I-405 BRT: Brickyard
Inline StationWSDOT Task Order and I-405 BRT
Budget Amendment
8/8/19
2
Why we are here
• Today we are here to inform today’s decision on two actions:
• A task order with WSDOT to advance engineering and develop a refined construction estimate for Brickyard in-line station—an element of the I-405 Bus Rapid Transit (BRT) project
• Budget amendment for I-405 BRT Project
3
Workshop held with Stakeholders to Refine Project
Workshop03/29Workshop Goals:
• Engage stakeholders
• Identify an interim and long-term solution for BRT
• Meet the objectives of ST3 and the vision of the I-405 Master Plan
4
2019 Legislative Session Authorized Tolling and Funding for Express Toll Lanes
Legislature Authorized:
• Second I-405 express toll lane in both directions
• I-405 direct access ramps at SR 522 and SR 527
Gov. Inslee signs SB 5825 into law on May 21
5
Workshop Outcome and I-405 ELG Recommendation
• Move BRT stations from outside ramps to inside stations to leverage state investment and Express Toll Lanes:
• Canyon Park inside station on WSDOT direct access ramp
• SR 522 inside station on WSDOT direct access ramp*
• Brickyard in-line station
*195th in-line station remains the long-term vision when funding becomes available
6
Funding Opportunities for Refined Project In-line station
WSDOT Funded
In-line station WSDOT Funded
ST funding*~$75M
• Reprogram funds from unneeded project components:
• Bus on shoulder north of Canyon Park
• I-405 outside ramp improvements
• Efficiencies from WSDOT partner projects and scope control
7
Refined project performance comparison Lynnwood to Bellevue
ST Express (existing) 57 MIN
ST3 representative project 50-55 MIN
I-405 BRT proposed refined project 46-51 MIN
I-405 BRT with express toll lanes 33-38 MIN
AM Peak hour travel times to Bellevue
8
WSDOT Task Order Scope
Brickyard inline station project development
• Project Administration
• 15% Conceptual Engineering and Environmental Review
• Permitting
• Traffic Engineering including an Access Revision Report
• Community Outreach
• Cost estimating services
• Value Engineering and Cost Estimate Validation Process
• Development of RFQ documents/administer solicitation/short listing
9
Next Steps
• Develop the conceptual engineering, including a cost estimate for Brickyard in-line station
• Complete conceptual engineering, environmental review and cost estimating for all I-405 BRT elements
• Board decision on the project to be built in late 2020
10
Illustrative - Not to Scale
Approved Today’s Action Future Action
ALLOCATION $ COMMITMENTS
I-405 BUS RAPID TRANSIT: Authorized Project Allocation $258.24MP
roj.
De
v.
$2
58
.24
M
Co
nst
ruct
ion
Constr.F/D
11
Illustrative - Not to Scale
Approved Today’s Action Future Action
I-405 BUS RAPID TRANSIT: Board Approves Agreement $7.48M
F/D
Pro
j.
De
v.
$2
58
.24
M
Co
nst
ruct
ion
Constr.
ALLOCATION $ COMMITMENTS
Thank you.