EXECUTIVE SUMMARY
Typhoon Pablo (international name: Bopha) was the second typhoon that affected Mindanao after TS Sendong in the last 2 years. It is the 16th Tropical Cyclone that entered the Philippine Area of Responsibility (PAR) in 2012. On 04 December 2012 Typhoon Pablo made landfall over Baganga, Davao Oriental with maximum sustained winds of 185 kph near the center and gustiness of 220 kph. The strong winds damaged houses, roads, bridges, school buildings, churches, covered courts, public and private infrastructures. It also uprooted trees, coconut trees, toppled bananas and blown light materials. The coastal municipalities of Baganga, Boston and Cateel were the most devastated. As of 01 March 2013, a total of 537 fatalities, 2,271 injured and 51 missing were recorded in Davao Oriental.
The Post Disaster Needs Assessment (PDNA) for the Province of Davao Oriental was conducted through the leadership of the Office of Civil Defense and the Regional Disaster Risk Reduction and Management Council (DRRMC) XI in cooperation with the Provincial DRRMC and the Municipal DRRMCs. The field assessment was done on 21-30 January 2013 in Davao Oriental covering 7 municipalities; Baganga, Boston, Cateel, Caraga, Manay, Tarragona and Gov. Genoroso; and Mati City.
In Davao Oriental, Typhoon Pablo resulted to a total damage of PhP12,802,604,657.17 and the amount needed for recovery and reconstruction is PhP14,350,733,106.33. The damaged sectors and recommended funding for recovery and reconstruction are as follows:
1. Infrastructure
Total estimated damage to infrastructures is PhP4,166,813,356.17. This sector also accounted all structures such as roads, bridges, irrigation facilities, flood control/seawall and all infrastructures related to education, tourism, mining, power, water, telecommunications and government. Education and health infrastructure yielded the highest amount of damage. A total amount of PhP5,387,919,153.33 is needed for the reconstruction of the infrastructure sector.
2. Livelihood
Total estimated damage to livelihood is PhP6,683,692,681.00.
This sector covers Agriculture, Tourism, Mining and ITS (Industry, Trade and Services). A total amount of PhP2,448,761,698.00 is
ii
needed for the reconstruction of the livelihood sector. Agriculture accounts for 70 percent of the total recovery needs.
3. Social
Total estimated damage to social is PhP261,080,720.00. This
sector focuses on the frontline services of the government towards society or community. This includes 3 sub-sectors: shelter, health and education. A total amount of PhP483,177,255.00 is needed for the reconstruction of the social sector. Fifty six percent of the total needs for the Social Sector is for programs and projects related to Shelter.
4. Resettlement
Total estimated damage to housing is PhP1,691,017,900.00.
This sector includes housing, land acquisition and land development. A total amount of PhP6,030,875,000.00 is needed for resettlement sector.
Summary of Damage and Recommended Funding for Recovery and Reconstruction
SECTOR
DAVAO ORIENTAL
DAMAGES
RECOMMENDED FUNDING FOR
RECOVERY/
RECONSTRUCTION
TOTAL 12,802,604,657.17 14,350,733,106.33
INFRASTRUCTURE 4,166,813,356.17 5,387,919,153.33
Roads 61,892,810.64 84,866,013.30
Bridges 275,100,000.00 353,450,000.00
Flood Control/Sea Wall 209,109,440.00 261,386,800.00
Irrigation Facilities 188,800,000.00 222,000,000.00
Health Infrastructure 2,115,157,692.31 2,749,705,000.00
Education Infrastructure 849,110,000.00 1,103,843,000.00
Government Infrastructure 288,845,720.00 341,291,436.00
Tourism Infrastructure 22,620,000.00 29,406,000.00
Mining Infrastructure 4,720,000.00 5,428,000.00
Power Infrastructure 112,877,141.22 139,877,752.03
Water Infrastructure 5,680,552.00 42,765,152.00
Telecommunication
Infrastructure 32,900,000.00 53,900,000.00
LIVELIHOOD 6,683,692,681.00 2,448,761,698.00
Agriculture 469,772,115.00 1,440,161,698.00
Tourism 5,528,200,000.00 5,200,000.00
Mining - 3,400,000.00
Industry, Trade, and Services 685,720,566.00 1,000,000,000.00
SOCIAL 261,080,720.00 483,177,255.00
iii
Shelter 227,953,000.00 271,980,000.00
Health (WASH) - 30,746,800.00
Health (Nutrition) 396,000.00 144,110,000.00
Education 32,731,720.00 36,340,455.00
RESETTLEMENT 1,691,017,900.00 6,030,875,000.00
Housing 1,691,017,900.00 3,108,125,000.00
Shelter (Land Acquisition) - 780,540,000.00
Shelter (Land Development) - 2,142,210,000.00
TABLE OF CONTENTS INTRODUCTION Hazard Assessment 1 Typhoon Pablo 2 Vulnerability and Exposure 2 INFRASTRUCTURE SECTOR Damage and Needs Assessment 6 Recommended Recovery/ Reconstruction Needs 11 Implementation Framework 38 Recommendation 38 LIVELIHOOD SECTOR Damage and Needs Assessment 41 Recommended Recovery/ Reconstruction Needs 43 Implementation Framework 59 Recommendation 60 SOCIAL SECTOR Damage and Needs Assessment 65 Recommended Recovery/ Reconstruction Needs 69 Implementation Framework 75 Recommendation 75 RESETTLEMENT Damage and Needs Assessment 79 Recommended Recovery/ Reconstruction Needs 80 Implementation Framework 83 Recommendation 83
1 | P a g e
INTRODUCTION On 04 December 2012, Typhoon Pablo made landfall in the Davao Region. Carrying strong winds, Typhoon Pablo devastated several municipalities in Region 11 particularly in the provinces of Davao Oriental and Compostela Valley. Houses were damaged, trees were uprooted and landslides occurred. President Benigno Simeon Aquino III declared a State of National Calamity through Proclamation No. 522 on 07 December 2012. The PDNA Report is divided into three (3) parts; Hazard, Vulnerability and Exposure Assessment, Damage; Losses and Needs Assessment; and Social Impact Assessment. HAZARD ASSESSMENT The Philippine Archipelago is bounded by Pacific Ocean on the east and West Philippine Sea on the west. It is also situated along the Pacific Ring of Fire and part of the Western Pacific Arc characterized by the active volcanoes. The country’s terrain is generally characterized as mountainous. Given its location and geologic characteristics, the Philippines is vulnerable to multiple natural hazards such as earthquakes and typhoons. Located in the Southeastern portion of Mindanao, Davao Region is bounded by the Philippine Sea in the East; provinces of Bukidnon, Surigao del Sur and Agusan del Sur on the north; and by Central Mindanao provinces in the West. Every year, an average of 20 typhoons crosses the country. Statistics from 1883-1990 showed that an average of 1 tropical cyclone per year crossed Mindanao every 10 years. However, in the last 15 years, there were 6 tropical cyclones that crossed Mindanao. For two years in a row Mindanao was hit by Typhoon; TS Sendong in 2011 and Ty Pablo in 2012 both of which hit Mindanao in the month of December. Seven Tropical Cyclones either made landfall or crossed Davao Provinces including Typhoon Pablo from 1948 – 2012. One Tropical Cyclone hit Davao Oriental every 20 years.
2 | P a g e
TYPHOON PABLO Typhoon Pablo (International name: Bopha) was the second Typhoon that affected Mindanao and the 16th Tropical Cyclone that entered the Philippine Area of Responsibility (PAR) in 2012. On 04 December at 4:45 am Typhoon Pablo first made landfall over Baganga, Davao Oriental with maximum sustained winds of 175 kilometers per hour (kph) and gustiness of 210 kph. It slightly weakened to sustained winds of 160 kph and gustiness of 195 kph after its landfall, traversed the Provinces of Compostela Valley and Bukidnon, slightly accelerated as it moved towards Southern-Negros Oriental. It made second landfall over South of Dumaguete City on the same day at 5:30 pm and weakened further to sustained winds of 140 kph and gustiness of 170 kph as it moved toward Northern Palawan. On 05 December 2012 at 8:00 am Typhoon Pablo made land fall for the third time over Roxas City, Palawan. On 08 December 2012, Pablo downgraded into a tropical storm as it headed towards the Ilocos Provinces and La Union. On 09 December 2012, it further weakened into tropical depression as it moved towards Ilocos Norte and subsequently into a low pressure area prior to its dissipation. Typhoon Pablo was the strongest Tropical Cyclone to make landfall in 2012; strongest since Typhoon Juan in 2010; strongest typhoon to cross Mindanao since Typhoon Nitang in 1984 and strongest to cross Davao provinces since Titang in 1970. VULNERABILITY AND EXPOSURE The coastal municipalities of Baganga, Boston and Cateel in the Province of Davao Oriental were the most affected by Typhoon Pablo. Strong winds caused damage to houses most of which were made of light materials. Palm trees which covered most of the mountainous areas of region were either uprooted or their leaves and fruits fallen. Upland settlements like the Municipality of New Bataan suffered from landslides and rockslides brought
Source: DOST-PAGASA
Figure 1. Typhoon Pablo Track
3 | P a g e
about by the amount of rainfall poured by Typhoon Pablo and the scarcely vegetated mountains. On 04 December 2012, over a five-hour period starting 7:45 am, rainfall recorded in the Municipality of Maragusan which is about 19.5 km south of New Bataan range from heavy (7-15 mm/hr) to intense rainfall (15-30 mm/hr). Highest amount of rainfall reached 51.82 mm/hr recorded at 6:45 am. In New Bataan alone, debris flow deposit was estimated at 25-30 million cubic meters.
Region 11’s topography is characterized by mountain ranges extending in the northern central and north western area and along the western border with uneven distribution of plateaus and lowlands. Only Twenty six percent of the total land area of the region has slope range of 0-8 % which is suitable for settlement, agricultures and industries.
Figure 2. Landslide and Flood Susceptibility Map of Manat Quadrangle
Source: Mines and Geosciences Bureau
4 | P a g e
Figure 3. Map of Typhoon Pablo Affected Population
Thirty four (34) provinces, 40 cities and 318 municipalities were affected by Typhoon Pablo. Mining and logging operations exists in areas affected by Typhoon Pablo in Region XI. Table 1.Affected Population in Region XI Region/Province/ Mun/ City Brgys Families Persons Davao Region 1,162 986,733 4,295,416 Compostela Valley 252 142,040 710,199 Davao del Norte 223 169,485 847,440 Davao del Sur 505 563,428 2,178,877 Davao Oriental 182 111,780 558,900
Source: NDRRMC Final Situational Report on Typhoon PABLO
Source: United Nations Office for the Coordination of Humanitarian Affairs
5 | P a g e
A total of 1,248 fatalities, 2,916 injured and 797 missing were reported for all the regions affected by Typhoon Pablo as of 01 March 2013. Region XI has the highest number of casualties with 1,007 dead, 2,529 injured and 524 missing. The table below shows the breakdown of fatalities in the affected regions and provinces Table 2. Casualties of Typhoon Pablo
Regions No. of Fatalities No. of Fatalities per Province IV-B 3 Palawan VI 1 Capiz VII 10 Siquijor (2), Cebu (6) and Negros Oriental (2) VIII 3 Northern Samar (1), Southern Leyte (1)
and Biliran (1) IX 1 Zamboanga City X 15 Misamis Occidental (2), Misamis Oriental (6),
Bukidnon (6) and Cagayan de Oro City (1) XI 1,188 Davao Oriental (537), Compostela Valley
(651) XII 8 General Santos City CARAGA 19 Surigao del Sur (5), Surigao del Norte (1) and
Agusan del Sur (13) Total 1,248
Source: NDRRMC Final Situational Report on Typhoon PABLO
6 | P a g e
INFRASTRUCTURE SECTOR BACKGROUND This chapter covers the assessment for the Infrastructure Sector which basically manifests the economic features of the structural engineering of all physical assets of the Province of Davao Oriental, namely: roads, bridges, ports, water supply, irrigation facilities, flood controls/sea walls/drainage, power, telecommunications and other public buildings, including health facilities. The existence of good infrastructure services complements the accessibility of opportunities and services of other sectors. In the case of Davao Oriental, these are likely useful in agriculture sector since majority of the people in the province are engaged in agricultural activities. The definitive factor for this assessment would be the identification of priority projects for restoration and recovery in the hardest hit municipalities: Boston, Cateel and Baganga and lesser affected municipalities of Caraga, Manay, Tarragona, Governor Generoso and the City of Mati. DAMAGE ASSESSMENT This chapter shows the extent of damages to physical assets of Davao Oriental caused by Typhoon Pablo. Transportation (Roads and Bridges)
Table 3 shows the summary of damages on different classification of existing infrastructures of the province per municipality. In particular, the health sub-sector reflects the highest cost on damages which is equivalent to PhP2,115,157,692.31. Damages on roads and bridges amounted to PhP336,992,810.64. Cases on road damages are caused by eroded soil under its geologic location where parts of its path collapsed or silted due to massive rainfall and fallen debris from trees or structures. With the hard road conditions, it is difficult for the people to transport their goods or travel to neighboring towns. Likewise, basic services will be hardly accessible to residents influenced by road damages. Meanwhile damages/destruction of bridges was basically caused by strong current of rivers/waterways. Inaccessibility of these linking facilities may result in the isolation of several communities and resources such as food, medicines and basic services will be scarce.
7 | P a g e
Flood Controls On the context of flood controls, the destruction of sea walls especially in Cateel Municipality was caused by storm surge, debris from the sea, falling trees and structures. This implies that there will be greater risks or vulnerability of the town from natural hazards especially on tsunami and storm surges if the sea walls are not restored. Lastly, culverts on drainage systems were damaged by enormous amount of sediments brought by heavy flooding. While these pipe culverts stay unrepaired or not replaced, the covered area for the pipe services will be vulnerable to flooding mainly because water from frequent rain and flowing waterways has no exit. Flood control and sea wall structures incurred damages in the total amount of PhP209, 109,440.00.
Agriculture Agricultural production is the main source of livelihood of Davao Oriental. This sector presents damages on irrigation facilities while its components are covered as infrastructural support for agriculture production. Specifically, a total of PhP188,800,000.00 worth in damages of irrigation facilities were recorded, mostly located within the towns of Cateel, Baganga and Caraga which are avenues for rice production. The effects of these damages to rice farmers are unexplainable since they are dependent on their specific crop. Restoration of these irrigation facilities requires not just great amount but time as well since the component dams and canals were generally destroyed. This may force farmers to shift to other crops which are low income generating. Health The health services in Davao Oriental practically reached all 183 barangays of Davao Oriental thru Barangay Health Stations, Rural Health Centers, District Hospitals and one Provincial Hospital. Typhoon Pablo scoured these facilities particularly in the first congressional district of the province, Municipalities of Boston, Cateel, Baganga, Caraga, Manay and Tarragona. In this section, damages on physical assets of health facilities are presented mostly on its buildings by municipality totaling to PhP 2,115,157,692.31. The concentration of damages is mainly in the three hardest hit municipalities of Boston, Cateel and Baganga. One (1) District Hospital covering the three municipalities is located in Brgy. Poblacion, Cateel. These health structures were destroyed primarily by strong winds leading them to stand roofless while some light engineered health stations were totally destroyed.
8 | P a g e
The delivery of basic health services such as immunization, pre-natal check up, and malaria/schistosomiasis treatments were acutely affected. Without these facilities, people are vulnerable to illnesses and epidemics as well as increase in maternal and infant mortality. It is imperative that health services be restored in all affected areas to avoid or minimize these effects.
Education Both public and private schools equally suffered destruction on its facilities particularly in the municipalities of Boston, Cateel, Baganga, Caraga and Manay. However, as a sub-sector of infrastructure, only the school’s physical assets like buildings/structures and its water and sanitations facilities are featured in this Sector. Equipage such as educational materials, office/faculty materials, tables/desks, arm chairs, computers and the like are included in the Social Sector. This section shows the reported total damages in school facilities in the amount of PhP849,110,000.00 on its physical assets. Much of this damage cost were reflected under the totally damaged facilities category equating to PhP693,050,000.00 or 81.5% of the total damage that basically concentrates along municipalities of Boston, Cateel, Baganga and Caraga. The damages were mainly caused by strong winds that rendered the structures roofless or even totally destroyed. Schools are not only avenue for learning but also automatically cater victims of catastrophes as commonly practiced in the Philippines. Oftentimes, schools are venues of big assemblies or gathering in the community.
Government Buildings
This section covers the damages in government establishments such as Municipal Halls, Barangay Halls, Social Halls, Purok structures, slaughter houses, public terminals, Barangay Pharmacies and Day Care Centers. The total reported damage of this sector amounts to PhP288,845,720.00. The destruction of these public buildings is generally caused by strong winds, falling trees and other hard debris. These establishments are essential for the execution of an effective coordination/communication from the Purok level up to the municipal government. The absence of such structure can lead to uncoordinated actions of people and government personnel because they have nothing to provide as an office, shelter/shade while delivering public service to their respective community. Tourism The Province of Davao Oriental is blessed with amazing cultural features and tourism destinations. Hundreds of tourists, both local and foreign, are in awe
9 | P a g e
of its astounding sceneries. The people hold great pride for possessing such natural richness. The Aliwagwag Falls and Mantunao Eco-Park in Cateel; Cabugao Island, coral garden, caves and rivers in Boston; and San Victor Island and hot springs in Baganga are just among of the province’s tourist sites. Furthermore, long shorelines with captivating beach resorts are in abundance in the Province of Davao Oriental. The province also offers amenities and tour packages to islets and coves. As a result of Typhoon Pablo, beach resorts, guest houses/lodging houses to include the municipal tourism guest houses, cultural sites like baywalk and parks and old churches were damaged especially in terms of structures, machine, equipment, stocks and trees and plants for the natural formations like the rivers, falls, islands, coves and caves, coral garden and eco-park. The total damages on parks alone reached the amount of PhP22,620,000.00, marking a great deal of investments to restore partly what was lost on the people’s heritage. Mining The mining activities in the province generally provide income or job opportunities to the local populace. Davao Oriental has a geology that is unique to the rest of the Philippines. The province is endowed with mineral resources such as gold, silver, copper, iron, chromite, manganese, nickel, silica, magnesite, sand and gravel. On this sector, there are only two (2) municipalities affected by Typhoon Pablo with mining activities, namely; municipality of Boston and Baganga, Davao Oriental. There are two exploration permits for gold in Boston, Davao Oriental covering a total of four thousand one hundred fifty two hectares (4,152 has). While there are two small scale mining for iron and a sand and gravel operating, covering a total of forty one (41) hectares in Baganga, Davao Oriental. Mining sector incurred damages in the total amount of PhP4, 720,000.00. Power Majority of Davao Oriental towns are catered by the power service of a private power company, the Davao Oriental Electric Cooperative (DORECO). Typhoon Pablo conspicuously devastated the power lines and sub-stations, especially in the three (3) hardest hit municipalities which is equivalent to PhP112,877,141.22. DORECO immediately responded to this endeavor and brought back power services within three (3) days in the lightly affected areas and within twenty (20) days in the three municipalities. Despite the initial restoration effort of DORECO, It could not restore power on all barangays in the first district. As of February 10, 2013, power is restored only along the highways and capital towns in the municipalities of Boston,
10 | P a g e
Cateel and Baganga. Power services are yet to be fully restored in fifty two (52) far flung barangays. Water Supply Water is an essential element for survival. In the context of accessibility to potable water, the municipalities of Boston, Cateel, Baganga and Caraga are experiencing scarcity of water resources due to damaged water supply facilities. The figures below shows the summary of damages on water supply facilities incurred from the typhoon. This section summarizes the reported damages on Water Supply sub-sector of the province. Of the eight (8) proposed LGUs to be covered by the PPDA team, only the municipalities of Boston, Cateel, Baganga and Caraga apparently sustained damages on water supply systems. On the four (4) municipalities, a total of twenty two (22) Water Supply firms/organizations were reported by the municipal LGUs, wherein the municipality of Cateel is reflected to have the most water system damages. A total damage to water system facilities is PhP5, 680,552.00. Without functional water system facilities, residents will be forced to utilize unsafe water sources like rivers and hand pumps which will eventually affect their health conditions. Moreover, diseases and epidemics are more likely to occur. It is not only the residential community who will be affected but also other sectors that are dependent on water like agriculture, industry and trade, government and non-government establishments. Telecommunications Cellular towers were damaged in the three (3) hardest hit municipalities because of strong winds and falling/flying debris from structures or nearby trees. Telecommunications incurred a total of PhP32,900,000.00 cost in damages. Cellular towers are aid in electronic communication which provides linkages for the residents of these towns to relatives, friends and in business transactions. Without these structures, they are more likely to be isolated in terms of information driven activities. These facilities also provide opportunities for marketing of local products and services and further disruption will eventually result to further losses on income for the market populace. Immediate restoration of these facilities will help in the recovery of the damaged towns through strengthening coordination process between National and Local Government levels in the subject of funding assistance and the corresponding technical requirements.
