Board of Water SupplyBeretania Complex Redevelopment
F A C T S H E E T
Project OverviewThe Honolulu Board of Water Supply (BWS) will be issuing a Request for Proposal(s) to redevelop a portion of its Beretania Complex. The purpose of this action is to provide a revenue stream for BWS.
99 Project area will be leased to third party.
99 Lessee will implement the redevelopment.
99 Revenue stream to help offset a portion of operating and capital improvement costs for BWS.
South Beretania Street
Lauhala Street
Street
Lusitana
Alap
ai
Stre
et
Lisbon Street
Project Area128,100 sfTMK (1) 2-1-036:001 and 005 (por)
ExistingPublic Service
Building
Beretania Complex
ExistingEngineering Building
ExistingPump Station
Site MapZoning: A2, Medium Density Apartment
Source: Google Earth
Beretania Complex Redevelopment Process
Develop 3 Alternative
Concept Plans
Identify Allowable/Appropriate Uses
A2 Zoning • Adjacent Land Use Compatibility • Market Studies
Select Lessee/Developer and Enter Lease
Agreement
Evaluate Developer Proposals
Issue Request for Proposals
(RFP)
Lessee Obtain Land Use
Entitlements
Developer/Lessee Finalize Plans for Site
Lessee Redevelops Site
Environmental Review Process
(Evaluate 3 Alternatives)
Potential Redevelopment Concepts (Potential Redevelopment Concepts are based on current A-2 Zoning, compatibility with surrounding land uses, and a BWS market analysis on the most appropriate uses for the property. Final project design is subject to change by selected developer/lessee. Additional environmental review may be required if proposed concept is different from those presented below).
BWS is currently initiating theEnvironmental Review Process
99Environmental review in accordance with Chapter 343 Hawaii Revised Statutes (HRS).
99EIS will evaluate environmental impacts of three alternatives on natural and human environment.
99EIS will recommend minimization and mitigation of any environmental impacts.
Scenario 1: Assisted Care Living Facility and Office Building
Scenario 3: Parking Structure and Office Building
Scenario 2: Affordable Senior Rental Apartments and Office Building
Environmental Impact Statement Preparation Notice
(EISPN)November 23, 2018
Public MeetingsNeighborhood Board and
Community Meetings
Draft EIS
June 2019 (Estimate)
Final EIS
November 2019 (Estimate)
30-day
Public Review
45-day Public Review
Recommended