AHAFO-ANO SOUTH DISTRICT ASSEMBLY
REPUBLIC OF GHANA
2017 ANNUAL PROGRESS REPORT
(DMTDP 2014-2017)
JANUARY, 2018
i
TABLE OF CONTENTS
TABLE OF CONTENTS ...................................................................................................................................... i
LIST OF TABLES ................................................................................................................................................ ii
ACRONYMS ....................................................................................................................................................... iii
EXECUTIVE SUMMARY ................................................................................................................................. iv
1.0 INTRODUCTION .................................................................................................................................. 1
1.1 Purpose of the Monitoring and Evaluation for the Stated Period, 2017 .................................... 1
1.2 Summary of Achievements of the Implementation of the DMTDP .......................................... 1
1.3 Challenges Encountered in the Implementation of the DMTDP ............................................... 3
1.4 Processes Involved in the Preparation of the 2017 Annual Progress Report ............................ 3
2.0 MONITORING AND EVALUATION ACTIVITIES REPORT, 2017 ............................................. 4
2.1 Programmes/Projects/Activities Status of 2017 ........................................................................ 4
2.2 Update on Funding Sources .................................................................................................... 13
2.3 Update on Disbursement ......................................................................................................... 14
2.4 Update on Indicators and Targets ............................................................................................ 14
2.5 Update on Critical Development and Poverty Issues .............................................................. 17
2.6 Evaluations Conducted, Their Findings and Recommendations ............................................. 18
2.7 Participatory Monitoring and Evaluation Undertaken and Their Results ............................... 20
3.0 CONCLUSION AND THE WAY FORWARD ................................................................................. 21
3.1 Summary of Key Issues Addressed in 2017 and Those Yet to be Addressed ......................... 21
3.2 Recommendations ................................................................................................................... 22
ii
LIST OF TABLES
Table 1.1: Proportion of the DMTDP Implemented ............................................................................... 2
Table 2.1: Programmes/Projects/Activities Register, 2017 .................................................................... 4
Table 2.2: Update on Revenue Sources from 2013 to 2017 ................................................................ 13
Table 2.3: Update on Expenditure from 2013 to 2017 ........................................................................ 14
Table 2.4: Performance of Core Indicators at the District Level ......................................................... 15
Table 2.5: Update on Critical Development and Poverty Issues in 2017 ............................................ 17
Table 2.6: Update on Evaluations Conducted in 2017 ........................................................................ 19
Table 2.7: Update on PM&E Conducted ............................................................................................. 20
iii
ACRONYMS
AAP : Annual Action Plan
AIDS : Acquired Immune Deficiency Syndrome
AASDA : Ahafo-Ano South District Assembly
AMMHIS : Ahafo-Ano South Mutual Health Insurance Scheme
BAC : Business Advisory Centre
CHPS : Community Health Planning Services
CIC : Community Information Centre
CLTS : Community Led Total Sanitation
DA : District Assembly
DACF : District Assemblies Common Fund
DBA : District Budget Analyst
DDF : District Development Fund
DE : District Engineer
DMTDP : District Medium Term Development Plan
DPCU : District Planning Co-ordinating Unit
DPO : District Planning Officer
FBOs : Farm Based Organisations
GES : Ghana Education Service
GOG : Government of Ghana
GSGDA : Ghana Shared Growth and Development Agenda
HIV : Human Infections Virus
HR : Human Resource
ICT : Information Communication Technology
IGF : Internally Generated Funds
LEAP : Livelihood Empowerment Against Poverty
M&E : Monitoring and Evaluation
MLGRD : Ministry of Local Government and Rural Development
MOFA : Ministry Of Food and Agriculture
MSMEs : Middle Small Medium Enterprises
NHIS : National Health Insurance Scheme
PPPs : Public Private Partnership
REP : Rural Enterprise Programme
SMEs : Small Medium Enterprises
SSNIT : Social Security National Insurance Trust
STIs : Sexually Transmitted Infections
iv
EXECUTIVE SUMMARY
1. From the 2017 Annual Action Plan of the District Medium-Term Development
Plan (2014-2017), the Ahafo-Ano South District Assembly proposed to implement
116 programmes, projects and activities.
2. Out of total 116 programmes, projects and activities proposed for implementation
in 2017, 105 representing 90.5 percent were initiated out of which 91 (86.7%)
were fully implemented with 14 (13.3%) still on-going. Hence, the average
performance (completion rate) of the District in 2017 is 95.0 percent.
3. Eleven (11) programmes, projects and activities representing 9.4 percent were not
initiated due to inadequate funding from District Assemblies Common Fund
(DACF), District Development Facility (DDF), Internally Generated Fund and
other sources.
4. Recommendations
Based on the challenges faced in 2017, we recommend early release of DACF and
DDF to MMDAs. This is because most of the budget allocations are from these
sources and as result their delays affect the implementation of programmes, projects
and activities in the District. In addition, the provision of adequate logistics
(Vehicle) for monitoring and evaluation will help to improve M&E activities in
the District.
1
1.0 INTRODUCTION
1.1 Purpose of the Monitoring and Evaluation for the Stated Period, 2017
The rationale for developing Monitoring and Evaluation (M&E) for the implementation of
2017 Composite Annual Action Plan is summarized as follows:
· To assess whether 2017 CAAP (DMTDP, 2014-2017) developmental targets were
being met.
· To provide information for effective coordination of District’s development at the
regional and national levels, African Union Agenda 2063 and the Sustainable
Development Goals.
· To document progress made and lessons learnt from the implementation of
programmes, projects and activities.
· To improve service delivery and influence allocation of resources in the District.
· To demonstrate M&E results to stakeholders as part of accountability and
transparency.
· To identify achievements, constraints and failures so that improvements can be made
to the CAAP and project designs to achieve better impact.
1.2 Summary of Achievements of the Implementation of the DMTDP
The 2017 Annual Progress Report is the appraisal of all programmes, projects and activities
implemented during the year embedded in the 2017 Composite Annual Action Plan of the
Ahafo-Ano South District Assembly. The main focus is to find out if the targets set by the
District were achieved during the period under review. The Annual Progress Report will
enable the District to measure the actual performance against the set targets. The report
presents the result of the assessment of the indicators and targets adopted for monitoring and
evaluating the achievements and impacts of key policy and programme interventions
executed in the year, 2017.
· Proportion of the Composite Annual Action Plan Implemented by the End of Year, 2017
Out of 116 programmes, projects and activities proposed for implementation in the year
2017, 11 representing 9.4 percent were rolled over from 2016. Out of this number, 11
accounting for 9.4 percent were not initiated due to inadequate funding (DACF, DDF and
Others). 105 representing 90.5 percent were initiated out of which 91 forming 86.7 percent
2
were fully completed and 14 forming 13.3 percent were partially completed with an overall
performance of 95 percent. Table 1.1 shows the level of implementation of the 2017
Composite Annual Action Plan. It is worth mentioning that, the District has successfully
implemented all the four years of the plan, that is, from 2014 to 2017 using the Composite
Annual Action Plans (CAAP) aggregated from the Ten (10) Decentralised Departments of the
Assembly. In the four years, the District has initiated 476 programmes, projects and activities
(averagely, 119), out of which 450 representing 94.5 percent have been implemented.
· Overall Proportion of the DMTDP Implemented within the Four Year Period (2014-2017)
Out of the 150 programmes, projects and activities proposed to be implemented within the
plan period of 2014 to 2017, 141 representing 94.0 percent were implemented with the
remaining nine accounting for 6.0 percent were not implemented. The implementation status
of the 141 programmes, projects and activities accounted for 132 representing 88.0 percent
fully completed with nine representing 6.0 percent still on-going. From the performance
review of the DMTDP 2014-2017, the District recorded 91.3 percent achievement.
Averagely, 119 programmes, projects and activities were implemented annually. As a result
of this, the District has seen a tremendous improvement in education, health, water,
sanitation, energy, transportation, LED and job creation which has enhanced the quality life
of the people. Again, all the cross-cutting issues targeting HIV/AIDS, gender, environment,
climate change, population and social protection programmes have been fully integrated in
the implementation of the programmes, projects and activities in the DMTDP (2014-2017). It
is worth mentioning that all the programmes, projects and activities implemented were from
the plan. Table 1.1 shows the performance achievement of the implementation of the
DMTDP 2014-2017.
Table 1.1: Proportion of the DMTDP Implemented Indicators 2017 2016 2015 2014
Percent Percent Percent Percent
Proportion of the Composite Annual Action Plans implemented by
the End of the Year
90.5 96.7 95.1 95.7
a. Percentage Completed 78.4 84.4 72.1 80.2
b. Percentage of On-going Interventions 12.1 12.3 23.0 15.5
c. Percentage of Interventions Yet to Start 9.5 3.3 4.9 4.3
Proportion of the Overall Medium-Term Development Plan
Implemented by the end of the Four Years
94.5 95.8 95.3 95.7
Source: DPCU-AASDA, January, 2018
3
1.3 Challenges Encountered in the Implementation of the DMTDP
The specific constraints, problems or difficulties encountered by the District Planning Co-
ordinating Unit (DPCU) during the implementation, monitoring and evaluation of the
Composite Annual Action Plans under the DMTDP 2014-2017 are outlined below.
· The major challenge facing the implementation of the plan is inadequate funding from
all sources (DACF, DDF, IGF and Other Donor Support). This is because some of the
DACF releases to the District are still in arrears. Similarly, DDF grants for 2013 and
2014 are still in arrears.
· Inadequate logistical support and other resources for monitoring and evaluation
activities in the District and at the sub-structures levels.
· Difficulty of assessing performance because some indicators were without baseline to
assist in setting realistic targets.
· Lack of assigned permanent vehicle for monitoring and evaluation of programmes,
projects and activities in the District.
