Concept Development Substructure Demolition and Quad Development Project (SDQD)
Presentation to UMass Boston
December 12, 2018
The immediate priority for this project is to proceed in a smart, timely, cost effective, environmentally responsible and a non-disruptive process.
The ultimate goal is to produce a distinguished, welcoming place at the heart of the campus, around which UMass Boston will grow & flourish!
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #2
Required Demolition The Optimum Outcome
Rebuilt Ped. Bridge
700 Surface Parking
Repaired Plaza
New Campus Green & Gathering Space
Substructure Repair with Parking Beneath Wheatley & McCormack
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #3
Rebuilt Ped. Bridge
700 Surface Parking
Repaired Plaza
New Campus Green & Gathering Space
Substructure Repair with Parking Beneath Wheatley & McCormack
Science Center Programs to be Relocated into Existing Buildings
Science Center, Pool, Garage & Portions of the Plaza Must be Demolished
McCormack & Wheatley Substructure Deterioration Requires Addressing.
Need to Accommodate Parking Currently at Bayside to Offset Cost of Shuttles & Free Up Parcel for Development
A Better Campus Focal Point and Gathering Space is Desirable
Replacement of Pedestrian Bridges is Critical
1
2
6
5
4
133
Campus Challenges Addressed with Full Scope
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #4
• Schematic development from Basis of Design
• Analysis of all existing elements, including installed braces, for updated structural action
• Identify the essential zones of repair and protection in the skeleton of the substructures
Substructure Repair
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #5
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #6
Existing Campus
Need to splice in the quad and parking lot and then follow with
the future phase
Proposed Concept
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #7
Future Campus
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #8
Available Funding:
State & UM Boston Funding $155,500,000
Estimated Cost of REAB ($41,000,000)
Total $114,500,000
Estimated Cost of SDQD:
Demolition $32,500,000
Substructure Repair $16,500,000
Plaza Repair $33,000,000
Quadrangle & Parking $18,500,000
Pedestrian Bridge $9,000,000
Other $5,000,000
Total $114,500,000
Budget
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #9
New Pedestrian Walkway – Preferred Option
UMass Boston SDQD Presentation to the University 2018 12 12 . Slide #12
New Pedestrian Walkway – Preferred Option
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #13
New Pedestrian Walkway – Preferred Option
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #14
New Pedestrian Walkway – Preferred Option
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #15
New Pedestrian Walkway – Preferred Option
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #16
The Future Quadrangle is large enough to accommodate several outdoor places and to seamlessly provide access from elevation 24’, to 34’ along
Quinn, and the plaza at 49’.
+34
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #17
Concept for New Quad
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #18
Conceptual Plan for New Quad
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #19
• Schematic Design February 2019
• Substructure Repair Documentation May 2019
• Pedestrian Walkway Documentation July 2019
• Demolition Documentation October 2019
• Plaza Documentation October 2019
• Quad & Parking Documentation March 2020
Next Steps
UMass Boston SDQD Presentation to the University . 2018 12 12 . Slide #20