Local Government Case Study – Fairfax County Jennifer L. Gorter, PE, CEM Fairfax County Government...

Preview:

Citation preview

Local Government Case Study –

Fairfax County

Jennifer L. Gorter, PE, CEMFairfax County GovernmentFacilities Management Department (FMD)

July 11, 2008

Facilities Management Department

• Facilities Management Department (FMD) is responsible for managing 170+ facilities

• Operate and maintain 8 million gross SF• Pay utilities for 6 million gross SF

Note: This does not include facilities operated by Parks, Schools, Housing or Public Works

FMD also manages annual utility costs of approximately $10 million (and rising!)

Energy Goal was established in FY2001 – to reduce energy consumption and energy costs

Where We Began

• Baseline usage established

• Installed Energy Management Control Systems (EMCS) in existing buildings

• Made EMCS standard for new buildings

• Review new building designs

• Cost management

• Picked “low hanging fruit” using ESCO

Completed Energy Projects

• Public Safety Complex Meter Totalization• Lighting retrofit in facilities

– T-12 lamps consume 40W each– T-8 lamps consume 32W each– Reduced 4 lamps to 3 per fixture for additional watts

reduction, overall light output remains the same

• Lighting and Variable Frequency Drive retrofit at the Government Center Complex

Government Center Complex Energy Project Results

calendar year energy cost energy usage (kBtu) $/kBtu2005 $1,618,417.53 103,615,608 $0.015622006 $1,625,827.53 98,381,255 $0.01653

Energy project use reduction 5.05%Energy project cost reduction -0.46%Cost avoidance in 2006 $ $86,501.80Cost avoidance in 2007 $ $90,554.31

$177,056.10Two Year Total Cost Avoidance

ResultsTotal energy consumption

500,000,000

505,000,000

510,000,000

515,000,000

520,000,000

525,000,000

530,000,000

535,000,000

540,000,000

2001

2002

2003

2004

2005

2006

2007

kBtu

ResultsConsumption/gross SF

9092949698

100102104106108110

2001

2002

2003

2004

2005

2006

2007

kBtu/SF

Historical Electric Costs

$0.045

$0.050

$0.055

$0.060

$0.065

$0.070

$0.075

$0.080

$0.085

electric

Historical Gas costs

Flo

yd Is

ab

el

Katr

ina

$0.40

$0.60

$0.80

$1.00

$1.20

$1.40

$1.60

natural gas

Results• Even when consumption decreases,

expenditures continue increasing

480,000,000

500,000,000

520,000,000

540,000,000

560,000,000

580,000,000

600,000,000

2001

2002

2003

2004

2005

2006

2007

Est 2

008

Est 2

009

$0$2,000,000$4,000,000$6,000,000$8,000,000$10,000,000$12,000,000$14,000,000$16,000,000

kBtu $

Energy Benchmarking

$0.0

$0.5

$1.0

$1.5

$2.0

$2.5

$3.0

2005

Actual

2006

Actual

2007

Actual

2008

Estimate

2009

Estimate

109.0

110.0

111.0

112.0

113.0

114.0

115.0

116.0

117.0

118.0

119.0

Utility Cost/SF BOMA cost/SF kbtu/SF

ResultsConsumption and cost savings per year

460,000,000

480,000,000

500,000,000

520,000,000

540,000,000

560,000,000

580,000,000

600,000,000

baseline

actual

Total cost avoidance since 2001 exceeds $4 million

Results

• FMD’s Goal was 10% kBtu/SF reduction over 10 years (average 1%/ year)

• Between FY01-FY07, total kBtu/SF was reduced by 11.1%, which is 1.85% average reduction per year.

Where we are now

• Budget constraints = no funds for energy projects

• Past Capital Renewal budget requests have made primarily based on maintenance needs.

• Budget constraints = less funds for Capital Renewal

New Capital Renewal budget request priorities =

High energy user + High maintenance

Capital Renewal Combined with Energy Saving Strategies

John Marshall Library HVAC renovation resulted in 28.8% energy consumption savings

0

50,000

100,000

150,000

200,000

250,000

300,000

350,000

AprM

ayJ un J ul

AugSep

Oct

Nov

DecJ an Feb M

ar

Before

After

The Good, the Bad and the Ugly

• The Ugly - Limited Resources means it will take longer to implement energy saving opportunities

»Money»Staffing»Time

• The Bad – no additional project resources for the next several years

• The Good - FY2009 budget establishes one full time staff position as Countywide Energy Coordinator

Where We Are Going

• Develop new reduction goals

• Prioritize projects to meet multiple needs and limited funding

• Other possibilities available– Evaluate renewable energy technologies– Demand side management– Work with code officials and engineers– Commissioning and Re-Commissioning

Contact Information

Jennifer L. Gorter, PE, CEMFairfax County GovernmentFacilities Management Department

Projects, Engineering, & Energy

12000 Government Center Parkway

Suite 424

Fairfax, VA 22035

703-324-2808

jennifer.gorter@fairfaxcounty.gov

Recommended