· Different reporting formats of the Decentralised Departments due to the requirement
of their reporting Sector Ministries, Departments and Agencies
· Delay in providing feedback on DMTDPs and Annual Progress Reports from NDPC.
· Inadequate training programmes organised by NDPC on the preparation and reporting
of DMTDPs and Annual Progress Reports respectively.
· Lack of sustainable funds to conduct DPCU activities, Social Accountability
Programmes, Evaluation and Participatory Monitoring and Evaluation.
1.4 Processes Involved in the Preparation of the 2017 Annual Progress Report
The District Planning Co-ordinating Unit (DPCU) facilitated the preparation of the 2017
Annual Progress Report with the involvement of the Decentralised Departments of the
Ahafo-Ano South District Assembly. Monitoring and Evaluation data were compiled from
both primary and secondary sources. The secondary data were compiled from the various
quarterly Reports of Departments and Agencies as well as from the District Assembly and its
Area Councils. The primary data were also obtained from the quarterly site meetings, public
hearings, town hall meetings, social accountability forums and the quarterly meetings with
the various stakeholders involved in the plan implementation and monitoring. The data were
collated, analysed and evaluated by the DPCU. The final report was disseminated to the
public by the District Development Communication Committee at the Town Hall meeting of
the Assembly.
4
2.0 MONITORING AND EVALUATION ACTIVITIES REPORT, 2017
2.1 Programmes/Projects/Activities Status of 2017
Table 2.1: Programmes/Projects/Activities Register, 2017 Item Project Description Thematic Area of
Policy Framework
Location Contractor/
Consultant
Contract
Sum/ Budget
(GH¢)
Source of
Funding
Date of
Award (D/M/Y)
Date
Started (DD/MM/YY)
Expected Date
of Completion (DD/MM/YY)
Expenditure
to Date
(GH¢)
Outstanding
Balance
(GH¢)
Implementa
tion Status
(%)
Remarks
1. Procure Value Books for the Assembly
Ensuring and Sustaining
Macroeconomic
Stability
Mankranso Finance Dept 6,000.00 IGF - · 06/02/17
· 13/06/17
· 06/09/17
· 21/11/17
· 08/02/17
· 15/06/17
· 08/06/17
· 23/11/17
3,000.00 - 100 Target achieved
2. Provide support to activities of Revenue Mobilisation
Ensuring and Sustaining
Macroeconomic
Stability
District Wide
Finance Dept 10,000.00 DACF/ IGF
- · 02/01/17
· 03/04/17
· 04/07/17
· 02/10/17
· 31/03/17
· 30/06/17
· 29/09/17
· 29/12/17
5,000.00 - 100 Target achieved
3. Gazette Fee-Fixing Resolution Ensuring and Sustaining
Macroeconomic
Stability
Mankranso - 6,000.00 IGF - - - - - - Not Implemented
4. Provide logistics (Rain Coats,
Wallington Boots, Torch lights) for revenue collectors
Ensuring and Sustaining
Macroeconomic
Stability
District
Wide
Finance Dept 10,000.00 DACF/
IGF
- · 02/01/17
· 03/04/17
· 04/07/17
· 02/10/17
· 31/03/17
· 30/06/17
· 29/09/17
· 29/12/17
5,000.00 - 100 Target achieved
5. Procure/Assign Revenue
Mobilisation Van for the Revenue Unit
Ensuring and Sustaining
Macroeconomic
Stability
Mankranso Finance Dept 150,000.00 DACF - · 12/09/17
· 12/09/17
- - 100 Target achieved. (One Pickup assigned
to Revenue Unit)
6. Pay compensation of employees
(Established Post and Non-Established Post)
Ensuring and Sustaining
Macroeconomic
Stability
District
Wide
Finance Dept 2,140,048.56 GOG/
IGF
- · 31/01/17
· 31/12/17
2,140,048.56 - 100 Target achieved
7. Pay Commission Collectors’
Allowances
Ensuring and Sustaining
Macroeconomic
Stability
District
Wide
Finance Dept 15,000.00 IGF - · 31/01/17
· 31/12/17
15,000.00 - 100 Target achieved
8. Organise 4 Training Programmes for women and
other MSMEs in Local
Economic Development
Enhancing
Competitiveness of
Ghana’s Private Sector
District Wide
Trade and Industry
(Bus. Adv.
Centre)
5,000.00 DACF - · 21/03/17
· 07/06/17
· 25/09/17
· 20/11/17
· 22/03/17
· 08/06/17
· 26/09/17
· 21/11/17
5,000.00 - 100 Target achieved
9. Support 4 Training Programmes for MSMEs organised by BAC
in LED (Mushroom Production,
Grasscutter rearing, Cassava
Processing, Oil Palm processing, Fish
Farming and Soap Making)
Enhancing
Competitiveness of
Ghana’s Private Sector
District Wide
Trade and Industry
(Bus. Adv.
Centre)
4,000.00 DACF - · 06/02/17
· 15/05/17
· 08/08/17
· 24/10/17
· 07/02/17
· 16/05/17
· 09/08/17
· 25/10/17
4,000.00 - 100 Target achieved
10. Provide loan facilities for
Traders under SIF-IRDP
Enhancing
Competitiveness of
Ghana’s Private Sector
District
Wide
- 50,000.00 SIF/
DACF
- - - - - - Not Implemented
11. Organise 2 Training Workshops
for Co-operative/Producer/ Farmer Based Organisations
Enhancing
Competitiveness of
Ghana’s Private Sector
District
Wide
Trade and
Industry (Bus. Adv.
Centre)
1,000.00 DACF - · 08/03/17
· 26/09/17
· 09/03/17
· 27/09/17
1,000.00 - 100 Target achieved
12. Construct 1No. Market Facility
at Mankranso
Enhancing
Competitiveness of
Ghana’s Private Sector
Mankranso - 5,000.00 IGF/
GOG
- - - - - - Target not
achieved
5
Item Project Description Thematic Area of
Policy Framework
Location Contractor/
Consultant
Contract
Sum/ Budget
(GH¢)
Source of
Funding
Date of
Award (D/M/Y)
Date
Started (DD/MM/YY)
Expected Date
of Completion (DD/MM/YY)
Expenditure
to Date
(GH¢)
Outstanding
Balance
(GH¢)
Implementa
tion Status
(%)
Remarks
13. Organise market forum for
market users in the District
Accelerated Agriculture
Modernisation And
Sustainable Natural
Resource Management
District
Wide
Health Dept
(Env’t
Health Unit)
1,000.00 IGF - · 09/01/17
· 10/04/17 18/07/17
· 29/10/17
· 11/03/17
· 12/04/17
· 20/07/17
· 31/10/17
1,000.00 - 100 Target achieved
(Organised in all
10 Area Councils)
14. Conduct Annual Farmers' Day in
the District
Accelerated Agriculture
Modernisation And
Sustainable Natural
Resource Management
Mankranso Agriculture
Dept
35,000.00 DACF - · 05/12/17 · 05/12/17 39,960.00 - 100 Target achieved
15. Provide Training Support in climate change and green
economy for the District
Agriculture Department
Accelerated Agriculture
Modernisation And
Sustainable Natural
Resource Management
District Wide
Agriculture Dept
6,000.00 IGF - · 06/02/17
· 13/06/17
· 06/09/17
· 21/11/17
· 07/02/17
· 14/06/17
· 07/06/17
· 22/11/17
3,000.00 - 100 Target achieved
16. Provide support to Agriculture
Extension Officers (AEOs) to
undertake farm visits to train farmers
in Climate Change and Green
Economy
Accelerated Agriculture
Modernisation And
Sustainable Natural
Resource Management
District Wide
Agriculture Dept
4,000.00 GOG - · 02/01/17
· 03/04/17
· 04/07/17
· 02/10/17
· 31/03/17
· 30/06/17
· 29/09/17
· 29/12/17
2,000.00 - 100 Target achieved
17. Activate and register 104 existing
farmers group and form 26 new
groups into cohesive and functional
group in modern technology of
farming in green economy and soil
management practices
Accelerated Agriculture
Modernisation And
Sustainable Natural
Resource Management
District
Wide
Agriculture
Dept
4,000.00 GOG - · 02/01/17
· 03/04/17
· 04/07/17
· 02/10/17
· 31/03/17
· 30/06/17
· 29/09/17
· 29/12/17
2,000.00 - 100 Target achieved
18. Provide loan facilities for 300 farmers under SIF-IRDP
Accelerated Agriculture
Modernisation And
Sustainable Natural
Resource Management
District Wide
50,000.00 SIF/ DACF
- - - - - - Not Implemented
19. Organise 4 Training
Programmes on Rice Production under Local Economic
Development in the District
Accelerated Agriculture
Modernisation And
Sustainable Natural
Resource Management
District
Wide
Agriculture
Dept
4,000.00 GOG - · 19/03/17
· 12/06/17
· 26/09/17
· 29/11/17
· 20/03/17
· 13/06/17
· 27/06/17
· 30/11/17
1,000.00 - 100 Target achieved
20. Undertake 52 weekly market
data collection under Local Economic Development
Accelerated Agriculture
Modernisation And
Sustainable Natural
Resource Management
District
Wide
Agriculture
Dept
4,000.00 GOG - · 01/01/17
· 31/12/17
1,000.00 - 100 Target achieved
21. Acquire 10,000 doses of thermo
stable Newcastle disease
vaccines and 1,000 doses of PPR vaccine for routine vaccination
Accelerated Agriculture
Modernisation And
Sustainable Natural
Resource Management
District
Wide
Agriculture
Dept
4,000.00 GOG - · 09/01/17
· 12/04/17
· 03/07/17
· 11/10/17
· 09/01/17
· 12/04/17
· 03/07/17
· 11/10/17
1,000.00 - 100 Target achieved
22. Train 400 farmers and agro-chemical
dealers in correct handling of Agro-
chemicals in support of climate
change and green economy
Accelerated Agriculture
Modernisation And
Sustainable Natural
Resource Management
District
Wide
Agriculture
Dept
4,524.00 GOG - · 06/02/17
· 26/04/17
· 07/08/17
· 11/12/12
· 07/02/17
· 27/04/17
· 08/08/17
· 12/12/17
1,000.00 - 100 Target achieved
23. CIDA support for Planting for
Food and Jobs and Climate
Change for agricultural activities
Accelerated Agriculture
Modernisation And
Sustainable Natural
Resource Management
District
Wide
Agriculture
Dept
126,665.00 CIDA - · 02/01/17
· 31/12/17
70,000.00 - 100 Target achieved
24. Facilitate the planting of trees degraded areas in the District
Accelerated Agriculture
Modernisation And
Sustainable Natural
Resource Management
District Wide
NADMO 10,000.00 DACF - · 02/01/17
· 31/12/17
5,000.00 - 100 Target achieved
6
Item Project Description Thematic Area of
Policy Framework
Location Contractor/
Consultant
Contract
Sum/ Budget
(GH¢)
Source of
Funding
Date of
Award (D/M/Y)
Date
Started (DD/MM/YY)
Expected Date
of Completion (DD/MM/YY)
Expenditure
to Date
(GH¢)
Outstanding
Balance
(GH¢)
Implementa
tion Status
(%)
Remarks
25. Provide support to Feeder Roads
operation and maintenance
activities and administrative support to Works Department
Infrastructure and
Human Settlements
Development
Mankranso Works Dept
(Feeder
Road Unit)
7,851.96 GOG/
IGF
- · 02/01/17
· 31/12/17
7,851.96 - 100 Target achieved
26. Reshape and construct culverts
on feeder roads in the District
Infrastructure and
Human Settlements Development
District
Wide
Works Dept
(Feeder Road Unit)
74,000.00 DACF - · 02/01/17
· 31/12/17
74,000.00 - 100 Target achieved
27. Provide Street Light Bulbs and
Solar Lamps to curb the
incidence of crime in the District
Infrastructure and
Human Settlements
Development
District
Wide
Procurement
Unit/
Storekeeper
30,000.00 DACF - · 02/01/17
· 31/12/17
10,000.00 - 100 Target achieved
28. Construct, mechanise and
rehabilitate 10No. boreholes in
the District
Infrastructure and
Human Settlements
Development
District
Wide
Works Dept 100,000.00 DACF/
DDF
- · 02/01/17
· 31/12/17
- - 75 Target not
achieved
29. Complete the construction of 1No. 12-seater Aqua Privy
Public Toilet at Asuadei
Infrastructure and Human Settlements
Development
Asuadei Maasim
Construction
Works/Works
Dept
104,845.29 DDF 25/11/16
· 29/11/16
· 25/03/17
104,668.50 - 100 Target achieved
30. Complete the construction of
1No. 12-seater Aqua Privy Public Toilet at Aburaso
Infrastructure and
Human Settlements Development
Aburaso Havakye
Enterprise/ Works Dept
104,989.11 DDF 25/11/16
· 30/11/16
· 25/03/17
104,833.50 - 100 Target achieved
31. Complete the construction of
1No. 16-seater Aqua Privy Public Toilet at Pokukrom
Infrastructure and
Human Settlements Development
Pokukrom Rich 3K’s
Construction
& Trading Ent.
129,642.10 DACF 22/09/16
· 01/10/16
· 22/01/17
129,572.60 - 100 Target achieved
32. Rehabilitate 5No. Public Toilets
in selected communities in the
District
Infrastructure and
Human Settlements
Development
Mankranso
Amakom,/ Nsuta
Dwenewoho,
Dunyan Nkwanta
Destex
Enterprise/
Works Dept
110,277.00 DACF 13/07/16
· 20/07/16
· 12/10/17
110,277.00 - 100 Target achieved
33. Organise monthly National
Sanitation Day in the District
Infrastructure and
Human Settlements
Development
District
Wide
Health Dept
(Env’t Health
Unit)
6,000.00 IGF - · 07/01/17
· 02/12/17
4,000.00 - 100 Target achieved
34. Procure Assorted Refuse
Management Equipment and
Chemical Detergents for the
Environmental Health Unit to
improve environmental sanitation
Infrastructure and
Human Settlements Development
Mankranso Health Dept
(Env’t Health Unit)
10,000.00 IGF - · 07/03/17
· 12/06/17
· 28/09/17
· 15/11/17
· 07/03/17
· 12/06/17
· 28/09/17
· 15/11/17
5,000.00 - 100 Target achieved
35. Pay Refuse Attendants in the
District
Infrastructure and
Human Settlements
Development
District
Wide
Health Dept
(Env’t Health
Unit)
12,000.00 IGF - · 31/01/17
· 31/12/17
12,000.00 - 100 Target achieved
36. Fumigate the District against diseases
Infrastructure and Human Settlements
Development
District Wide
Health Dept (Env’t
Health Unit)
212,000.00 DACF - · 07/03/17
· 12/06/17
· 28/09/17
· 15/11/17
· 07/03/17
· 12/06/17
· 28/09/17
· 15/11/17
212,000.00 - 100 Target achieved
37. Implement Community Led Total Sanitation activities in the
District – (Sanitation
Improvement Package/Final Disposal Site Management)
Infrastructure and Human Settlements
Development
District Wide
Health Dept (Env’t
Health Unit)
150,000.00 DACF - · 07/03/17
· 12/06/17
· 28/09/17
· 15/11/17
· 07/03/17
· 12/06/17
· 28/09/17
· 15/11/17
150,000.00 - 100 Target achieved
38. Organise educational campaigns
on safe handling of food and
screen food/drinks vendors
Infrastructure and
Human Settlements
Development
District
Wide
Health Dept
(Env’t
Health Unit)
5,000.00 IGF - · 13/03/17
· 15/06/17
· 20/09/17
· 14/11/17
· 14/03/17
· 16/06/17
· 21/09/17
· 15/11/17
1,000.00 - 100 Target achieved
7
Item Project Description Thematic Area of
Policy Framework
Location Contractor/
Consultant
Contract
Sum/ Budget
(GH¢)
Source of
Funding
Date of
Award (D/M/Y)
Date
Started (DD/MM/YY)
Expected Date
of Completion (DD/MM/YY)
Expenditure
to Date
(GH¢)
Outstanding
Balance
(GH¢)
Implementa
tion Status
(%)
Remarks
39. Organise sensitization
programmes on cholera
prevention in the District
Infrastructure And
Human Settlements
Development
District
Wide
Health Dept
(Env’t
Health Unit)
5,000.00 IGF - · 13/03/17
· 15/06/17
· 20/09/17
· 14/11/17
· 14/03/17
· 16/06/17
· 21/09/17
· 15/11/17
1,000.00 - 100 Target achieved
40. Evacuate/Push refuse dump
sites in the District
Infrastructure And
Human Settlements
Development
Mankranso
Kunsu
Health Dept
(Env’t
Health Unit)
50,000.00 DACF - · 14/04/17
· 20/10/17
· 15/04/17
· 21/10/17
30,000.00 - 100 Target achieved (Two refuse dumps
were evacuated)
41. Organise Stakeholder’s meeting on proper usage of land in the
District
Infrastructure And Human Settlements
Development
District Wide
Physical Planning
Department
(T&CP)
1,000.000 GOG - · 28/03/17
· 13/06/17
· 07/09/17
· 29/11/17
· 28/03/17
· 13/06/17
· 07/09/17
· 29/11/17
1,000.00 - 100 Target achieved
42. Prepare settlement layout for community in the District
Infrastructure And Human Settlements
Development
District Wide
- 3,000.00 DACF - - - - - - Not Implemented
43. Provide support for the T&CP
Unit and Works Department to promote housing standards,
design and construction
Infrastructure And
Human Settlements Development
District
Wide
Physical
Planning Department
(T&CP)
4,355.00 GOG/
IGF
- · 02/01/17
· 31/12/17
4,355.00 - 100 Target achieved
44. Provide street names and property addressing in the
District
Infrastructure and Human Settlements
Development
Kunsu Physical
Planning
Department
(T&CP)
20,000.00 DACF - · 02/01/17
· 31/12/17
5,000.00 - 100
Target achieved
45. Provide quarterly support to District
Education Fund / DEOC/ SPAM/
STMIE Clinic to celebrate girl child
education week and other girl child
related activities
Human
Development,
Productivity and Employment
District
Wide
Education
Dept
37,135.18 DACF/
IGF
- · 28/03/17
· 13/06/17
· 07/09/17
· 29/11/17
· 28/03/17
· 13/06/17
· 07/09/17
· 29/11/17
5,000.00 - 100 Target achieved
46. Identify and provide bursaries to
Needy Students to promote especially
Girl Child Education in the District
Human Development,
Productivity and
Employment
District Wide
Education Dept
20,000.00 DACF - · 02/01/17
· 31/12/17
27,602.00 - 100 Target achieved
47. Organise My First Day at School
for boys and girls in the District
Human Development,
Productivity and
Employment