11 | P a g e
RECOMMENDED RECOVERY/ RECONSTRUCTION NEEDS To respond to the pressing demand for restoration of the communities destroyed by Typhoon Pablo, the Province of Davao Oriental has determined priority projects which cover necessary activities to repair what has been damaged, restore what has been lost, regain the people’s pride and build back better communities.
In line with the sector’s coverage on physical assets, several Plans, Programs and Activities from National and Local Government Units were identified.
Table 3. Summary of Damages and Recommended Recovery/ Reconstruction Needs in the Infrastructure Sector
INFRA SUB-SECTORS REPORTED DAMAGES (PhP)
RECOMMENDED RECOVERY/RECONSTRUC
TION NEEDS (PhP)
Roads 61,892,810.64 84,866,013.30 Bridges 275,100,000.00 353,450,000.00 Flood Control and Seawall Infrastructure 209,109,440.00 261,386,800.00 Irrigation Facilities 188,800,000.00 222,000,000.00 Health Infrastructure 2,115,157,692.31 2,749,705,000.00 Education Infrastructure 849,110,000.00 1,103,843,000.00 Government Infrastructure 288,845,720.00 341,291,436.00 Tourism Infrastructure 22,620,000.00 29,406,000.00 Mining Infrastructure 4,720,000.00 5,428,000.00 Power Infrastructure 112,877,141.22 139,877,752.03 Water Infrastructure 5,680,552.00 42,765,152.00 Telecommunications Infrastructure 32,900,000.00 53,900,000.00
GRAND TOTAL 4,166,813,356.17 5,387,919,153.33 The table above shows the summary of recovery/reconstruction needs of every sub-sector on infrastructure. These are composed of identified projects per municipality as listed in the following table:
12 | P a g e
Table 4. Recommended Recovery/ Reconstruction Needs A. Roads
RA
NK
PRIORITY PROJECTS/
ACTIVITIES (description)
LOCATION/
SITES
AMOUNT
IMPLEMENTING
AGENCIES
TIMELINE/
IMPLEMENTATION
PERIOD
REMARKS
REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
2 Repair of 2 km municipal
road Boston 134,160.00 167,700.00 P/MLGU 5 days
3 Repair of Barangay Roads All 8 Brgys. In
Boston 5,600,000.00 7,000,000.00 LGU Boston 30 days
4 Repair of 96.54 km. Brgy.
Roads
Brgy. San
Miguel, and
Alegria, Cateel
19,707,692.00 24,634,615.00 LGU Cateel 50 days
6 Repair of 23.31 km.
Provincial Roads
Taytayan-
Dayong, NHJ
Cateel-San
Alfonso-Aragon,
NHJ Cateel-
Abejod, Sta.
Felomina-Mainit,
Cateel
4,758,508.00 5,948,135.00 PLGU 25 days
7 Repair of 3.8 km. municipal
road Cateel 268,320.00 335,400.00 P/MLGU 7 days
8 Repair of 185.29 km.
Barangay Roads
Brgys. Mahan-
ub, Ban-ao,
Batiano and
Kinablangan,
Baganga
8,957,480.00 11,196,850.00 LGU Baganga 2 months
13 | P a g e
11 Repair of 27.22 km.
Provincial Roads
San Isidro-Mikit-
Campawan, NHJ
Baganga-
Binondo, NHJ
Baganga-
Batiano, Baganga
1,154,113.60 1,442,642.00 PLGU 30 days
12 Repair of 4.4 km municipal
road Baganga 268,320.00 335,400.00 P/MLGU 9 days
16 Repair of 149.4 km.
Barangay Roads
Brgys. Pichon,
Palma Gil and
Alvar, Caraga
4,494,200.00 5,617,750.00 LGU Caraga 50 days
17 Repair of 32.049 km.
Provincial Roads
NHJ San Jose-
DLB, San Jose-
Mercedes, NHJ
Caraga-San
Pedro, San
Miguel-Caningag,
Caraga
793,797.60 992,247.00 PLGU 30 days
18 Repair of 2.8 km. municipal
road Caraga 200,920.00 251,150.00 P/MLGU 5 days
22 Repair of 93.83 km.
Barangay Roads
Brgys. San
Ignacio, Old
Macopa and
Taocanga roads,
Manay
3,700,510.40 4,625,638.00 LGU Manay 3 months
23 Repair of 48.74 km.
Provincial Roads
NHJ Manay-Rizal,
Holy Cross-Buan,
Guza-San
Fermin, Manay
1,921,989.60 2,402,487.00 PLGU 2 months
24 Repair of 4.2 km municipal
road Manay 335,400.00 419,250.00 P/MLGU 9 days
25 Concreting of 500m Upper
Limot-Cangusan Road Tarragona -- 7,500,000.00 P/MLGU 3 months
14 | P a g e
section
27 Repair of 74.77 km.
Barangay Roads
Brgys. Maganda,
Lucatan and
Limot, Tarragona
1,168,486.40 1,460,608.00 LGU Tarragona 3 months
28 Repair of 42.46 km
Provincial Roads
Baguan-Lucatan-
Longagon Road,
Tarragona
663,553.60 829,442.00 PLGU 2 months
29 Repair of 1.8 km. municipal
road Tarragona 134,160.00 167,700.00 P/MLGU 5 days
32
Repair of Surigao del Sur -
Davao Oriental Coastal
roads
Boston to Mati 1,635,473.04 2,044,341.30 DPWH 1 month
33 Repair of 181.92 km.
Barangay Roads City of Mati 2,859,766.40 3,574,708.00 LGU Mati 5 months
34 Repair of 181.93 km
Provincial Roads City of Mati 1,808,520.00 2,260,650.00 PLGU 5 months
36 Repair of 18 km. municipal
road City of Mati 1,207,440.00 1,509,300.00 P/MLGU 2 weeks
37 Repair of Mati-Maragusan
road
Mati to
Maragusan 120,000.00 150,000.00 DPWH 1 month
SUB-TOTAL 61,892,810.64 84,866,013.30
15 | P a g e
B. Bridges
RA
NK
PRIORITY PROJECTS/
ACTIVITIES (description) LOCATION/ SITES
AMOUNT
IMPLEMENTING
AGENCIES
TIMELINE/
IMPLEMENTATION
PERIOD
REMARKS REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
1 Construction of 100 ln.m.
footbridges
Brgys. San Jose,
Cabasagan and
Sibahay, Boston
1,500,000.00 4,000,000.00 LGU Boston 3 months
Bridge collapsed
due to
flashfloods
2 Construction of NHJ 45 ln.m.
Lomao Bridge
Brgy. San Miguel,
Cateel 28,800,000.00 36,000,000.00 DPWH/LGU 12 months
2 spans deflected
and scoured
approaches - "A
& B"
3
Construction of 2 units Bailey
panel bridge (9 ln.m. and 18
ln.m.)
Brgy. Taytayan,
Cateel 4,320,000.00 5,400,000.00 DPWH/LGU 4 months
Dilapidated
lumbers and
panels were seen
on site
4 Construction of 170 ln.m.
footbridge
Brgy. Maglahus,
Cateel 4,000,000.00 5,000,000.00 DPWH/LGU 6 months
Bridge collapsed
due to
flashfloods
5 Repair of Bridge Abutments Brgy. Taytayan,
Cateel 4,000,000.00 6,000,000.00 DPWH/LGU 4 months
Installation of
ramp was
established at
damaged
approach
6 Repair of abutments (151.6 m
bridge) Udiongan, Cateel 1,750,000.00 4,400,000.00 DPWH/LGU 3 months
Bridge
approaches were
scoured
16 | P a g e
7 Construction of 5 units - 21 ln.
m. Bailey Panel Bridge
Brgys.
