framing Steel Pans will be Erected at Gymnasium Bleachers Concrete will be Poured at Gymnasium Bleachers Roofing will Continue Sheetrock Installation will Commence Tape and Bed will Commence

LOOKING AHEAD