2019SPRING MAINTENANCE BOARD REPORT

MEDVEJIE HATCHERY

NEW PUMP CONTROL AND PLC ALARM SYSTEM UPGRADES

Worked with Dan at Cooper Marine Services

Remote access to alarm system

VFD level tracking

Programmable level set points

PROGRAMABLE SET POINTS SCREEN

ELECTRIC HYDRO’S FOR THE NET WASHER AREA

• Installed electric hydraulic pack to operate the

net washer and block

• Replaced gas hydraulic pack

• Installed by hatchery staff

NEW GREEN LAKE BOAT CONSTRUCTION

• Specmar 18’ Outback kit

• This replaces our old roughneck

Skiff

• Being built by hatchery staff

SAWMILL CREEK HATCHERY

CONSTRUCTED AN INSULATED SHED OVER THE FIRE LINE CROSSOVER TAP

BUILT BY HATCHERY STAFF

GUNNUK CREEK HATCHERY TEMPORARY HYDRO INSTALL

PLUMBING IS CURRENTLY BEING INSTALLED BY HATCHERY STAFF

HIDDEN FALLS DOMESTIC WATER SYSTEM / CHLORINATION PUMP RE PLUMB

FABRICATING NEW JUMP OUT SCREENS AND CROWDERS FOR ADULT RACEWAYS

NEW ELECTRICAL RUN INSTALLED TO SEPTIC TANK

SHOP ORGANIZATION AND CLEAN UP