Campawan,
Mahan-ub, Mikit,
Batiano and San
Isidro, Baganga
17,600,000.00 22,000,000.00 DPWH/LGU 6 months
Bridge
approaches were
scoured
8 Construction/Repair of 225
ln.m.Teodoro Palma Gil Bridge
San Antonio,
Caraga 101,920,000.00 127,400,000.00 DPWH/LGU 24 months
9 spans collapsed
from approached
"B" due to
flashfloods
9 Construction/Repair of Caraga
Bridge San Jose, Caraga 101,920,000.00 127,400,000.00 PLGU/MLGU 24 months
9 spans collapsed
from approach
"B" due to
flashfloods
10 Construction of 15 m Bailey
panel bridge
Brgy. Alvar,
Caraga 2,400,000.00 3,000,000.00 DPWH/LGU 2 months
In line with the
Building Back
Better concept
11 Construction of 12 m Bailey
panel bridge
Brgy. San Luis,
Caraga 1,920,000.00 2,400,000.00 PLGU/MLGU 2 months
In line with the
Building Back
Better concept
12 Construction of 75 ln.m.
hanging bridge
Brgy. Lamiawan,
Caraga 2,400,000.00 3,000,000.00 DPWH/LGU 4 months
Totally damaged
due to flashflood
13 Repair of 20 cu.m. abutments Brgy. Sobrecarey,
Caraga 200,000.00 1,000,000.00 PLGU/MLGU 40 days
Abutments "A &
B" were
damaged due to
flood
14 Construction of 50 ln.m.
footbridge
Brgy. Taocanga,
Manay 500,000.00 2,500,000.00 P/MLGU 2 months
In line with the
Building Back
Better concept
15 Repair of bridge abutments Brgy. Limot,
Tarragona 400,000.00 2,000,000.00 PLGU/MLGU 1 month
Approach "A"
was totally
damaged due to
flashfloods
17 | P a g e
16 Construction of 15 ln.m. bailey
panel bridge
Brgys. Don
Salvador Lopez,
Mati
960,000.00 1,200,000.00 PLGU/MLGU 2 months
Dilapidated
lumbers and
panels were seen
on site
17 Construction of 40 meter
hanging bridge
Brgy Central,
Mati 480,000.00 600,000.00 P/CLGU 1 month
Totally damaged
due to
flashfloods
18 Repair of bridge abutment (13
cu.m.)
Brgy. Poblacion,
Manay 30,000.00 150,000.00 DPWH/LGU 1 month
Abutments "A &
B" were
damaged due to
flood
SUB-TOTAL 275,100,000.00 353,450,000.00
18 | P a g e
C. Flood Control and Seawall Infrastructure
RA
NK
PRIORITY PROJECTS/
ACTIVITIES (description)
LOCATION/
SITES
AMOUNT
IMPLEMENTING
AGENCIES
TIMELINE/
IMPLEMENTATION
PERIOD
REMARKS REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
1 Construction of 210 ln.m. Sea
Wall
Brgy. Poblacion,
Boston 10,080,000.00 12,600,000.00 P/MLGU 9 months
In line with the
Building Back
Better concept
2 Construction of 450 ln.m. Flood
Control
Brgys. San Jose-
Caatihan-
Simulao, Boston
21,600,000.00 27,000,000.00 P/MLGU 6 months
50 meter existing
flood control on
site and In line
with the Building
Back Better
concept
3
Construction of 4-unit box
culverts and installation of 20-
line pipe culverts
Brgys. Carmen-
sitio weig, San
Jose and
Caatihan, Boston
6,209,600.00 7,762,000.00 P/MLGU 12 months
In line with the
Building Back
Better concept
4 Construction of 515 ln.m. flood
control
Brgy. Taytayan,
Cateel 24,000,000.00 30,000,000.00 P/MLGU 8 months
In line with the
Building Back
Better concept
5 Construction of 120 ln.m. Sea
Wall
Brgy. Poblacion,
Cateel 5,760,000.00 7,200,000.00 P/MLGU 7 months
In line with the
Building Back
Better concept
6 Construction of 105 ln.m. flood
control Udiongan, Cateel 5,040,000.00 6,300,000.00 P/MLGU 6 months
In line with the
Building Back
Better concept
7 installation of 25-line pipe
culverts
Brgys. Alegria,
Cateel 3,200,000.00 4,000,000.00 P/MLGU 12 months
In line with the
Building Back
19 | P a g e
Better concept
8 Construction of 800 ln.m. Flood
Control
Brgy. Campawan,
Baganga 38,400,000.00 48,000,000.00 P/MLGU 14 months
In line with the
Building Back
Better concept
9 Construction of 350 ln.m. flood
control
Brgy. Mahan-ub,
Baganga 16,800,000.00 21,000,000.00 P/MLGU 6 months
In line with the
Building Back
Better concept
10 Construction of 90 ln.m. Sea
Wall
Brgy. Poblacion,
Baganga 4,320,000.00 5,400,000.00 P/MLGU 10 months
In line with the
Building Back
Better concept
11
Construction of 2-unit box
culverts and installation of 24-
line pipe culverts
Brgys. San Isidro
(2), Bobonao (3),
Mahan-ub (2),
Salingcomot (3),
San Isidro (2),
Kinablangan (4),
Lucod (3), San
Victor (3) and
Mikit (4),
Baganga
14,240,640.00 17,800,800.00 P/MLGU 10 months
In line with the
Building Back
Better concept
12 Construciton of 600m line canal Brgy. Batiano,
Baganga 1,200,000.00 1,500,000.00 P/MLGU 1 month
In line with the
Building Back
Better concept
13
Construction of 90 ln.m.
Manorigao river bank
protection
Brgy. San
Antonio, Caraga 9,936,000.00 12,420,000.00 P/MLGU 12 months
In line with the
Building Back
Better concept
14 Construction of 150 ln.m. Flood
Control
Brgy. San Jose,
Caraga 7,200,000.00 9,000,000.00 P/MLGU 12 months
In line with the
Building Back
Better concept
20 | P a g e
15
Construction of 2 units box
culverts and installation of line
pipe culverts
Brgys. Palma Gil
(4), Pichon (5),
NHJ Caraga-San
Pedro (2), Alvar
(3), Tiblawan-
Sobrecarey (3),
San Miguel-
Caningag (4) and
Santiago (5),
Caraga
3,353,600.00 4,192,000.00 P/MLGU 1 month
In line with the
Building Back
Better concept
16 Construction of 400 ln.m. Sea
Wall
Brgys. Poblacion
and San Ignacio,
Manay
19,200,000.00 24,000,000.00 P/MLGU 12 months
In line with the
Building Back
Better concept
17
Construction of 2 box culverts
and installation of 15 line pipe
culverts
NHJ Manay-Rizal,
Guza-San
Fermin, and
Brgy. Holy Cross,
Manay
2,632,000.00 3,290,000.00 P/MLGU 3 months
In line with the
Building Back
Better concept
18
Construction of 3 units box
culverts and installation of 4
line pipe culverts
Brgys. Lucatan,
Maganda, Limot
and Dadong,
Tarragona
3,720,000.00 4,650,000.00 P/MLGU 4 months
In line with the
Building Back
Better concept
19 Construction of 108 ln.m. flood
controls
Brgys. Mayo,
Mati 5,184,000.00 6,480,000.00 P/MLGU 12 months
In line with the
Building Back
Better concept
20
Construction and reinstallation
of 5 lines pipe culverts and box
culverts
Brgys. Sainz,
Bobon and
Lawigan, Mati
City
5,433,600.00 6,792,000.00 P/MLGU 7 months
In line with the
Building Back
Better concept
21 Construction of 800m line canal
Brgy.
Tagbinogna, Mati 1,600,000.00 2,000,000.00 P/MLGU 2 months
SUB-TOTAL 209,109,440.00 261,386,800.00
21 | P a g e
D. Irrigation Facilities R
AN
K
PRIORITY PROJECTS/
ACTIVITIES (description) LOCATION/ SITES
AMOUNT
IMPLEMENTING
AGENCIES
TIMELINE/
IMPLEMENTATION
PERIOD
REMARKS REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
1
Repair and restoration of the
CCIP -Construction of Cateel
Irrigation Project: Diversion
Work & Canalization
Brgy, Aragon,
Cateel
88,000,000.00 97,000,000.00 PLGU July to September Constructed
Diversion Dam &
Canals were
destroyed by
recent typhoon
and need to be
restored
immediately. This
facility will serve
the 1600 ha.
increased
riceland area.
2
Repair and restoration of canals
and canal structures.
Brgy. Aragon,
Taytayan,
Abejod, San
Antonio, San
Rafael, Mun.of
Cateel
32,000,000.00 39,500,000.00 NIA July to Sep Restore 5,000-
8,000 has. of
irrigated farm
lands in
3
Repair and restoration of dam,
canals and canal structures.
Boston 8,800,000.00 11,000,000.00 NIA July to Sep Restore 5,000-
8,000 has. of
irrigated farm
lands in priority
NIS, CIS &
Diversion Dams.
22 | P a g e
3 Repair and restoration of dam,
canals and canal structures.
Baganga 30,000,000.00 38,000,000.00 NIA July to Sep
3 Repair and restoration of dam,
canals and canal structures.