District
Wide
Education
Dept
7,000.00 DACF - · 12/09/17
· 12/09/17
7,000.00 - 100 Target achieved
48. Support the implementation of School Feeding Programme to
promote Girl Child Education
Human Development,
Productivity and
Employment
District Wide
MWCSP 35,969.75 Pooled - · 10/01/17
· 02/05/17
· 12/09/17
· 06/04/17
· 03/08/17
· 14/12/17
35,969.75 - 100 Target achieved
49. Organise literacy/quiz
competitions to promote gender competition
Human Development,
Productivity and
Employment
District
Wide
Education
Dept
2,000.00 DACF - · 28/03/17
· 13/06/17
· 05/10/17
· 28/03/17
· 13/06/17
· 05/10/17
2,000.00 - 100 Target achieved
50. Organise Mock Examinations for BECE candidates in the
District
Human Development,
Productivity and
Employment
District Wide
Education Dept
5,000.00 DACF - · 14/02/17
· 21/03/17
· 02/05/17
· 17/02/17
· 24/03/17
· 05/05/17
5,000.00 - 100 Target achieved
51. Organise training workshops for NFED Facilitators, NSS
Personnel and Trainees
Human Development,
Productivity and
Employment
District Wide
Education Dept
1,000.000 DACF - · 28/03/17
· 13/06/17
· 05/10/17
· 13/12/17
· 28/03/17
· 13/06/17
· 05/10/17
· 13/12/17
1,000.00 - 100 Target achieved
52. Facilitate the employment of youths under NYEA
Human Development,
Productivity and
Employment
District Wide
Education Dept
1,000.000 GOG - · 02/01/17
· 31/12/17
1,000.00 - 100 Target achieved
8
Item Project Description Thematic Area of
Policy Framework
Location Contractor/
Consultant
Contract
Sum/ Budget
(GH¢)
Source of
Funding
Date of
Award (D/M/Y)
Date
Started (DD/MM/YY)
Expected Date
of Completion (DD/MM/YY)
Expenditure
to Date
(GH¢)
Outstanding
Balance
(GH¢)
Implementa
tion Status
(%)
Remarks
53. Provide support to sports and
culture
Human Development,
Productivity and
Employment
District
Wide
Education
Dept
8,000.000 DACF - · 02/01/17
· 31/12/17
1,000.00 - 100
Target achieved
54. Provide support to maintenance
of school buildings
Human Development,
Productivity and
Employment
District
Wide
Works Dept 16,000.00 IGF - · 02/01/17
· 31/12/17
10,000.00 - 100 Target achieved
55. Rehabilitate 1No. 6-Unit Classroom Block at Potrikrom
Human Development,
Productivity and
Employment
Potrikrom Maasim
Construction
Works
140,820.20 DACF 14/01/16
· 20/01/16
· 10/11/17
140,820.20 - 100 Target achieved
56. Rehabilitate 1No. 6-Unit
Classroom Block at Nsuta
Human Development,
Productivity and
Employment
Nsuta - 147,000.00 DACF - - - - - - Not Implemented
57. Complete the construction of
1No. 3-Unit Classroom Block
with Office, Store, 4-Seater KVIP and Urinal at Amokrom
Human Development,
Productivity and
Employment
Amokrom Fatop
Ventures/
Works Dept
164,969.28 DACF 14/01/16
· 20/01/16
· 27/11/17
160,857.60 - 100 Target achieved
58. Construct 1No. 6-Unit
Classroom Block with Office
and Store at Sabronum
Human Development,
Productivity and
Employment
Sabronum Okogyeaboat
Limited/
Works Dept
- SIF/
DACF
31/05/16
· 12/06/16
· 31/07/17
- - 70 Target not
achieved (Roofing
Stage)
59. Construct 1No. 6-Unit
Classroom Block with Office
and Store at Barniekrom
Human Development,
Productivity and
Employment
Barniekrom Adalk
Company
Limited
410,000.80 MOE 16/10/17
· 23/10/17
· 16/02/18
- - 60 Target not
achieved (Lentil
Stage)
60. Construct 1No. 3-Unit Classroom
Block Office, Store and 1No. 4-
Seater KVIP and Urinal at Asukese
Human Development,
Productivity and
Employment
Asukese - 170,000.00 DDF - - - - - - Not Implemented
61. Complete the construction of
2No. 3-Unit Teacher’s Quarters at Aponaponoso and Bonsukrom
Human Development,
Productivity and
Employment
Bonsukrom
and Aponaponoso
Bachor
Company
Limited/
Works Dept
129,483.50 DACF 22/09/16
· 29/09/16
· 22/12/16
46,935.92 82,547.58 60 Target not
achieved (Completion Stage)
62. Complete the construction of
1No. 4-Unit Teacher’s Quarters
at Sabronum Camp
Human Development,
Productivity and
Employment
Sabronum
Camp
Tonsuma
Construction
Work Ltd/ Add Design
173,933.90 DACF 26/01/12
· 28/01/12
· 12/09/17
173,933.90 - 100 Target achieved
63. Complete the construction of
1No. 4-Unit Teacher’s Quarters
at Pokuase
Human Development,
Productivity and
Employment
Pokuase Nickseth
Const. Comp.
Ltd/ Add
Design
124,191.00 DACF 26/01/12
· 31/01/12
· 26/07/12
89,128.66 35,062.34 60 Target not
achieved
(Lentil Stage)
64. Complete the construction of 3No. Teachers Quarters at
Abasua, Kunsu Dotiem and
Adanse Yawboadi
Human Development,
Productivity and
Employment
Abasua, Kunsu
Dotiem and
Adanse
Yawboadi
Works Dept 100,000.00 DDF - · 02/01/17
· 31/127/17
- - 50 Target not achieved (Completion Stage)
65. Manufacture and Supply of 550 dual desks and 150 teachers’
tables and chairs in the District
Human Development,
Productivity and
Employment
District Wide
- 100,000.00 DDF - - - - - - Not Implemented
66. Provide support for roll back malaria and immunisation (NID)
and other health programmes in
the District
Human Development,
Productivity and
Employment
District Wide
Health Dept. 10,000.00 DACF - · 08/03/17
· 13/06/17
· 04/09/17
· 04/12/17
· 15/03/17
· 20/06/17
· 11/09/17
· 11/12/17
10,000.00 - 100 Target achieved
67. Provide support to Health Programmes in the District
Human Development,
Productivity and
Employment
District Wide
Health Dept. 51,860.00 DACF - · 02/01/17
· 31/12/17
10,000.00 - 100 Target achieved
9
Item Project Description Thematic Area of
Policy Framework
Location Contractor/
Consultant
Contract
Sum/ Budget
(GH¢)
Source of
Funding
Date of
Award (D/M/Y)
Date
Started (DD/MM/YY)
Expected Date
of Completion (DD/MM/YY)
Expenditure
to Date
(GH¢)
Outstanding
Balance
(GH¢)
Implementa
tion Status
(%)
Remarks
68. Complete the construction of
1No. CHPS Compound with
1No. 2-Seater KVIP with Bathroom at Abesewa
Human Development,
Productivity and
Employment
Abesewa Works Dept 51,860.00 DDF - · 02/01/17
· 31/127/17
- - 10 Target not
achieved
(Completion Stage)
69. Complete the construction of
1No. Maternity Home at Fawoman
Human Development,
Productivity and
Employment
Fawoman Okogyeaboat
Limited/ Works Dept
- SIF/
DACF
31/05/16
· 12/06/16
· 31/07/17
- - 70 Target not
achieved (Roofing Stage)
70. Complete the construction of
1No. Community Clinic at
Kunsu Camp
Human Development,
Productivity and
Employment
Kunsu Camp Okogyeaboat
Limited/
Works Dept
- SIF/
DACF
31/05/16
· 12/06/16
· 31/07/17
- - 70 Target not
achieved (Roofing
Stage)
71. Complete the construction of 1No. Nurses Quarters at
Sabronum
Human Development,
Productivity and
Employment
Sabronum Okogyeaboat Limited/
Works Dept
- SIF/ DACF
31/05/16
· 12/06/16
· 31/07/17
- - 70 Target not achieved (Roofing
Stage)
72. Facilitate the construction of
1No. Paediatric Ward at
Mankranso Government Hospital
Human Development,
Productivity and
Employment
Mankranso Nti Asante
Ghana Ltd./
Works Dept
179,830.81 NHIS 24/05/14
· 31/05/14
· 24/02/15
149,252.57 30,578.24 70 Target not
achieved (Roofing
Stage)
73. Provide monthly support for the
co-ordination and management
of HIV/AIDS programmes in the District
Human Development,
Productivity and
Employment
Mankranso Health Dept. 2,000.00 DACF - · 02/01/17
· 31/12/17
2,000.00 - 100 Target achieved
74. Organise quarterly monitoring
and evaluation of HIV/AIDS programmes in the District
Human Development,
Productivity and
Employment
District
Wide
Health Dept. 2,000.00 DACF - · 08/03/17
· 13/06/17
· 04/09/17
· 04/12/17
· 08/03/17
· 13/06/17
· 04/09/17
· 04/12/17
2,000.00 - 100 Target achieved
75. Organise Educational
Campaigns on HIV Testing and Counseling (HTC)
Human Development,
Productivity and
Employment
District
Wide
Health Dept. 2,000.00 DACF - · 10/03/17
· 15/06/17
· 06/09/17
· 06/12/17
· 10/03/17
· 15/06/17
· 06/09/17
· 06/12/17
2,000.00 - 100 Target achieved
76. Organise Annual Stakeholder’s
Workshop on HIV/AIDS and other STIs under Community
System Strengthening
Human Development,
Productivity and
Employment
Mankranso Health Dept. 2,000.00 DACF - · 20/12/17
· 20/12/17
2,000.00 - 100 Target achieved
