ASDSO Dam Safety 2013 Presentation

  • View
    462

  • Download
    0

  • Category

    Design

Preview:

Citation preview

UNDER PRESSURE: AGING OUTLET CONDUITS

Jeremy Young, PE

Tyson Clouser, PE

Dam Safety 2013 –

ASDSO National Conference

Providence, Rhode Island

September 9, 2013

CONDUITS THROUGH EMBANKMENT DAMS

2

AGING, PRESSURIZED CONDUITS

3

PRESENTATION OUTLINE

4

External Seepage and Earth Pressures

PRESSURIZED CONDUIT/DOWNSTREAM CONTROL

5

Ref: FEMA 484

Internal Water Pressure

PFMs ASSOCIATED WITH CONDUITS

6

• PFM 1: Erosion of Soils into a Nonpressurized Conduit

• PFM 2: Erosion by Flow from a Pressurized Conduit

• PFM 3: Erosion of Soils Along the Outside of a Conduit

• PFM 4: Erosion in the Earthfill Above/Below/Adjacent to a Conduit

PFM 2: EROSION BY FLOW FROM A PRESSURIZED CONDUIT

7Ref: FEMA 484

CONTRIBUTING FACTORS TO FAILURE

8

COMMON PFMs ASSOCIATED WITH IRON PIPES

9

Ref: NRCC

COMMON PFMs ASSOCIATED WITH IRON PIPES

10

Ref: NRCC

IDENTIFYING CORROSIVE POTENTIAL

11

CORROSION RATES

12

• As MC increases, so does corrosion rate

• Corrosion rates are slower under saturated conditions (Less Exposure to O2)

MOISTURE CONTENT

13

CORROSION RATES AS A FUNCTION OF TIME?

14

• Development Has Been Elusive to Researchers

• Generally Decrease with Time

• DIPRA provides average pitting rates for various soils on the 10-pt rating scale

Ref: Bonds et al. 2005

ESTIMATE LIFESPAN OF DUCTILE IRON PIPES

DIPRA Research –

Asphaltic Coated DIP

15

16Ref: Spickelmire 2012

DIP vs. CIP

INSPECTION OF PRESSURIZED CONDUITS

17

INSPECTION

• Requirements vary widely

Visible portions of outlet system are inspected, detailed internal inspection only required if problems noted.

Require detailed inspections on regular intervals, from 2 to 10 years.

Requirements on how a detailed inspection is defined varies, from only inspecting accessible portions of the outlet conduit to inspecting each and every portion of the outlet works system.

18

INSPECTION

• Inspections can be accomplished by manned entry or with push-cameras or ROVs, depending on size.

19

INSPECTION

• Visual quality in the wet is typically poor to accurately assess the condition / potential defects in the pipe.

• Recommended to dewater pipe Drain Reservoir? Not typically feasible, especially with water

supply reservoirs. Install Bulkhead on upstream end of pipe Access to downstream end of pipe?

20

DIFFICULT ACCESS - MANIFOLD SYSTEM

21

Flow

DIFFICULT ACCESS – VERTICAL BENDS

22

Flow

BULKHEAD/PLUG TYPES

• Steel Plate

23

BULKHEAD/PLUG TYPES

• Inflatable Plug

24

WHAT HAPPENS WHEN THE LIMITS ARE PUSHED?!

25

TURBERCULATION, PIPE CLEANING AND LINING

• Tuberculation - Friend or Foe? Hydraulic Capacity Concerns

Water Supply

Remove to facilitate effective inspection of pipe interior Tuberculation acts a protective layer

Corrosion begins more quickly, then tapers as pipe is tuberculated

Sliplining or Cured In-Place Pipe

26

PIPE CLEANING - JETTING

• Pre-cleaning inspection must be performed

• Based on results of this inspection, jetting pressures and angles, pace of jetting action, etc. can be established

27

PIPE CLEANING – PIGGING

• Must have adequate access

• Any fixed obstructions within the pipe prevent this type of cleaning

28

PIPE CLEANING - CHAINING

• Risk of damage to pipe

• Should only be used before sliplining

29

INSPECTION CASE HISTORY

30

NON-DESTRUCTIVE TESTING

• Varying Degrees of Accuracy and Application

• Methods available (from FEMA 484) Voids on outside of a conduit

Self-potential Resistivity Seismic tomography Ground penetrating radar

Pipe thickness Ultrasonic Magnetic Flux Broadband Electromagnetics

New Technologies Sensor passes through pipe to find potential leaks from pressurized pipes

31

REDUCING RISK OF FAILURE

32

REDUCING RISK OF FAILURE

33

EMBANKMENT RAISE/CONDUIT EXTENSION

34

RETROFIT CONDUITS WITH UPSTREAM CONTROL

35

CONSTRUCTION WITH FULL POOL?

36

CASE HISTORY

37

• Constructed 1879• Pressurized CIP, No Concrete Encasement, Corroded• Abandoned (Grouted) Conduit In-Place• Constructed New Siphon Intake Structure on Abutment

RECOMMENDATIONS

• Evaluate Each Dam Site Independently

• Plan and Coordinate with Entire Project Team Owner Engineer Regulators Contractors

• Balance Technical, Practical, and Regulatory Constraints

• Develop an Appropriate Investigation/Repair Plan

38

RISK INFORMED DECISION MAKING

• Can be Used to Prioritize Investigations and Repairs

• Refer to Procedures Developed by Various Federal Agencies

• Consider Factors that Contribute to Failure and their Consequences:

39

Conduit Type, Age, Encasement Wall Thickness and Section Loss

Defect Dimension Pipe Coating

Soil Gradation and Erodibility Soil Resistivity

Hydraulic Fracture pH of Reservoir

Seepage Gradient

QUESTIONS?

40

UNDER PRESSURE: AGING OUTLET CONDUITS

Jeremy Young, PE

Tyson Clouser, PE

Dam Safety 2013 –

ASDSO National Conference

Providence, Rhode Island

September 9, 2013

Recommended