Caraga 30,000,000.00 36,500,000.00 NIA July to Sep
TOTAL 188,800,000.00 222,000,000.00
23 | P a g e
E. Health Infrastructure R
AN
K
PRIORITY PROJECTS/
ACTIVITIES (description)
LOCATION/
SITES
AMOUNT
IMPLEMENTING
AGENCIES
TIMELINE/
IMPLEMENTATION
PERIOD
REMARKS REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
1 Repair of CDA (35 beds) Cateel 40,000,000.00 52,000,000.00 PLGU Feb All health facility
to be built
according to
DOH standards
and meet criteria
PhilHealth
packages
RHU as BEMONC
facilities
BHS with birthing
facilities
2 Repair of MDH (18 beds) Manay 15,384,615.38 20,000,000.00 PLGU Feb
3 Reconstruction of Main RHU Baganga 7,692,307.69 10,000,000.00 PLGU Feb
4 Reconstruction of Lying in
Poblacion,
Baganga 11,538,461.54 15,000,000.00 PLGU Feb
5 Reconstruction of BHS (18) Baganga 27,692,307.69 36,000,000.00 PLGU Feb
6 Reconstruction of RHU Cateel 7,692,307.69 10,000,000.00 PLGU Feb
7 Reconstruction of BHS (16) Cateel 24,615,384.62 32,000,000.00 PLGU Feb
8 Reconstruction of Main RHU Boston 3,846,153.85 5,000,000.00 PLGU Feb
9 Reconstruction of BHS(8) Boston 12,307,692.31 16,000,000.00 PLGU Feb
10 Reconsutrction of RHU Caraga 3,846,153.85 5,000,000.00 PLGU Feb
11 Reconsutrction of BHS(10) Caraga 13,507,692.31 17,560,000.00 PLGU Feb
12
Construction of on-site low
cost communal sanitation
facilities in relocation areas
Boston (8) 164,965,384.62 214,455,000.00 Feb
Cateel (16) 454,434,615.38 590,765,000.00 Feb
Baganga (18) 679,453,846.15 883,290,000.00 Feb
Caraga (17) 374,603,846.15 486,985,000.00 Feb
Manay (17) 133,138,461.54 173,080,000.00 Feb
Tarragona (10) 66,703,846.15 86,715,000.00 Feb
Mati City (2) 73,503,846.15 95,555,000.00 Feb
13
Establishment of stabilization
site in CDH for SAM with
complication
230,769.23 300,000.00 PLGU Feb
TOTAL 2,115,157,692.31 2,749,705,000.00
24 | P a g e
F. Education Infrastructure
RA
NK
PRIORITY PROJECTS/
ACTIVITIES (description)
LOCATION/
SITES
AMOUNT
IMPLEMENTING
AGENCIES
TIMELINE/
IMPLEMENTATION
PERIOD
REMARKS REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
1
Rehabilitation/Repair of
Schools Buildings (313
classrooms)
Boston(25)
Cateel(19)
Baganga(148)
Caraga(65)
Manay(43)
Tarragona(13)
93,900,000.00 122,070,000.00 DepEd March-April 2013
The total damaged
classroom (789)
amounting to
P823,875,000.00 and
254 partially damaged
amounting to
P121,367,781.80 is the
result of PDNA ground
zero visit to affected
area. Addt'l.
amount(P159,292,981)
added for totally and
partialy damaged
classrooms were taken
from the report of
DEPED national
submmited by the
local level.
2 Reconstruction of School
Buildings
Boston(96)
Cateel(314)
Baganga(310)
Caraga(32)
Manay(23)
Tarragona(2)
693,050,000.00 900,965,000.00 DPWH March-April 2013
3 Reconstruction of Toilet with
Water Sanitation
Boston(96)
Cateel(314)
Baganga(310)
Caraga(32)
Manay(23)
Tarragona(2)
62,160,000.00 80,808,000.00 DepEd March-April 2013
SUB-TOTAL 849,110,000.00 1,103,843,000.00
25 | P a g e
G. Government Infrastructure R
AN
K PRIORITY PROJECTS/
ACTIVITIES (description)
LOCATION/
SITES
AMOUNT
IMPLEMENTING
AGENCIES
TIMELINE/
IMPLEMENTATION
PERIOD
REMARKS REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
1 Reconstruction/Repair of
Municipal Buildings
Baganga, Cateel,
Boston, Manay
14,420,000.00 18,746,000.00 LGU 6 months See details in
Annex;
Recommended
funding includes
reconstruction
and retrofitting
of structures
based on disaster
resilient designs
which are
resistant to
damages due to
earthquakes,
storms, and
flood;
2 Reconstruction/Repair of
Barangay Halls
Baganga, Cateel,
Boston, Caraga
35,845,000.00 46,598,500.00 LGU 6 months
3 Reconstruction/Repair of
Public Markets
Baganga, Cateel,
Boston, Caraga
63,530,720.00 82,589,936.00 LGU 6-10 months
4 Reconstruction of
Slaughterhouse
Baganga, Caraga 500,000.00 650,000.00 LGU 6 months
5 Rehabilitation of Legislative
Building
Cateel, Boston,
Caraga
3,510,000.00 4,563,000.00 LGU 6 months
6
Reconstruction/Repair of Day
Care Centers
Baganga, Cateel,
Boston, Caraga,
Tarragona
40,785,000.00 44,863,500.00 LGU 6 months
26 | P a g e
7 Reconstruction/Repair of
Municipal Gym
Baganga, Cateel,
Boston, Caraga
20,520,000.00 22,572,000.00 LGU 6 months
8 Reconstruction/Repair of
Covered Court
Baganga, Cateel,
Boston, Caraga
77,633,000.00 85,396,300.00 LGU 6 months
9 Reconstruction/Repair of
Public Terminal
Boston,
Baganga
1,600,000.00 1,760,000.00 LGU 6 months
10 Reconstruction/Repair of
Tourism Center
Boston, Caraga 3,100,000.00 3,410,000.00 LGU 6 months
11 Reconstruction/Repair of
Barangay Pharmacy
Cateel, Boston,
Caraga
220,000.00 242,000.00 LGU 6 months
12
Reconstruction/Repair of
Social Hall/Multipurpose
Building
Baganga, Cateel,
Boston
8,442,000.00 9,286,200.00 LGU 6 months
13 Reconstruction/Repair of Sitio
Halls
Cateel, Caraga 1,040,000.00 1,144,000.00 LGU 6 months
14 Reconstruction/Repair of
Senior Citizen Building
Baganga,
Boston
1,070,000.00 1,177,000.00 LGU 6 months
15 Reconstruction/Repair of
Training Center
Cateel, Boston 2,690,000.00 2,959,000.00 LGU 6 months
16 Reconstruction/Repair of
Barangay Kiosk
Caraga 600,000.00 660,000.00 LGU 6 months
27 | P a g e
17
Reconstruction/Repair of
Stage
Baganga, Cateel,
Boston, Caraga,
Mati City
11,340,000.00 12,474,000.00 LGU 6 months
18 Reconstruction/Repair of
Guest House
Boston 470,000.00 517,000.00 LGU 6 months
19 Reconstruction/Repair of
Purok House
Cateel, Caraga 980,000.00 1,078,000.00 LGU 6 months
20 Reconstruction/Repair of MRF Cateel 550,000.00 605,000.00 LGU 6 months
TOTAL 288,845,720.00 341,291,436.00
28 | P a g e
H. Tourism Infrastructure
RA
NK
PRIORITY PROJECTS/
ACTIVITIES (description) LOCATION/ SITES
AMOUNT
IMPLEMENTING
AGENCIES
TIMELINE/
IMPLEMENTATION
PERIOD
REMARKS REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
1
Reconstruction of Bayview Park Boston, Davao
Oriental
22,000,000.00 28,600,000.00 DOT, DPWH,
LGU
March 2013-
February 2014
To determine the
recommended
amount for
funding, an
additional 30%
was added to the
amount of
reported damage
which includes the
improvement and
DRR
2
Repair of Centennial Park Cateel, Davao
Oriental
120,000.00 156,000.00 LGU, DOT,
DPWH
March 2013- June
2013
To determine the
recommended
amount for
funding, an
additional 30%
was added to the
amount of
reported damage
which includes the
improvement and
DRR
29 | P a g e
3
Repair of Baywalk Manay, Davao
Oriental
500,000.00 650,000.00 LGU, DOT,
DPWH
March 2013- June
2013
To determine the
recommended
amount for
funding, an
additional 30%
was added to the
amount of
reported damage
which includes the
improvement and
DRR
Total 22,620,000.00 29,406,000.00
30 | P a g e
I. Mining Infrastructure
RA
NK
PRIORITY PROJECTS/
ACTIVITIES (description) LOCATION/ SITES
AMOUNT
IMPLEMENTING
AGENCIES
TIMELINE/
IMPLEMENTATION
PERIOD
REMARKS REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
1
Brgy. Road Rehabilitation /
Grading / Gravelling
3 kms. Stretch of
Brgy. Bantawan,
Baganga
200,000.00 230,000.00 District or
Regional
6 mos.
1
Brgy. Road Rehabilitation /
Grading / Gravelling
50 meters stretch
of Brgy. Batiano,
Baganga
Ulip road
50,000.00 57,500.00 Brgy. Fund 1 mo.
2
Repair/rehabilitation of Barging
Port Area
Lambajon Port,
Brgy. Lambajon
and Brgy.