77. Organise Educational Campaigns on causes and
impacts of HIV/AIDS and other
STIs under Behaviour Change Communication in the District
Human Development,
Productivity and
Employment
District Wide
Health Dept. 2,000.00 DACF - · 10/03/17
· 15/06/17
· 06/09/17
· 06/12/17
· 10/03/17
· 15/06/17
· 06/09/17
· 06/12/17
2,000.00 - 100 Target achieved
78. Provide all year round support
for PLWHIV
Human Development,
Productivity and
Employment
District
Wide
Health Dept. 2,000.00 DACF - · 02/01/17
· 31/12/17
2,000.00 - 100 Target achieved
79. Sensitize 10 communities on the dangers and effects of child
labour and abuse
Human Development,
Productivity and
Employment
District Wide
SW Dept. 1,000.00 GOG - · 29/03/17
· 28/06/17
· 26/09/17
· 29/11/17
· 29/03/17
· 28/06/17
· 26/09/17
· 29/11/17
1,000.00 - 100 Target achieved
10
Item Project Description Thematic Area of
Policy Framework
Location Contractor/
Consultant
Contract
Sum/ Budget
(GH¢)
Source of
Funding
Date of
Award (D/M/Y)
Date
Started (DD/MM/YY)
Expected Date
of Completion (DD/MM/YY)
Expenditure
to Date
(GH¢)
Outstanding
Balance
(GH¢)
Implementa
tion Status
(%)
Remarks
80. Supervise and monitor activities
of Day Care Center
Human Development,
Productivity and
Employment
District
Wide
Social
Welfare Unit
1,000.00 GOG - · 14/02/17
· 21/05/17
· 07/08/17
· 24/10/17
· 15/02/17
· 22/05/17
· 08/08/17
· 25/10/17
1,000.00 - 100 Target achieved
81. Provide support and monitor
progress of vulnerable and
marginalised persons under LEAP
Human Development,
Productivity and
Employment
District
Wide
Social
Welfare Unit
1,9650.00 GOG - · 28/02/17
· 27/04/17
· 29/06/17
· 30/08/17
· 31/10/17
· 28/12/17
· 28/02/17
· 27/04/17
· 29/06/17
· 30/08/17
· 31/10/17
· 28/12/17
1,9650.00 - 100 Target achieved
82. Train and sponsor PWDs in
income generating activities in Local Economic Development
Human Development,
Productivity and
Employment
District
Wide
Social
Welfare Unit
64,939.00 DACF - · 14/02/17
· 17/04/17
· 18/07/17
· 11/10/17
· 16/02/17
· 18/04/17
· 19/05/17
· 12/10/17
64,939.00 - 100 Target achieved
83. Provide administrative support to
Social Welfare and Community
Development Department
Human Development,
Productivity and
Employment
District
Wide
Social
Welfare Unit
8,200.00 DACF/
IGF
- · 02/01/17
· 31/12/17
8,200.00 - 100 Target achieved
84. Train 100 women in income
generating activities and home
management
Human Development,
Productivity and
Employment
District
Wide
Community
Devt Unit
800.00 GOG - · 14/02/17
· 21/05/17
· 07/08/17
· 24/10/17
· 15/02/17
· 22/05/17
· 08/08/17
· 25/10/17
800.00 - 100 Target achieved
85. Sensitise communities to
undertake self-initiated projects
Human Development,
Productivity and
Employment
District
Wide
Community
Devt Unit
2,050.00 GOG - · 14/03/17
· 20/04/17
· 05/07/17
· 22/11/17
· 14/03/17
· 20/04/17
· 05/07/17
· 22/11/17
2,050.00 - 100 Target achieved
86. Organise stakeholders meeting for
100 participants to discuss
community participation in
development projects and
programmes
Human Development,
Productivity and
Employment
District
Wide
Community
Devt Unit
500.00 GOG - · 14/03/17
· 20/04/17
· 05/07/17
· 22/11/17
· 14/03/17
· 20/04/17
· 05/07/17
· 22/11/17
500.00 - 100 Target achieved
87. Provide support services for
NGOs/ Donor funded projects
through monitoring
Human Development,
Productivity and
Employment
Mankranso Community
Devt Dept.
500.00 GOG - · 02/01/17
· 31/12/17
500.00 - 100 Target achieved
88. Pay Utilities Bills (Electricity, Water and Post Office etc.) and
Bank Charges
Transparent And Accountable
Governance
Mankranso Central Adm Dept
19,500.00 IGF - · 02/01/17
· 31/12/17
19,500.00 - 100 Target achieved
89. Provide for maintenance of
equipment and machinery, repairs of
vehicles, running cost and lubricants
for official vehicles
Transparent And Accountable
Governance
Mankranso Central Adm Dept
146,500.00 DACF/ IGF
- · 02/01/17
· 31/12/17
146,500.00 - 100 Target achieved
90. Pay transfer grants for staff Transparent And
Accountable
Governance
Mankranso Central Adm
Dept
10,000.00 IGF - · 02/01/17
· 31/12/17
10,000.00 - 100 Target achieved
91. Provide for hosting of official guests, Donations and
refreshment
Transparent And Accountable
Governance
Mankranso Central Adm Dept
25,243.00 IGF - · 02/01/17
· 31/12/17
25,243.00 - 100 Target achieved
92. Provide for maintenance of office, office buildings, official
bungalows, furniture and fittings
Transparent And Accountable
Governance
Mankranso Works Dept 60,000.00 DACF/ IGF
- · 02/01/17
· 31/12/17
60,000.00 - 100 Target achieved
11
Item Project Description Thematic Area of
Policy Framework
Location Contractor/
Consultant
Contract
Sum/ Budget
(GH¢)
Source of
Funding
Date of
Award (D/M/Y)
Date
Started (DD/MM/YY)
Expected Date
of Completion (DD/MM/YY)
Expenditure
to Date
(GH¢)
Outstanding
Balance
(GH¢)
Implementa
tion Status
(%)
Remarks
93. Provide for printed materials and
stationery
Transparent and
Accountable
Governance
Mankranso Central Adm
Dept
30,000.00 DACF/
IGF
- · 02/01/17
· 31/12/17
30,000.00 - 100 Target achieved
94. Provide for other administrative
expenses and NALAG Dues and
Dailies
Transparent and
Accountable
Governance
District
Wide
Central Adm
Dept
161,427.56 DACF/
IGF
- · 02/01/17
· 31/12/17
161,427.56 - 100 Target achieved
95. Support National Celebrations and Senior Citizenship Day (6th
March, Religious Festivities etc)
Transparent and Accountable
Governance
District Wide
Central Adm Dept
80,000.00 DACF - · 06/06/17
· 01/07/17
· 06/06/17
· 01/07/17
80,000.00 - 100 Target achieved
96. Organise Workshop for women
economic and political
empowerment
Transparent and
Accountable
Governance
District
Wide
Central Adm
Dept
10,000.00 DACF - · 20/03/17
· 26/06/17
· 12/09/17
· 30/11/17
· 20/03/17
· 26/06/17
· 12/09/17
· 30/11/17
10,000.00 - 100 Target achieved
97. Provide support to security
services
Transparent and
Accountable
Governance
District
Wide
Central Adm
Dept
17,000.00 DACF - · 02/01/17
· 31/12/17
17,000.00 - 100 Target achieved
98. Establish and strengthen sub-
district structures
Transparent and
Accountable
Governance
District
Wide
Central Adm
Dept
67,135.18 DACF - · 02/01/17
· 31/12/17
67,135.18 - 100 Target achieved
99. Provide contingency and other unseen expenses (recurrent
expenditures)
Transparent and Accountable
Governance
District Wide
Central Adm Dept
260,958.02 DACF/ IGF
- · 02/01/17
· 31/12/17
260,958.02 - 100 Target achieved
100. Provide support to MPs CF/SIF Programmes and Projects
Transparent and Accountable
Governance
District Wide
Central Adm Dept
404,575.78 DACF/ SIF
- · 02/01/17
· 31/12/17
404,575.78 - 100 Target achieved
101. Renovate staff quarters in the District
Transparent and Accountable
Governance
Mankranso Works Dept 50,000.00 DACF - · 02/01/17
· 31/12/17
50,000.00 - 100 Target achieved
102. Complete the construction of
staff quarters at Mankranso
Transparent and
Accountable
Governance
Mankranso Works Dept 50,000.00 DACF - · 02/01/17
· 31/12/17
- - 50 Target achieved (Completion Stage)
103. Construction and mechanisation
of boreholes at Assembly’s
residential area
Transparent and
Accountable
Governance
Mankranso - 20,000.00 DACF - - - - - - Not Implemented
104. Fabricate and fix burglar proof for Assembly’s Offices
Transparent and
Accountable
Governance
Mankranso Works Dept 20,000.00 DACF - · 02/01/17
· 31/12/17
20,000.00 - 100 Target achieved
105. Provide support to Community Initiated Projects
Transparent and
Accountable
Governance
District Wide
Central Adm Dept
167,838.00 DACF - · 02/01/17
· 31/12/17
167,838.00 - 100 Target achieved
106. Pay counterpart funding to
support SIF programmes and projects
Transparent and
Accountable Governance
District
Wide
Central Adm
Dept
334,565.55 DACF - · 02/01/17
· 31/12/17
100,000.00 - 50 Target not
achieved
107. Organise Monitoring and
Evaluation of all programmes
and projects quarterly and conduct Evaluation and PM&E
on selected programmes and
projects
Transparent and
Accountable
