HiRadMat safety preparation

Preview:

DESCRIPTION

HiRadMat safety preparation. Follow-up meeting 24 /06/2011. Processes. See Marion’s talk. Alarms. Instruction meeting f or CCC operators on Monday June 20th https:// edms.cern.ch/document/1149524/1 List of alarms consolidated Lot of them not yet operational - PowerPoint PPT Presentation

Citation preview

HiRadMat safety preparation

Follow-up meeting24/06/2011

Processes

• See Marion’s talk

Alarms• Instruction meeting for CCC operators on Monday June 20th• https://edms.cern.ch/document/1149524/1• List of alarms consolidated • Lot of them not yet operational• Operational procedure in being written

Beam commissioning low intensity

• Operational procedure approved• https://edms.cern.ch/document/1149525/2• Dry run outcome• https://edms.cern.ch/document/1149523/1• Additional DSO tests on Tuesday• First shot hit the dump !

First protons through TT60-TT66

DSO tests

B.846 works during next TS

• Met L. Colly• 2 x 2 lifting points• Load specification by FB• Will be installed during next TS

Evacuation hardware

• Met GS-ASE• Cable extension during next TS• Evacuation buttons and sirens will be installed

during the August TS.

Safety file descriptive part

• Still in work.