Bantawan in
Baganga
3,750,000.00 4,312,500.00 District or
Regional
18 mos
1
Repair of Bridge Bridge
connecting San
Jose and
Manorigao
720,000.00 828,000.00 District or
Regional
12 mos
SUB-TOTAL 4,720,000.00 5,428,000.00
31 | P a g e
J. Power Infrastructure
RA
NK
PRIORITY PROJECTS/
ACTIVITIES (description)
LOCATION/
SITES
AMOUNT
IMPLEMENTING
AGENCIES TIMELINE REMARKS REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
1
Replacement/Installation of
Transformers, KWH Meters &
Poles
Boston 4,123,487.82 5,698,630.56 DORECO March-April 2013 For installation
2
Replacement/Installation of
Transformers, KWH Meters &
Poles
Cateel 14,284,915.80 19,200,636.27 DORECO March-April 2013 For installation
3
Replacement/Installation of
Transformers, KWH Meters &
Poles
Baganga 12,714,276.50 16,702,270.20 DORECO March-April 2013 For installation
4
Replacement/Installation of
Transformers, KWH Meters &
Poles
Caraga 42,046,539.70 49,765,668.02 DORECO March-April 2013 For installation
5
Replacement/Installation of
Transformers, KWH Meters &
Poles
Manay 30,603,904.37 37,129,543.90 DORECO March-April 2013 For installation
6
Replacement/Installation of
Transformers, KWH Meters &
Poles
Tarragona 9,104,017.03 11,381,003.08 DORECO March-April 2013 For installation
TOTAL 112,877,141.22 139,877,752.03
32 | P a g e
K. Water Infrastructure
RA
NK
PRIORITY PROJECTS/
ACTIVITIES (description)
LOCATION/
SITES
AMOUNT
IMPLEMENTING
AGENCIES TIMELINE REMARKS REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
1 Rehabilitation of Brgy. Sibahay
Level II Spring Development
Pk. Manga 1,
2 & Peña,
Brgy.
Sibahay,
Municipality
of Boston
100,800.00 500,000.00 LGU 35 days
Const'n. of 1 unit
concrete ground
reservoir, 10 units
concrete tub &
rehabilitation of
transmission line
1 Restoration of Cateel Level III
Water Supply System
New
reservoir be
constructed
@ Brgy. Sta.
Felomina,
Municipality
of Cateel
770,752.00 3,749,752.00 LGU 60 days
Const'n. of 1 unit
reinforced
concrete
reservoir,
additional
pipelines &
replacement of
chlorinator,
pumps & electrical
works
1 Rehabilitation of Baganga
Water District
Brgy. Batiano
& Poblacion,
Municipality
of Baganga
342,000.00 470,000.00 LGU 35 days
Replacement of
damaged
chlorinator,
generator set and
reconstruction of
pump house &
fence
33 | P a g e
1 Rehabilitation of Caraga
Waterworks System (Level III)
Brgy.
Poblacion,
Municipality
of Caraga
TURBIDITY
PROBLEM ON
ITS WATER
SOURCE
10,000,000.00 LGU 60 days
Source direct from
intake box. Needs
const'n. of 10,000
cu.m. reinforced
concrete reservoir
w/ water
treatment facility
& rehabilitation of
old piping
network
2
Rehabilitation of Brgy.
Cabasagan Level II Spring
Development
Sitio
Panaohon,
Narra &
Mahayahay,
Brgy.
Cabasagan,
Boston
220,000.00 560,400.00 LGU 35 days
Const'n. of 1 unit
concrete ground
reservoir,
rehabilitation of
pipeline &
replacement of
communal faucets
2 Rehabilitation of Bangas Level
II Spring Development
Brgy. Mainit,
Municipality
of Cateel
385,000.00 20,620,000.00 LGU 75 days
Const'n. of 1 unit
concrete ground
reservoir, intake
box, rehabilitation
of transmission
lines & provision
of eration,
sedimentation &
treatment tanks
2 Rehabilitation of Binondo Level
II Water System
Brgy.
Binondo,
Municipality
of Baganga
65,000.00 150,000.00 LGU 10 days
Const'n. of 1 unit
intake box &
rehabilitation of
distribution line
2 Rehabilitation of Santiago Level
II Spring Development
Brgy.
Santiago,
Municipality
65,000.00 300,000.00 LGU 10 days Rehabilitation on
transmission line
34 | P a g e
of Caraga
3 Rehabilitation of Brgy. Carmen
Level II Spring Development
Sitio Lambog,
Brgy.
Carmen,
Boston
65,000.00 150,000.00 LGU 25 days
Const'n. of 1 unit
intake box &
rehabilitation of
distribution line
3 Rehabilitation of Taytayan Level
II Water Supply System
Brgy.
Taytayan,
Municipality
of Cateel
495,000.00 1,110,000.00 LGU 45 days
Const'n. of 1 unit
concrete elevated
reservoir, intake
box &
rehabilitation of
pipelines
3 Rehabilitation of Masao Level II
Water System
Brgy. Masao,
Municipality
of Baganga
65,000.00 150,000.00 LGU 10 days
Const'n. of 1 unit
intake box &
rehabilitation of
distribution line
3 Rehabilitation of PM Sobrecarey
Level II Spring Development
Pk. Mangga
& Proper,
Brgy. PM
Sobrecarey,
Municipality
of Caraga
370,000.00 450,000.00 LGU 25 days
Const'n. of 1 unit
intake box &
rehabilitation of
transmission line
4 Rehabilitation of San Rafael
Level II Spring Development
Brgy. San
Rafael,
Municipality
of Cateel
350,000.00 450,000.00 LGU 45 days
Const'n. of 1 unit
intake box &
rehabilitation of
stand pipe &
pipelines
4 Rehabilitation of San Jose Level
III Spring Development
Brgy. San
Jose,
Municipality
of Caraga
SOIL EROSION
PROBLEM @
SOURCE
150,000.00 LGU 15 days Construction of
slope protection
5 Rehabilitation of Maglahus
Level III Water System
Brgy.
Maglahus, 65,000.00 100,000.00 LGU 4 days
Rehabilitation of
500m distribution
35 | P a g e
Municipality
of Cateel
line
5 Rehabilitation of Manorigao
Level II Spring Development
Brgy.
Manorigao,
Municipality
of Caraga
110,000.00 150,000.00 LGU 15 days Rehabilitation on
pipelines
6 Rehabilitation of San Alfonso
Level II Water System
Brgy. San
alfonso,
Municipality
of Cateel
410,000.00 500,000.00 LGU 35 days
Rehabilitation of
pipelines & stand
pipes
6 Rehabilitation of Mercedes
Level II Spring Development
Brgy.
Mercedes,
Municipality
of Caraga
100,000.00 150,000.00 LGU 15 days Rehabilitation on
pipelines
7 Rehabilitation of San antonio
Level II Spring Development
Brgy. San
Antonio,
Municipality
of Cateel
870,000.00 1,860,000.00 LGU 65 days
Total
rehabilitation on
intake box,
reservoir,
communal faucets
& pipelines
7 Rehabilitation of San Miguel
Level II Spring Development
Brgy. San
Miguel,
Municipality
of Caraga
32,000.00 50,000.00 LGU 5 days Rehabilitation on
pipelines
8 Rehabilitation of Abejod Level II
Spring Development
Brgy. Abejod,
Municipality
of Cateel
245,000.00 385,000.00 LGU 20 days
Const'n. of 1 unit
intake box &
rehabilitation of
distribution line
8 Rehabilitation of Lamiawan
Level II Spring Development
Brgy.
Lamiawan,
Municipality
of Caraga
210,000.00 210,000.00 LGU 7 days Rehabilitation on
pipelines
36 | P a g e
9 Rehabilitation of Alegria Level II
Water Supply System
Brgy. Alegria,
Municipality
of Cateel
220,000.00 360,000.00 LGU 10 days
Rehabilitation on
distribution line,
replacement of
sub. Pump &
procurement of 1
unit generator set
10 Rehabilitation of Aliwagwag
Level II Spring Development
Brgy.
Aliwagwag,
Municipality
of Cateel
125,000.00 190,000.00 LGU 28 days
Repair on intake
box, reservoir &
pipelines
TOTAL 5,680,552.00 42,765,152.00
H. Telecommunications Infrastructure
RA
NK
PRIORITY PROJECTS/
ACTIVITIES (description) LOCATION/ SITES
AMOUNT
IMPLEMENTING
AGENCIES
TIMELINE/
IMPLEMENTATION
PERIOD
REMARKS REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
1 Reconstruction of 2 Globe
Cellular Tower Boston 7,000,000.00 14,000,000.00
Globe Telecom
Co.
Replacement of
totally destroyed
Cellular Tower
2 Reconstruction of 2 Globe
Cellular Tower Cateel 7,000,000.00 14,000,000.00
Globe Telecom
Co.
Replacement of
totally destroyed
Cellular Tower
3 Repair of Smart Cellular Tower Cateel 4,900,000.00 4,900,000.00 Smart Telecom
Co.
Partially damaged
tower
4 Reconstruction of 2 Globe
Cellular Tower Baganga 7,000,000.00 14,000,000.00
Globe Telecom
Co.
Replacement of
totally destroyed
Cellular Tower
5 Reconstruction of Baganga 7,000,000.00 7,000,000.00 Smart Telecom Replacement of
37 | P a g e
CellularTower Co. totally destroyed
Cellular Tower
TOTAL 32,900,000.00 53,900,000.00
38 | P a g e
IMPLEMENTATION FRAMEWORK
Most of the identified projects are to be implemented by their respective Local Government Units and the Provincial Government Unit of Davao Oriental. The implementation time table is categorized in three different stages which are the Short-term (within a year), Medium-term (within two to three years) and Long-term (more than three years). As to stakeholders involve in recovery/reconstruction of projects, three definitive factors are to be considered, namely: (a) Fund sources, (b) Implementing bodies, and (c) Monitoring and Evaluation Team. a. Possible Fund Sources (under the guideline of GAA and proposed
by DBM): • National Calamity Fund (NDRRMF) • Local Calamity Fund (LDRRMF) • International Donors • Local Donors • National Programs
b. Implementing Bodies/Agencies
• Department of Public Works and Highways (DPWH) • Provincial Local Government Unit • City/Municipal Government Units • Respective Sector Agencies
c. Monitoring &Evaluation Team
• Department of Budget and Management (DBM) • Commission on Audit (COA) • Department of Public Works and Highways (DPWH) • Provincial Local Government Unit • City/Municipal Government Units • Respective Sector Agencies
RECOMMENDATION Proposed Strategies for Recovery and Reconstruction
1. Strict implementation of policy standards on infrastructure projects.
2. Strict monitoring and regular inspection of ongoing infrastructure projects to ensure compliance with the prescribed standards and timelines.