Governance
District
Wide
DPCU 30,000.00 DACF - · 15/01/17
· 09/04/17
· 09/07/17
· 08/10/17
· 16/03/17
· 22/06/17
· 21/09/17
· 21/12/17
30,000.00 - 100 Target achieved
12
Item Project Description Thematic Area of
Policy Framework
Location Contractor/
Consultant
Contract
Sum/ Budget
(GH¢)
Source of
Funding
Date of
Award (D/M/Y)
Date
Started (DD/MM/YY)
Expected Date
of Completion (DD/MM/YY)
Expenditure
to Date
(GH¢)
Outstanding
Balance
(GH¢)
Implementa
tion Status
(%)
Remarks
108. Organise General Assembly and
Other Meetings of the Assembly
Transparent and
Accountable
Governance
District
Wide
Central Adm
Dept
92,437.00 IGF - · 19/04/17
· 19/09/17
· 22/12/17
· 19/04/17
· 19/09/17
· 22/12/17
92,437.00 - 100 Target achieved
109. Procure motorbikes for Assembly Members
Transparent and Accountable
Governance
District Wide
-
355,000.00 DACF - - - - - - Not Implemented
110. Support Capacity Building Programmes of the Assembly
under DACF and IGF
Transparent and Accountable
Governance
Mankranso Central Adm 46,000.00 DACF/ IGF
- · 02/01/17
· 31/12/17
46,000.00 - 100 Target achieved
111. Organise 4 Training Workshops
and procure office equipment for offices of the District Assembly
under DDF
Transparent and
Accountable Governance
Mankranso Central Adm 51,413.00 DDF - · 15/02/17
· 24/05/17
· 07/09/17
· 29/11/17
· 16/02/17
· 25/05/17
· 08/09/17
· 29/11/17
51,413.00 - 100 Target achieved
112. Collate data on all the disaster
prone communities in the District
Transparent and
Accountable Governance
District
Wide
NADMO &
Fire Service
5,000.00 DACF - · 02/01/17
· 31/12/17
5,000.00 - 100 Target achieved
113. Procure Relief Items for Disaster Victims in the District
Transparent and Accountable
Governance
District Wide
NADMO & Fire Service
25,000.00 DACF - · 02/01/17
· 31/12/17
25,000.00 - 100 Target achieved
114. Organise 4 Public Education on Disaster Prevention and
Management
Transparent and Accountable
Governance
District Wide
NADMO & Fire Service
13,000.00 DACF - · 16/02/17
· 25/05/17
· 08/09/17
· 29/11/17
· 16/02/17
· 25/05/17
· 08/09/17
· 29/11/17
13,000.00 - 100 Target achieved
115. Facilitate with the District Fire Service and National Ambulance
Service to response to disasters
in the District
Transparent and Accountable
Governance
District Wide
NADMO & Fire Service
3,000.00 IGF - · 02/01/17
· 31/12/17
3,000.00 - 100 Target achieved
116. Construct 1No. Fire Station with
mechanised borehole at
Mankranso
Transparent and
Accountable
Governance
Mankranso - 200,000.00 DDF - - - - - - Not Implemented
Source: DPCU-AASDA, January, 2018
13
2.2 Update on Funding Sources
A total of GH¢3,694,620.38 was the amount received by the Ahafo-Ano South District Assembly by the end of the 2017 fiscal year. The range of the
revenue sources include Internal Generated Fund (IGF), District Assemblies Common Fund (DACF), Member of Parliament Common Fund (MPCF),
Disability Common Fund (PWDCF), MSHAP, Ghana School Feeding Programme (GSFP), SRWSP, District Development Facility (DDF) and
Livelihood Empowerment Against Poverty (LEAP) A summary of the trend of revenue performance of the District is presented in Table 2.2. As
shown on Table 2.2, out of the GH¢5,216,803.68 estimated by the end of 2017, an amount of GH¢3,694,620.38 was realized representing a 70.8
percent. However, the Assembly’s inability to implement 11 programmes, projects and activities representing 9.4 percent out of the 116 programmes,
projects and activities, is attributed to the untimely release of DACF and non-payment of DDF arrears for 2013 and 2014.
In order to generate enough IGF, adequate measures have been put in place to educate the public on the need to pay rates. In addition, several actions
were taken by the Assembly to improve upon the revenue collection and management during the year, 2017. These included compilation of revenue
database register for major towns in the District, establishment of a Revenue Task Force and successful implementation of the 2017 Revenue
Improvement Action Plan.
Table 2.2: Update on Revenue Sources from 2013 to 2017 Sources of Revenue 2013
Baseline
(GH¢)
2017
Target
(GH¢)
2017
Actual
(GH¢)
2016
Target
(GH¢)
2016
Actual
(GH¢)
2015
Target
(GH¢)
2015
Actual
(GH¢)
2014
Target
(GH¢)
2014
Actual
(GH¢)
Internal Generated Fund (IGF) 204,173.98 491,164.80 389,758.44 470,018.76 365,320.96 281,600.88 712,251.55 420,477.96 424,131.10
District Assemblies Common Fund (DACF) 378,504.38 3,242,700.24 2,514,025.07 3,112,360.08 1,802,591.17 4,596,918.96 1,538,218.19 2,323,725 523,092.45
Member of Parliament Common Fund (MPCF) 27,115.04 294,576.00 466,567.19 267,796.20 591,793.65 142,898.28 325,427.98 142,898.28 232,658.46
Disability Common Fund (PWDCF) 47,440.57 71,037.96 0.00 59,710.45 59,710.45 64,938.96 34,514.53 64,939.08 52,593.88
MSHAP 4,000.00 0.00 - - - - - - -
Ghana School Feeding Programme (GSFP) 49,041.20 164,990.76 0.00 391,853.04 0.00 391,853.04 145,635.00 424,790.04 313,741.50
SRWSP - - - 7,975.56 0.00 212,000.04 0.00 212,000.04 0.00
District Development Facility (DDF) 427,589.04 879,874.92 251,810.68 887,789.04 567,562.51 891,153.48 0.00 132,1284.12 926,923.68
Livelihood Empowerment Against Poverty (LEAP) 72,459.00 72,459.00 72,459.00 72,459.00 72,459.00 72,459.00 72,459.00 72,459.00 72,459.00
Total 1,210,323.21 5,216,803.68 3,694,620.38 5,269,962.13 3,459,437.74 6,653,822.64 2,828,506.25 4,982,573.52 2,545,600.07 Source: DPCU-AASDA, January, 2018
14
2.3 Update on Disbursement
In order to ensure effective implementation every plan and budget, revenue and expenditure report played a key role for successful implementation.
This section of the progress report brings on board the revenue and expenditure for the year under review. This will demonstrate the total revenue
generated within the year and how funds were released to finance the expenditure of the 2017 Composite Budget and the 2017 Composite Annual
Action Plan
From Table 2.3, in 2017, an amount GH¢3,683,620.38 representing (70.8 percent) out of the total estimated expenditure of GH¢5,216,803.68 was
spent. However, out of the total actual receipts of GH¢3,694,620.38, the District spent within the budget leaving a balance surplus of GH¢11,000.00
(0.3 percent). All the four expenditure items represent all the programmes, projects and activities in the 2017 Composite Annual Action Plan and
2017 Composite Budget, which were prepared from the DMTDP 2014-2017.
Table 2.3: Update on Expenditure from 2013 to 2017 Expenditure Item 2013
Baseline
(GH¢)
2017
Target
(GH¢)
2017
Actual
(GH¢)
2016
Target
(GH¢)
2016
Actual
(GH¢)
2015
Target
(GH¢)
2015
Actual
(GH¢)
2014
Target
(GH¢)
2014
Actual
(GH¢)
Compensation 598,246.80 1,508,880.48 1,508,880.48 1,357,992.43 1,297,882.43 1,222,193.19 850,736.43 1,099,973.87 773,785.25
Goods and Service 196,629.41 1,272,302.84 936,298.21 1,545,336.08 899,108.81 2,141,793.20 645,447.84 1,658,884.28 617,002.86
Investment 49,041.20 375,669.32 112,315.90 399,097.48 100,806.87 291,853.04 145,635.00 291,853.04 98,741.50
Assets 365,343.80 2,059,951.04 1,126,125.79 1,967,536.14 1,101,529.63 2,997,983.21 1,175,235.98 1,931,862.33 1,054,613.46
TOTAL 1,209,261.21 5,216,803.68 3,683,620.38 5,269,962.13 3,399,327.74 6,653,822.64 2,817,055.25 4,982,573.52 2,544,143.07
Source: DPCU-AASDA, January, 2018
2.4 Update on Indicators and Targets
The NDPC in consultation with stakeholders has strategically devised twenty (20) core indicators and targets to track the performance of the
implementation of the 2017 Composite Annual Action Plan and the 2017 Composite Budget as well as the trend analysis of the implementation of
the DMTDP 2014-2017. Table 2.4 shows the performance indicators and targets for the implementation of 2017 Annual Action Plan and Composite
Budget. In general, the policy outcomes are affected by the delays in the release of the major funding sources (DACF and DDF) as they constitute
more than halve of the budgetary allocations to the Assembly.
