ADDENDUM NO. 3 Page 1
Florida Governmental Utility Authority (FGUA) Lift Station No. 6 Replacement Project
FGUA Project No. PSP09
Addendum No. 3
The following are revisions and/or clarifications to the Bid Documents (Drawings and
Technical Specifications).
A. QUESTIONS
1. Question: Should space become an issue onsite for stockpiled excavated
materials, is there another location relatively close to the site available for stock
piling?
Response: If the Contractor has a surplus of excavated material that cannot be
stored onsite, the FGUA will provide access to the areas as shown on the attached
aerials for stockpiling excavated materials. The limits for stockpiling shown on the
aerial are approximate. The Contractor will be responsible for coordinating with
the FGUA during construction to identify actual limits acceptable for stockpiling.
2. Question: According to the contract documents, substantial completion is to be 180 days. If the Generator and sound attenuated enclosure has a significantly lengthy lead time, will the SC date be reconsidered in order to prevent liquidated damages against the contractor? Response: The contract time has been extended to 210 calendar days to Substantial Completion, and 240 days to Final Completion to account for the lead time of the generator and sound attenuated enclosure. See Section D of this addendum for revisions to Sections 00020, 00100, 00300, & 00500.
B. CLARIFICATIONS
1. Attention is directed to the equipment slab detail on Sheet D1.01. Per Note 1, the
generator pad dimensions shown in the Slab Schedule are approximate and
subject to change based on the actual generator enclosure furnished meeting the
requirements of the Specifications. The generator pad dimensions shall be
minimum 1-foot larger than the generator enclosure on all sides.
C. DRAWINGS
1. Drawing D1.02
ADDENDUM NO. 3 Page 2
CHANGE the thickness of the generator pad shown on Drawing D1.02 to the
following.
D. TECHNICAL SPECIFICATIONS
1. CHANGE the paragraph in Specification Section 00020, Page 2 to read as
follows:
“The Successful Bidder shall be required to fully complete all Work to be performed
pursuant to this invitation to bid within 240 calendar days from and after the
Commencement Date specified in the Notice to Proceed.”
ADDENDUM NO. 3 Page 3
2. CHANGE the paragraph in Specification Section 00100, Article 11 – CONTRACT
TIMES, 11.01 to read as follows:
“11.01 Time is of the essence in the performance of the Work under this
Agreement. The "Commencement Date" shall be established in the Notice
to Proceed to be issued by the FGUA. Contractor shall commence the Work
within five (5) calendar days from the Commencement Date. No Work shall
be performed at the Project site prior to the Commencement Date. Any
Work performed by Contractor prior to the Commencement Date shall be at
the sole risk of Contractor. The Work shall be substantially completed within
210 calendar days from the Commencement Date. The date of substantial
completion of the Work (or designated portions thereof) is the date certified
by the Design Professional when construction is sufficiently complete, in
accordance with the Contract Documents, so FGUA can occupy or utilize
the Work (or designated portions thereof) for the use for which it is intended.
The Work shall be fully completed and ready for final acceptance by FGUA
within 240 calendar days from the Commencement Date (herein "Contract
Time").”
3. CHANGE the paragraph in Specification Section 00300, Article 6 – TIME OF
COMPLETION, 6.01 to read as follows:
“6.01 Bidder agrees that the Work will be Substantially Complete within 210
calendar days after the date when the Contract Times commence to run as
provided in Paragraph 2.03 of the General Conditions, and will be
completed and ready for final payment in accordance with paragraph
14.07.B of the General Conditions within 240 calendar days after the date
when the Contract Times commence to run, which days will be entered by
Owner into the Agreement as the Contract Times.”
4. CHANGE the paragraph in Specification Section 00500, Article 4 – CONTRACT
TIMES, 4.02, A to read as follows:
“A. The Work will be substantially completed within 210 calendar days after the
date when the Contract Times commence to run as provided in Paragraph
2.03 of the General Conditions, and completed and ready for final payment
in accordance with Paragraph 14.07 of the General Conditions within 240
calendar days from the date of the Contract Times commence to run.”
END OF ADDENDUM NO. 3
Mitchell Ranch WTP:
Approximate Address: 7937 MITCHELL RANCH ROAD, NEW PORT RICHEY, FL 34655
General area to be used for temporary storage of excavated material shown below within the Red oval.
Caution: overhead high-power electrical lines are present at the site (Yellow lines).
Recommended