39 | P a g e
3. Periodic inspection of existing infrastructure projects to ensure its
structural integrity and recommend possible requirements for structural interventions.
4. Conduct training on Disaster Prevention and Mitigation for technical personnel who shall compose the infrastructure monitoring and inspection team.
5. Provide tax incentives to private sectors for adopting DRR/CCA in its recovery and reconstruction program of damaged as well as newly-constructed structures.
6. Provide strong linkages and coordination between and among the regional, provincial and local agencies and LGUs in the planning and implementation of infrastructure programs and projects.
7. Institutionalize reporting and feed-back mechanisms in all levels of governance including individual citizens on the prevailing conditions of infrastructures and structural integrity.
Policy Recommendations
1. Policy-review on quality standards for infra projects in mainstreaming the DRR/CCA.
2. Revisit the approved Provincial Development and Physical Framework Plan (PDPFP) and Municipal Comprehensive Land Use Plan (MCLUP).
3. Passage of appropriate ordinances or policies, such as Land Use Plan, Zoning, etc., mainstreaming DRR/CCA.
4. Review of existing ordinances, such as water system management, rationalizing revenue generations and efficient service delivery as well as embedding preventive and mitigating measures.
40 | P a g e
LIVELIHOOD SECTOR BACKGROUND In Davao Oriental, among the productive sub-sectors, agriculture is most affected by Typhoon “Pablo” owing to the fact that agriculture is a major driver of the province’s economy. The main sources of livelihood in the province are agricultural products such as farm crops, permanent/high value crops, animal production, and fish production/cultivation. Most of the populations at risk are farmers and fisherfolks who rely on agricultural and aquaculture produce to support and sustain their family’s basic needs. Due to the massive devastation brought by Typhoon “Pablo” in agriculture, it brought astounding effects especially to the farm workers in terms of social and economic development. Typhoon “Pablo” devastated more than 50% of the total hectare of agricultural lands planted with rice, corn, coconut, and high value crops (for export) like banana, rubber, cacao, coffee, vegetables palm oil and others. Davao Oriental also has a geology that is unique to the rest of the Philippines. The province is endowed with mineral resources such as gold, silver, copper, iron, chromite, manganese, nickel, silica, magnesite, sand and gravel. Thus, the province is considered as the mineral hub of Davao region. There are two (2) municipalities affected by the typhoon Pablo namely; municipality of Boston and Baganga, Davao Oriental. There are two exploration permits for gold in Boston covering a total of 4,152 hectares. While in Baganga, there are two small scale mining for iron, sand and gravel permittees covering a total of 41 hectares. The Province of Davao Oriental is prominent for the scenic views, natural formations and coastal areas laden with beach resorts. The province has extremely high biodiversity areas endowed with unblemished natural resources and with so many potential tourist and cultural sites that are yet to be developed. The Aliwagwag Falls and Mantunao Eco-Park in Cateel; Cabugao Island, coral garden, caves and rivers in Boston; and San Victor Island and hot springs in Baganga are just among of the provinces’ tourist sites. These tourist and cultural sites have really helped the locals in terms of income generation and employment. These sites are the major reasons why local and international guests and tourists flock to Davao Oriental which resulted to the increased demand in guest houses/ lodging houses/inns in the localities.
41 | P a g e
DAMAGE ASSESSMENT This chapter shows the extent of damages to the livelihood of the affected population of Davao Oriental incurred from the destructive might of Typhoon Pablo. Agriculture Assessments on damage were based on the reported areas of crops, fishery and forestry affected by the disaster multiplied by the pre-disaster market value of the specific crop, fishery and forestry lands. Subject-matter specialists from the municipal and provincial agriculturists’ office provided valuation on a province-wide perspective, employing near-to-the-actual value of the agricultural area. The total damage of the province in agriculture is accounted at PhP469,772,115.00. Large percentage of the damage was on permanent and high value cops followed by forestry products. Damages are mostly incurred by the private sector. Total damages in livestock and poultry amounted to PhP133,487,300.00. In Davao Oriental, major products severely affected are coconut, pomelo, mango, rice, corn, banana, and abaca. Tourism As a result of Typhoon Pablo, beach resorts, guest houses/lodging houses to include the municipal tourism guest houses, cultural sites like baywalk and parks and old church were damaged especially in terms of structures, machine, equipment and stocks which amounted to PhP24,022,000.00. The trees and plants of the natural formations like the rivers, falls, islands, coves and caves, coral garden and eco-park were also damaged which amounted to PhP5,528,200,000.
Private owners of the beach resorts and lodging houses, locals earning through equipment and machine rental, tour guides and stall owners are adversely affected. These people lost a very huge amount in revenues amounting to PhP29,450,000.00. It should be noted that there are no official and comprehensive reports on damages and losses from the Local Tourism Offices. Data are based on the interviews with the Local Tourism Officers and owners of the lodging houses and resorts. Cost is based on estimation. Almost all resorts and guest houses are non-operational in Davao Oriental because the damages incurred in these firms are on buildings, cottages,
42 | P a g e
machine and equipment. Thus, the income that should be generated for 2013 is lost. Only a few lodging houses operate but can only accommodate lesser number of guests with lower rates due to lack of power, inadequate water supply, partially damaged rooms and less provision of supplies and materials. With regard to the effects in natural formations, the damages resulted from the vast devastation of trees, plants and marine protective areas. The number of tourists/ guests decreased and as a result, the income generated by the LGU like the user’s fee and income earned by the motor drivers, pump boat operators, stall owners and tour guides are also lost. Mining Typhoon Pablo incurred a total damage and losses amounting to PhP6,146,000.00 for the Municipalities of Baganga and Boston, Davao Oriental. The two (2) small scale permit holders in Baganga have the bigger share in losses (foregone income and cleaning up of debris) that incurred in the amount of PhP3,965,000.00. They are supposed to ship out 3,000 M.T. of iron ores worth PhP1,800,000.00 (3,000 M.T. x PhP360.00 estimated net income per M.T,) last December, 2012 and incurred additional expense for cleaning up of debris amounting to PhP5,000.00 on the barging area that was spared from the devastating effects of typhoon Pablo. It will continue to incur losses from foregone income amounting to PhP2,160,000.00 for CY 2013 (estimated production and sales of 300 M.T. per month or 3,600 M.T. for the year). One (1) sand and gravel permittee also incurred losses as foregone income amounting to PhP80,000.00 (320 cu.m. x PhP250.00-estimated net income per month) last December 2012 and PhP240,000.00 for CY 2013 (960 cu. m. x PhP250.00). Two (2) exploration permit holders in Boston incurred damages to structures and equipments. They also incurred losses from cleaning up of debris amounting to PhP15,000.00. Industry, Trade and Services Under this sector, all of the affected establishments in Davao Oriental are purely private. The government can only extend financial assistance in the form of a loan (Soft loan to be specific with a very minimal and lenient requirement). While affected micro entrepreneurs can be given the option to engage in other types or means of livelihood together with the necessary assistance in the form of trainings or grants. Total damage is estimated at PhP685,720,566.00. An estimated amount of PhP 1 billion is needed to assist the sector in recovering their productive capacity.
43 | P a g e
RECOMMENDED RECOVERY/ RECONSTRUCTION NEEDS To respond to the pressing demand for restoration of the communities destroyed by TY Pablo, the Province of Davao Oriental determined priority projects which cover necessary activities to repair what was damage, restore what was lost, regain the people’s pride, and build back better communities. In line with the sector’s coverage on physical assets, several PPAs from National and Local Government Units were identified.
Table 5. Summary of Damages and Recommended Recovery/ Reconstruction Needs in the Livelihood Sector
LIVELIHOOD REPORTED DAMAGES (PhP)
RECOMMENDED RECOVERY/
RECONSTRUCTION NEEDS (PhP)
Agriculture 469,772,115.00 1,440,161,698.00 Tourism 5,528,200,000.00 5,200,000.00 Mining 0.00 3,400,000.00 Industry, Trade, and Services
685,720,566.00 1,000,000,000.00
GRAND TOTAL 6,683,692,681.00 2,448,761,698.00
The table above shows the summary of recovery/reconstruction needs of every sub-sector on livelihood. These are composed of identified projects per municipality as listed in the following tables:
44 | P a g e
Table 6. Recommended Recovery/ Reconstruction Needs
A. Agriculture
RA
NK
PRIORITY PROJECTS/ ACTIVITIES
(description)
LOCATION/
SITES
AMOUNT
IMPLEMENTING
AGENCIES TIMELINE REMARKS REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
1 A. Crop Production 212,438,975.00 175,000,000.00 DA 2013
Provision and distribution of
seeds and planting materials (
rice certified/inbred), corn-OPV
legumes (soybeans & peanut) &
rootcrops
Boston,
Cateel,
Baganga,
Caraga,
Manay,
Tarragona
25,000,000.00
annual crops
including saba-
banana as staple
food and could
produce in short
term months
and is a source
of livelihood.
Legumes are
best source of
protein & as
nitrogen-fixing
bacteria
Provision & distribution of saba-
banana plantlets
Distribution of cassava cuttings
(food/feeds)
2013
as staple food
substitute in all
seasons
Provision of High value crops
and industrial crops (durian,
mango, rubber, coffee & cacao)
2013-15
45 | P a g e
Provision & distribution of abaca
plantlets
FIDA 2013 Immediate
rehabilitation for
value adding
product as
source of
livelihood of
farmers
Distribution of seednuts 150,000,000.00
PCA
2013-2016
Restore coconut
areas by
providing new
variety where is
the champion
commodity
2
B. Pre-Post Production
Equipment & Machinery
10,000,000.00
DA, PhilMech
2013-2016
Ensure
postharvest
losses and
quality of
produce
1
C. Livestock & Poultry
Production
Boston,
Cateel,
Baganga,
Caraga,
Manay,
Tarragona
133,487,300.00
200,000,000.00
Restocking of breeders
(Cattle/Carabao)
DA-BAI, PCC
2014
Restore
breederstock
due to mortality
caused by
typhoon pablo.
This will help
enable famers to
sustain livestock
production as
46 | P a g e
source of
livelihood
1 Forage & Pasture Development LGU 2013
4 Reconstruction of slaughter 2014-2015
5
Establishment of Artificial
Insemination Center (Native
Pigs)
2014-2015
4 Establishment of native chicken
hatchery
2013
2 Animal health program, drugs &
biologics
2014
D. Fishery 64,965,180.00 71,461,698.00 DA, LGUs, BFAR,
LGU
2
Rehabilitation of mangrove Boston,
Cateel,
Baganga,
Manay
Immediate
rehab of
sanctuaries as
shelter to
enhance
biodiversity of
marine & other
aquatic specie
2 Rehabilitation of fish sanctuaries
1
Communal fish seeding Immediate
source of food
and livelihood
for inland
farmers and
fisherfolks and
restore the
annual earnings
& production of
43,723,000 &
47 | P a g e
301MT
respectively
1 Fingerling Dispersal
1 Provision of fishing banca,
engines & gears
2013
3 Establishment/Rehabilitation of
Aquasilvi (mudcrab project)
Cateel,
Baganga
1 Rehabilitation of fishpond
(freshwater tilapia)
Boston,
Cateel, Mati
3 Establishment/Rehabilitation of
seaweeds project
Cateel,
Baganga
Immediate
rehabilitation of
projects stated
to restore
livelihood of
fisherfolk
Establishment/Rehabilitation of
lobster production in pen
project
Baganga
Establishment/Rehabilitation of
fishcages (saline tilapia) project
Cateel,
Baganga
E. Forestry 58,880,660.00 5,000,000.00 DENR, LGU Reforestation
1 Bamboo Production
Boston,
Cateel,
Baganga,
Manay
1 Reforestration Project
2 F. Extension, Education &
Training
4,410,000.00
48 | P a g e
Capability building of farmers on
the different Package of
Technology (POT) on rice, corn
cassava, HVCC livestock &
poultry production & disease
management (native animals)
SALT for upland areas
Boston,
Cateel,
Baganga,
Manay,
Tarragona
ATI, LGU 2013-2015
institutionalize
capability-
building to
enhanced
technical know-
how farmers
especially on
marginal areas
to sustain
productivity &
profitability
2
G. Establishment of Technology
Demonstration/Commercializati
on (Diversified Farming)
Boston,
Cateel,
Baganga,
Manay,
Tarragona
550,000.00
RFU-LGU
2013-2016
To be
established in
the identified
production
zones for market
promotion
2 H. Research & Development 370,000.00
On - Farm Review of technology
on crop - soil adaptability-
suitability
Boston,
Cateel,
Baganga
270,000.00
RFU-LGU
2,013
To determine
the specific crop
and type of soil
that crops are
more suitable
and resilient
Conduct of market research on
champion commodities
Boston,
Cateel,
Baganga,
Manay,
Tarragona
100,000.00
RFU-LGU
2,015
To determine
domestic &
international
markets
1 I. Agricultural Land Debris
Management (Cash for Work)
49 | P a g e
Debris Management a. Forest
Trees and Coconut Trunks
798,000,000.00 DA-PCA, DENR,
LGU,
Development
Partner
2013 Obstruction to
dev't,pollution
of waterways
health hazard,
siltation &
flooding as well
as damage to
infrastructure.
Other
incidentals
(tools,
equipments, fuel
for transport
etc.) will be
shouldered by
the concern
agencies
TOTAL 469,772,115.00 1,440,161,698.00
50 | P a g e
B. Tourism
RANK
PRIORITY PROJECTS/
ACTIVITIES
(description)
LOCATION/
SITES
AMOUNT
IMPLEMENTING
AGENCIES TIMELINE REMARKS REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
1 Reforestation Cabugao Island,
Boston, Davao
Oriental
500,000.00 650,000.00 DENR, LGU, March 2013-June
2013
To determine the
recommended
amount for funding,
an additional 30%
was added to the
amount of reported
damage which
includes the
improvement and
DRR
1 Reforestation Tagoan and
Poblacion Rock
Islets, Boston,
Davao Oriental
150,000.00 195,000.00 DENR, LGU, March 2013-June
2013
To determine the
recommended
amount for funding,
an additional 30%
was added to the
amount of reported
damage which
includes the
improvement and
DRR
51 | P a g e
1 Reforestation Bil-at Cave,
Boston, Davao
Oriental
150,000.00 195,000.00 DENR, LGU, March 2013-June
2013
To determine the
recommended
amount for funding,
an additional 30%
was added to the
amount of reported
damage which
includes the
improvement and
DRR
1 Reforestation Baclinan,
Sabang, Simulao,
Cabasagan
Rivers, Boston,
Davao Oriental
500,000.00 650,000.00 DENR, LGU, March 2013-June
2013
To determine the
recommended
amount for funding,
an additional 30%
was added to the
amount of reported
damage which
includes the
improvement and
DRR
1 Reforestation Hulid,
Anahawon,
Magdawa, Busa,
Magpong Falls,
Boston, Davao
Oriental
1,000,000.00 1,300,000.00 DENR, LGU, March 2013-June
2013
To determine the
recommended
amount for funding,
an additional 30%
was added to the
amount of reported
damage which
includes the
improvement and
DRR
52 | P a g e
1 Vegetation Coral Garden/
Marine, Boston,
Davao Oriental
500,000.00 650,000.00 BFAR, DENR,
LGU
March 2013-June
2013
To determine the
recommended
amount for funding,
an additional 30%
was added to the
amount of reported
damage which
includes the
improvement and
DRR
2 Reforestation Aliwagwag Falls,
Cateel, Davao
Oriental (10,000
has land forest)
5,524,200,000.00 7,181,460,000.00 DENR, LGU, March 2013-June
2013
To determine the
recommended
amount for funding,
an additional 30%
was added to the
amount of reported
damage which
includes the
improvement and
DRR
2 Reforestation Cream Sand
Long Beach (9
km stretch)
300,000.00 390,000.00 DENR, LGU March 2013-June
2013
To determine the
recommended
amount for funding,
an additional 30%
was added to the
amount of reported
damage which
includes the
improvement and
DRR
53 | P a g e
2 Reforestation Cateel, Riverend 400,000.00 520,000.00 DENR, LGU, March 2013-June
2013
To determine the
recommended
amount for funding,
an additional 30%
was added to the
amount of reported
damage which
includes the
improvement and
DRR
3 Reforestation San Victor Island,
Baganga, Davao
Oriental
200,000.00 260,000.00 DENR, LGU, March 2013-June
2013
To determine the
recommended
amount for funding,
an additional 30%
was added to the
amount of reported
damage which
includes the
improvement and
DRR
3 Reforestation Baculin Eco-Park
(Mangroove),
Baganga, Davao
Oriental
100,000.00 130,000.00 DENR, LGU, March 2013-June
2013
To determine the
recommended
amount for funding,
an additional 30%
was added to the
amount of reported
damage which
includes the
improvement and
DRR
54 | P a g e
3 Reforestation Ban-ao Resort,
Baganga, Davao
Oriental
200,000.00 260,000.00 DENR, LGU, March 2013-June
2013
To determine the
recommended
amount for funding,
an additional 30%
was added to the
amount of reported
damage which
includes the
improvement and
DRR
TOTAL 5,528,200,000.00 7,186,660,000.00
55 | P a g e
C. Mining R
AN
K
PRIORITY PROJECTS/
ACTIVITIES (description)
LOCATION/
SITES
AMOUNT
IMPLEMENTING
AGENCIES TIMELINE REMARKS REPORTED
DAMAGE
RECOMMENDED
FOR FUNDING
1
Capacity building and
training for LGUs (from
Purok, Barangay,
Municipal to Provincial
Level), small-scale
miners and other
stakeholders
Davao Oriental 500,000.00 DBM 3 mos Enhancement of
training and
development to
participants as
technical experts in
basic mine safety
standards as well
as knowledge on
risk reduction
strategies
1
Continue with and
expand the scope of the
National Greening
Program (NGP) and
purchase of seedlings
Davao Oriental 800,000.00 DBM 3 mos Rehabilitation and
protection of
barangay roads and
national highways
through massive
tree planting
activities and
denuded forests
56 | P a g e
2
Continuing activities in
the conduct of geo-
hazard mapping and
providing updated geo-
hazard maps and threat
advisories
Davao Oriental 500,000.00 DBM 3 mos MGB XI to continue
the conduct of geo-
hazard mapping
and providing
updated geo-
hazard maps and
threat advisories to
local government
units (provinces,
municipalities and
barangays), mining
companies, small-
scale miners
assn/cooperatives
as inputs in the
preparation of
their disaster
management plan
Purchase and
installation of warning
systems like billboards
and signages in high
risks areas prone to
landslides and flooding
patterned to MGB
format
Davao Oriental 300,000.00 DBM 3 mos To provide
information for the
community not to
engaged in any
mining activities
and strict
adherence to the
no build zones in
highly risked areas
2
Recommended