15
Table 2.4: Performance of Core Indicators at the District Level No. Indicator (Categorised by GSGDA II Thematic Areas) 2013
Baseline
2017
Target
2017
Actual
2016
Target
2016
Actual
2015
Target
2015
Actual
2014
Target
2014
Actual
A PRIVATE SECTOR COMPETITIVENESS
1 Change in Yield of Selected Crops, Livestock and Fish (%):
a. Maize 60.1% 90.0% 79.2% 80.0% 70.5% 80.0% 68.3% 80.0% 65.2%
b. Rice (Milled) 45.2% 70.0% 60.1% 60.0% 55.1% 60.0% 50.3% 60.0% 46.5%
c. Cassava 50.5% 70.0% 61.5% 70.0% 58.4% 70.0% 55.2% 70.0% 51.2%
d. Yam 10.3% 20.0% 15.2% 20.0% 11.8% 20.0% 12.5% 20.0% 10.7%
e. Pineapple 5.2% 10.0% 7.0% 10.0% 7.4% 10.0% 6.1% 10.0% 5.8%
f. Pawpaw 2.1% 8.0% 2.5% 8.0% 2.5% 8.0% 2.2% 8.0% 2.2%
g. Mango 9.9% 20.0% 13.1% 20.0% 12.3% 20.0% 12.2% 20.0% 10.3%
h. Banana 40.5% 60.0% 51.5% 60.0% 48.1% 60.0% 45.4% 60.0% 43.5%
i. Fish 15.1% 20.0% 22.0% 20.0% 20.0% 20.0% 17.1% 20.0% 15.1%
j. Livestock 25.5% 50.0% 38.5% 50.0% 34.3% 50.0% 30.3% 50.0% 26.2%
2 Proportion/Length of Roads Maintained/Rehabilitated:
a. Trunk Roads (in km) NA NA NA NA NA NA NA NA NA
b. Urban Roads (in km) NA NA NA NA NA NA NA NA NA
c. Feeder Roads (in km) 21.4km 50km 50km 40km 97km 30km 30km 30km 30km
3 Percentage (%) Change in Number of Households with Access to Electricity 8.0% 10.0% 9.0% 10.0% 8.9% 10.0% 8.7% 10.0% 8.5%
4 Hectares of Degraded Forest, Mining, Dry and Wet Lands Rehabilitated/Restored:
a. Forest 0.02ha 0.50ha 0.03ha 0.50ha 0.02ha 0.50ha 0.02ha 0.50ha 0.02ha
b. Mining 0.01ha 0.50ha 0.02ha 0.50ha 0.01ha 0.50ha 0.01ha 0.50ha 0.01ha
c. Dry and Wetland 0.01ha 0.50ha 0.01ha 0.50ha 0.01ha 0.50ha 0.01ha 0.50ha 0.01ha
5 Change in Tourist Arrivals (%) 0 2 0 2 0 2 0 2 0
6 Tele density/Penetration Rate NA NA NA NA NA NA NA NA NA
B HUMAN RESOURCE DEVELOPMENT
7 HIV/AIDS Prevalence Rate (Percentage (%) of Adult Population, 15-49 Yrs. HIV Positive) 0.21% 0.05% 0.06% 0.05% 0.07% 0.05% 0.09% 0.05% 0.19%
8 Maternal Mortality Ratio (No. of Deaths due to Pregnancy and Childbirth per 100,000 Live Births) 0.002 0.000 0.001 0.000 0.001 0.000 0.001 0.000 0.000
9 Under-Five Mortality Rate (No. of Deaths occurring between Birth and Exact Age Five per 1,000 Live
Births)
0.006 0.000 0.003 0.000 0.004 0.000 0.004 0.000 0.005
10 Malaria Case Fatality in Children under Five Years per 10,000 Population 0.003 0.000 0.001 0.000 0.002 0.000 0.002 0.000 0.001
11 Percent of Population with Sustainable Access to Safe Water Sources 45.0% 60.0% 60.0% 55.0% 55.0% 55.0% 50.0% 55.0% 48.0%
12 Proportion of Population with Access to Improved Sanitation (Flush Toilets, KVIP, Household Latrine) 25.0% 30.0% 30.0% 30.0% 29.0% 30.0% 28.0% 30.0% 27.0%
13 a. Gross Enrolment Rate (Indicates the Number of Pupils/Students at a given Level of Schooling-
regardless of age - as Proportion of the Number Children in the Relevant Age Group):
- Primary 85.5% 95.0% 85.9% 95.0% 87.7% 95.0% 87.7% 95.0% 85.9%
- JHS 75.5% 90.0% 77.7% 90.0% 78.9% 90.0% 78.8% 90.0% 76.4%
- SHS 55.6% 70.0% 79.5% 70.0% 56.1% 70.0% 56.2% 70.0% 55.9%
b. Net Admission Rate in Primary Schools (Indicates Primary One Enrolment of Pupils Aged 6 years) 65.7% 95.0% 75.7% 95.0% 71.1% 95.0% 68.0% 95.0% 78.3%
14 Gender Parity Index (Ratio between Girls’ and Boys’ Enrolment Rates, the Balance of Parity is 1.00) 0.89 1.00 0.91 1.00 0.89 1.00 0.89 1.00 0.91
15 Proportion of Unemployed Youth benefiting from Skills/Apprenticeship and Entrepreneurial Training 5.0% 10.0% 8.0% 10.0% 6.5% 10.0% 6.0% 10.0% 5.0%
16
No. Indicator (Categorised by GSGDA II Thematic Areas) 2013
Baseline
2017
Target
2017
Actual
2016
Target
2016
Actual
2015
Target
2015
Actual
2014
Target
2014
Actual
C GOOD GOVERNANCE AND CIVIC RESPONSIBILITY
16 Total Amount of Internally Generated Revenue 204,173.98 491,164.80 389,758.44 470,018.76 365,320.96 281,600.88 712,251.55 420,477.96 424,131.10
17 Amount of Development Partner and NGO funds contribution to DMTDP Implementation 10,000.00 30,000.00 25,000.00 30,000.00 25,000.00 20,000.00 20,000.00 20,000.00 5,000.00
18 Percentage (%) of DA Expenditure within the DMTDP Budget
(How much of DA’s Expenditure was not in the Annual Budget?)
100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
19 Number of Reported Cases of Abuse (Children, Women and Men) 234 100 141 100 185 100 123 100 213
20 Police Citizen Ratio 1:4,864 1:500 1:3,378 1:500 1:3,576 1:500 1:3,800 1:500 1:4,053
Source: DPCU-AASDA, January, 2018
17
2.5 Update on Critical Development and Poverty Issues
This section provides the update of the critical development and poverty issues being
implemented in the District. These include Ghana School Feeding Programme, Capitation
Grants, National Health Insurance Scheme, Livelihood Empowerment Against Poverty
(LEAP) Programme, National Youth Employment Program, One District-One Factory
Programme, One Village-One Dam Programme, One Constituency-One Million Dollars
Programme, Planting for Food and Jobs Programme, Free SHS Programme, National
Entrepreneurship and Innovation Plan (NEIP) and Implementation of Infrastructural for
Poverty Eradication Programme (IPEP). In order to provide lasting solutions to the
challenges identified, policy recommendations have been provided under each section.
Table 2.5: Update on Critical Development and Poverty Issues in 2017 Critical Development
and Poverty Issues
Allocation
GH¢
Actual
Receipt GH¢
No. of Beneficiaries Remarks
Targets Actuals
Male Female Total
Ghana School Feeding
Programme 210,000.00 217,776.00 5,000 2,241 2,296 4,537
Timely release of the
School Feeding Grants
Capitation Grants 198,957.24 198,957.24 40,000 16,365 17,729 34,094 Timely release of the
Capitation Grants
National Health
Insurance Scheme 500,000.00 458,900.00 50,000 15,253 21,585 36,838
Provision of Office
Accommodation
Livelihood
Empowerment Against
Poverty (LEAP)
Programme
72,459.00 72,459.00 3,000 845 1,327 2,172
Provision of adequate
logistics
National Youth
Employment Programme 950,000.00 600,000 300 117 75 192
Timely payment of
Allowances to beneficiaries
One District-One
Factory Programme NA NA 100 - - -
Identification of Factories
in progress
One Village-One Dam
Programme NA NA 100 - - -
Yet to be implemented in
the District
One Constituency-One
Million Dollars
Programme
3,000,000.00 - 100,000 - - - Yet to be implemented in
the District
Planting for Food and
Jobs Programme 75,000.00 50,000.00 30,000 11,928 7,348 19,276
Timely provision of
Seedlings
Free SHS Programme 1,323,000.00 - 770 441 233 674 Timely release of the Free
SHS Grant
National
Entrepreneurship and
Innovation Plan (NEIP)
NA NA 50,000 - - - Yet to be implemented in
the District
Implementation of
Infrastructural for
Poverty Eradication
Programme (IPEP)
NA NA 50,000 - - - Yet to be implemented in
the District
Others
Sensitization Workshops
on LGS Protocols (SoS,
CoS, CoC, SDS, PMS, OM) 50,000.00 20,000.00 160 54 97 151
Timely release of the
Capacity Building Grants
Capacity Building
Programmes 100,000.00 60,000.00 160 54 97 151
Timely release of the
Capacity Building Grants
Source: DPCU-AASDA, January, 2018
18
2.6 Evaluations Conducted, Their Findings and Recommendations
Evaluation plays a vital role in the life of every project implementation as the feedback
always determines the success or failure of the project. Therefore, the evaluation of the
achievements of the 2017 Composite Annual Action Plan was conducted in two phases
that is before (Ex-ante Evaluation) and after (Terminal evaluation) the implementation of
the programmes, projects and activities based on the M&E Calendar and Budget. This
was performed by the DPCU with support from the collaborating Agencies and
Stakeholders.
The conduct of the evaluations involved scrutinizing the status-quo reports and the
analyzed data from both primary and secondary sources and comparing them with the
appraisal reports during and after the implementation of the year’s activities. Field
surveys including data collection, analysis, observations, presentation and reporting were
used to conduct the evaluation of the selected physical projects implemented in the year.
In addition, the DPCU and Stakeholders Forum were used to valid and confirm the data
before and after completion to ascertain if the intervention achieved its original objectives
and assess the overall changes caused by the implementation of the physical project.
From Table 2.6, 10 evaluations were conducted with for five Ex-ante Evaluations and the
other five for Terminal Evaluations.
The findings of the evaluation revealed that all the selected physical projects implemented
in the year, 2017, impacted positively on the quality life of the people in the District as
exhibited in Table 2.6. However, funding for the implementation of most projects are
lacking with respect to Central Government Transfers (DACF and DDF). It is therefore
recommended that funds should be released timely and adequately toward the
implementation of the 2018-2021 DMTDP. In addition, adequate funds should be made
readily available to conduct evaluations so as to improve decision making and provide
insights for effective programme, project and activity design and implementation in the
District.
19
Table 2.6: Update on Evaluations Conducted in 2017 Name of the
Evaluation
Policy/Programme/
Project Involved
Consultant or Resource Persons
Involved
Methodology Used Findings Recommendations
1. Ex-Ante
Evaluation
of
Physical
Projects
Construction of Physical Projects
including:
· Educational Facilities –
Classrooms, Teachers
Quarters, Institutional Latrines
· Health Facilities –Health
Centres, CHPS, Nurses
Quarters
· Water Facilities – Boreholes
· Sanitation Facilities –
Communal Toilet Facilities
· Roads
· District Co-ordinating Director
· District Planning Office
· District Budget Analyst
· District Finance Officer
· District Works Engineer
· Director, Ghana Health Service
· Director, Ghana Education Service
· Feeder Road Engineer
· Selected DPCU Members
· Assembly Members
· Community Water and Sanitation
Agency – Ashanti Region
· Field Surveys
including Data
Collection and
Analysis
· Observations
· Presentations
· Dissemination
· Report Writing
· Low Teachers’ conduct hours
· Low students’ attendance to school
· Low access to quality healthcare
· Low access to potable water
· Low access to improved sanitation
facilities
· High cost of transportation
· Provision of conducive environment for teaching and
learning (Classrooms, Teachers Quarters, Institutional
Latrines) to improve conduct hours and students
attendance
· Provision of Health Facilities (Health Centres, CHPS,
Nurses Quarters) to increase access to quality
healthcare
· Provision of water facilities (boreholes and mechanised
boreholes) to improve access to potable water
· Reshaping of feeder road network to reduce cost of
transportation in the District
2. Terminal
Evaluation
of
Physical
Projects
Construction of Physical Projects
including:
· Educational Facilities –
Classrooms, Teachers
Quarters, Institutional Latrines
· Health Facilities –Health
Centres, CHPS, Nurses
Quarters
· Water Facilities – Boreholes
· Sanitation Facilities –
Communal Toilet Facilities
· Roads
· District Co-ordinating Director
· District Planning Office
· District Budget Analyst
· District Finance Officer
· District Works Engineer
· Director, Ghana Health Service
· Director, Ghana Education Service
· Feeder Road Engineer
· Selected DPCU Members
· Assembly Members
· Community Water and Sanitation
Agency – Ashanti Region
· Field Surveys
including Data
Collection and
Analysis
· Observations
· Presentations
· Dissemination
· Report Writing
· Increased in Teachers’ conduct
hours from 3 hours in 2013 to 5
hours in 2017
· Increased in students’ attendance
from 32,546 in 2013 to 34,444 in
2017 representing 5.6% change
· Improved coverage access to
quality healthcare from 1:15
communities in 2013 to 1:9
communities in 2017
· Access to potable water coverage
increased from 45.0% in 2013 to
60.0% in 2017
· Access to improved sanitation
facilities increased from 25.0 % in
2013 to 30.0% in 2017
· Length of feeder road improved
from 200.0km in 2013 to 273.4km
in 2017 representing 36.7
percentage
· Provision of conducive environment for teaching and
learning (Classrooms, Teachers Quarters, Institutional
Latrines) to improve conduct hours and students
attendance
· Provision of Health Facilities (Health Centres, CHPS,
Nurses Quarters) to increase access to quality
healthcare
· Provision of water facilities (boreholes and mechanised
boreholes) to improve access to potable water
· Reshaping of feeder road network to reduce cost of
transportation in the District
· Funds should be released timely and adequately toward
the implementation of the 2018-2021 DMTDPs
(Composite Annual Action Plans)
· In addition, adequate funds should be made readily
available to conduct evaluations so as to improve
decision making and provide insights for effective
programme, project and activity design and
implementation in the District
Source: DPCU-AASDA, January, 2018
20
2.7 Participatory Monitoring and Evaluation Undertaken and Their Results
Participatory Monitoring and Evaluation (PM&E) refers to the practice where all key stakeholders are directly involved in the M&E design and
implementation process. For the 2017 under review, the District conducted PM&E using Community Score Card and Participatory Expenditure
Tracking Surveys in the implementation of 2017 Composite Annual Action Plan. The key stakeholders who participated in the two PM&E
through the stakeholders’ analysis included Traditional Authorities, Assembly Members, Unit Committee Members, Opinion Leaders,
Contractors, Heads of Decentralised Departments and other Agencies, Political Parties (NPP and NDC), Civil Society Organisations, Religious
Bodies, Financial Institutions, Artisans, Communities and Media. The details of the conduct of the PM&E is presented in Table 2.7.
Table 2.7: Update on PM&E Conducted Name of the
PM&E Tool
Policy/Programme/
Project Involved
Consultant or Resource Persons
Involved
Methodology Used Findings Recommendations
1. Participatory
Expenditure
Tracking
Surveys
(PETS) on
Public
Financial
Management
Organisation of Social
Accountability Programmes in
the area:
· External Funding Sources
· Internal Funding Sources
· Expenditure incurred on
the implementation of
Programmes, Projects and
Activities
· District Co-ordinating Director
· District Planning Office
· District Budget Analyst
· District Finance Officer
· District Works Engineer
· Town Hall Meeting
using Public
Financial
Management
Template (PFM)
· Public Hearings
· Field Surveys
· Observations
· Report Writing
· Delay in the completion of projects
· Delay and inadequate transfer of funds
from Central Government Transfer
· Low mobilisation of Internally Generated
Funds
· Low communal spirit in the
implementation of self-help projects
· Funds should be released timely and
adequately toward the implementation of
the 2018-2021 DMTDPs (Composite
Annual Action Plans)
· Ensuring effective implementation of
revenue Improvement Action Plans
· Organisation of sensitisation
programmes for community self-help
projects
2. Community
Score Card
(CSC) on
Physical
Projects
Construction of Physical
Projects including:
· Educational Facilities –
Classrooms, Teachers
Quarters, Institutional
Latrines
· Health Facilities –Health
Centres, CHPS, Nurses
Quarters
· Water Facilities –
Boreholes
· Sanitation Facilities –
Communal Toilet
Facilities
· Roads
· District Co-ordinating Director
· District Planning Office
· District Budget Analyst
· District Finance Officer
· District Works Engineer
· Director, Ghana Health Service
· Director, Ghana Education
Service
· Selected DPCU Members
· Assembly Members
· Traditional Authorities
· Unit Committee Members
· Opinion Leaders
· Contractors
· Other Key Stakeholders
· Site Meetings
· Observations
· Projects Reporting
· Delay in the completion of projects
· Low hiring of communal labour for
projects by Contractors
· Low payment of Internally Generated
Funds
· Inadequate provision of Social Amenities
such as education, health, water, sanitation,
energy, transportation, employment and
among others
· Provision of adequate funds for
completion of projects
· Identification of technical skills needed
by Contractors in the communities
· Organisation of sensitization programmes
on Internally Generated Funds
· Provision of Community Social
Amenities such as education, health,
water, sanitation, energy, transportation
and employment
Source: DPCU-AASDA, January, 2018
21
3.0 CONCLUSION AND THE WAY FORWARD
This section summarizes the 2017 Annual Progress Report by exhibiting the key issues
addressed and those yet to be addressed as well as the recommendations for successful
implementation of subsequent Composite Annual Action Plans (CAAP). The details are
outlined in the sub-section 3.1 and 3.2.
3.1 Summary of Key Issues Addressed in 2017 and Those Yet to be Addressed
In the course of implementation of the 2017 Composite Annual Action Plan, the
following key issues were identified and addressed successfully in 2017, which need to be
sustained for subsequent years.
· Funds for Monitoring and Evaluation activities were provided quarterly for the
District Monitoring Team to conduct the exercise with ease. This provided funds
for Quarterly M&E Reporting and the payment of Day Trip Allowances.
· Logistics in form of fuel, stationery and other Monitoring and Evaluation
materials were provided timely for the conduct of the M&E exercise in the
District. This provided solution to the logistical challenge raised by the District
Monitoring Team.
· Funds were released for the 10 Decentralised Departments of the Assembly to
carry-out their mandated programmes, projects and activities in the 2017
Composite Annual Action Plan. This addressed the challenge of lack of funds for
Departments to carry-out their activities in the 2017 CAAP.
However, the implementation of the 2017 Composite Annual Action Plan was challenged
with the following key issues which are yet to be addressed, possibly in 2018.
· Lack of assigned permanent vehicle for Monitoring and Evaluation of
programmes, projects and activities in the District. This pending issue is yet to be
rectified by management of the District Assembly.
· Inadequate and untimely release of DACF has negatively affected the
implementation of programmes, projects and activities in the District. This issue is
yet to be resolved by the District Assemblies Common Fund Administrator.
· The delay in the release of DDF for 2013 and 2014 have deferred the
implementation of DDF sourced projects and capacity building programmes in the
2017 Annual Action Plan. This challenge is yet to be addressed by the DDF
Secretariat under the Ministry of Local Government and Rural Development.
22
3.2 Recommendations
In conclusion, the way forward to address the challenges faced in the Monitoring and
Evaluation activities, in addition to those yet to be addressed, include the following.
· Provision of permanent vehicle for Monitoring and Evaluation exercise in the
District will help to improve the routine inspection and supervision of
programmes, projects and activities.
· Based on the challenges identified in the implementation of DACF programmes,
the Assembly recommends timely and adequately release of DACF to finance the
plan and budget implementation in the District.
· Based on the infrastructural challenges identified in the District, the Assembly
recommends timely release of DDF for 2013 and 2014 to finance the
implementation of infrastructural gaps identified.
· Regular reshaping of road network in the District will improve Monitoring and
Evaluation exercise.
· Organisation of Monitoring and Evaluation training programmes by the National
Development Planning Commission (NDPC) to equip District Monitoring Teams
with the required knowledge and experience.
· Setting-up DPCU Fund to promote the functionality of DPCU as enshrined in the
Local Governance Act 936, 2016 and the National Development Planning
(System) Regulations, LI 2232, 2016.
Recommended