Concept Development Substructure Demolition and Quad Development Project (SDQD)

Presentation to UMass Boston

December 12, 2018

The immediate priority for this project is to proceed in a smart, timely, cost effective, environmentally responsible and a non-disruptive process.

The ultimate goal is to produce a distinguished, welcoming place at the heart of the campus, around which UMass Boston will grow & flourish!

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #2

Required Demolition The Optimum Outcome

Rebuilt Ped. Bridge

700 Surface Parking

Repaired Plaza

New Campus Green & Gathering Space

Substructure Repair with Parking Beneath Wheatley & McCormack

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #3

Rebuilt Ped. Bridge

700 Surface Parking

Repaired Plaza

New Campus Green & Gathering Space

Substructure Repair with Parking Beneath Wheatley & McCormack

Science Center Programs to be Relocated into Existing Buildings

Science Center, Pool, Garage & Portions of the Plaza Must be Demolished

McCormack & Wheatley Substructure Deterioration Requires Addressing.

Need to Accommodate Parking Currently at Bayside to Offset Cost of Shuttles & Free Up Parcel for Development

A Better Campus Focal Point and Gathering Space is Desirable

Replacement of Pedestrian Bridges is Critical

1

2

6

5

4

133

Campus Challenges Addressed with Full Scope

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #4

• Schematic development from Basis of Design

• Analysis of all existing elements, including installed braces, for updated structural action

• Identify the essential zones of repair and protection in the skeleton of the substructures

Substructure Repair

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #5

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #6

Existing Campus

Need to splice in the quad and parking lot and then follow with

the future phase

Proposed Concept

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #7

Future Campus

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #8

Available Funding:

State & UM Boston Funding $155,500,000

Estimated Cost of REAB ($41,000,000)

Total $114,500,000

Estimated Cost of SDQD:

Demolition $32,500,000

Substructure Repair $16,500,000

Plaza Repair $33,000,000

Quadrangle & Parking $18,500,000

Pedestrian Bridge $9,000,000

Other $5,000,000

Total $114,500,000

Budget

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #9

New Pedestrian Walkway – Preferred Option

UMass Boston SDQD Presentation to the University 2018 12 12 . Slide #12

New Pedestrian Walkway – Preferred Option

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #13

New Pedestrian Walkway – Preferred Option

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #14

New Pedestrian Walkway – Preferred Option

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #15

New Pedestrian Walkway – Preferred Option

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #16

The Future Quadrangle is large enough to accommodate several outdoor places and to seamlessly provide access from elevation 24’, to 34’ along

Quinn, and the plaza at 49’.

+34

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #17

Concept for New Quad

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #18

Conceptual Plan for New Quad

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #19

• Schematic Design February 2019

• Substructure Repair Documentation May 2019

• Pedestrian Walkway Documentation July 2019

• Demolition Documentation October 2019

• Plaza Documentation October 2019

• Quad & Parking Documentation March 2020

Next Steps

UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #20