Loraine Independent School District. Campus Improvements Construction Update February 21 , 2012. PROJECT STATUS. PLANS. PLANS. SCHEDULE. SCHEDULE STATUS. Gymnasium Slab is Complete Steel Erection is Near Completion Masonry is Complete In Locker Room Areas - PowerPoint PPT Presentation
Citation preview
Loraine IndependentSchool District
• Campus Improvements• Construction Update• February 21, 2012
PROJECT STATUS
Budgeted Amount
Cost Savings
GMP Total
Amount Billed
Through December
% Comp
Owner's Contingency
Contractor Contingency
$10,800,000 $83,599 $10,716,401 $3,554,443 33% $104,540 $214,328
PLANS
PLANS
SCHEDULE
Gymnasium Slab is Complete Steel Erection is Near Completion Masonry is Complete In Locker Room Areas CMU is Continuing at Gymnasium Exterior Brick Veneer Has Begun Interior and Exterior Framing is Progressing Well Mechanical and Electrical Rough-in Has Begun Roofing Has Begun / HS~JH~Lab is Dried-in Bus Barn is Erected
SCHEDULE STATUS
Masonry at Gymnasium
Gymnasium Steel Structure
Cafeteria and Stage Steel
Framing at Kitchen and Administration
Roof of Science Wing
Brick and CMU Masonry Will Continue Steel Erection Will Be Complete - Crane Will be Removed Exterior Drywall Framing And Sheathing Will Continue MEP Wall And Ceiling Rough-In Will Follow CMU And
Drywall Framing Steel Pans will be Erected at Gymnasium Bleachers Concrete will be Poured at Gymnasium Bleachers Roofing will Continue Sheetrock Installation will Commence Tape and Bed will Commence
LOOKING AHEAD