Bond Projects Update Madison Elementary SD December 2015

Preview:

Citation preview

Bond Projects Update

Madison Elementary SD

Madison Elementary SD

December 2015

Tonight's topicsTonight's topics

Simis progress update, move into new building and phase two schedule.

Park café replacement timeline.Meadows two-story replacement

timeline.Other projects scheduled for

winter recess.

Simis replacementSimis replacement

Simis replacementSimis replacement

Simis replacementSimis replacement

Simis replacementSimis replacement

Simis replacementSimis replacement

Simis replacementSimis replacement

The moveThe move

Staff have been delivered boxes and instructions (10/15/15)

Completion of packing (12/18/15)

Items moved to new location (12/19-23/15)Staff unpacking and preparing

for students return (12/28-29/15)

Out with the old

Out with the old

FurnitureTechnology

Simis ReplacementSimis Replacement

Timeline for major Bond

ProjectsTimeline for major Bond

Projects

Madison Park Café replacement, Project start (3/15/16) Completion (8/1/16)

Madison Meadows two-story classroom replacement, project start (9/1/16) Completion (7/1/17)

Other projects during winter

recessOther projects during winter

recessHVAC replacement, Rose Lane

ElementaryHVAC replacement, Heights

ElementaryConcrete floor re-polish MTAWarranty on wrought iron

fencing, MTA