The Story of the Bournedale Elementary School MSBA partnered with Bourne and design team=$13M savings

Bourne elementary and ecc timeline v2

Embed Size (px)

Citation preview

Page 1: Bourne elementary and ecc timeline v2

The Story of the Bournedale Elementary School

MSBA partnered with Bourne and design team=$13M savings

Page 2: Bourne elementary and ecc timeline v2

Pre-MSBA: Building Plan & Oversight of Design Development

at Local Level• Bourne wanted to replace the Hoxie School (100 years

old) & the Otis Memorial School (55 year old building located on Otis AFB)

• “Cape Villages” concept to reflect Cape Cod municipalities (Town of Barnstable=Hyannis, Osterville, Centerville, etc.)

• Single story “houses” connected by long hallways• Segregate Pre-K/K/Grades 1-5• Move 5th grade into new elementary, out of new middle

school• 946 kids: Make building larger than current enrollment

just in case of Otis AFB disposition• Siting: required a $4M MassHighway project for access

Page 3: Bourne elementary and ecc timeline v2

Bourne

Original Design: “Cape Villages” Concept

Page 4: Bourne elementary and ecc timeline v2

Bourne Elementary &ECC: 2003 Scope and Budget

• Expanded for full day K (not previously offered, half day K for past 40 years)

• Area: 135,000 sf

• Budget: $26,850,000

• Debt Exclusion passed for $26.8 M in 2003

Page 5: Bourne elementary and ecc timeline v2

Bourne

Original “Cape Villages” Concept

Page 6: Bourne elementary and ecc timeline v2

• Preliminary Estimate >>$30+ Million• District proposed change to MSBA Guidelines:

– Pre-K and K classroom sf = 1,100 (vs. 1,200 sf)– Classroom sf = 820 (vs. 900 sf)– Gym = 4,800 (vs. 6,000 sf)

• Area = 115,785 sf (down from 135,000 sf)• Maintained a smaller version of “Cape Villages”

concept• However, total cost (bids): $40.1 Million• 2nd override vote failed and bids were rejected

Revise the Dream: 2005 Cost Estimate

Page 7: Bourne elementary and ecc timeline v2

Bourne

Revised “Cape Villages” Concept

Page 8: Bourne elementary and ecc timeline v2

• Building reconfigured to traditional 2-story building with interior courtyard and double-loaded corridors

• pK – 4 (with ½ day K). Kept 5th grade in Middle School• Revised enrollment projections to 584 students (pk-4)• Area: 66,000 sf• Room and infrastructure for potential future expansion• Creative interior design maintains “village” concept• Estimate: $26.8 Million• Bids: $25.5 Million• Maintained master plan goal of replacing Hoxie and Otis

Memorial Schools

First plan fails at ballot box…2006 redesign

Page 9: Bourne elementary and ecc timeline v2

Bourne

Redesigned Building: 2-story building with interior courtyard

Potential Future Expansion

Potential Future Expansion

Page 10: Bourne elementary and ecc timeline v2

Bourne

Redesigned Building: Upper Level

Page 11: Bourne elementary and ecc timeline v2

Bourne

Redesigned Building: Traditional 2-story building with interior courtyard

Main Façade

Page 12: Bourne elementary and ecc timeline v2

Bourne

Redesigned Building: Gymnasium: colors and shapes delineate gym classroom groupings

Page 13: Bourne elementary and ecc timeline v2

Bourne

Redesigned Building: Cafetorium Entrance: Music Room is on Cafetorium Stage, separated by flexible wall

Page 14: Bourne elementary and ecc timeline v2

Bourne

Redesigned Building: Use of Color for Way-finding