N.C. Department of Transportation The Construction of I40/I77 Interchange August 9, 2012

The Construction of the I-40/I-77 Interchange August 9, 2012

Embed Size (px)

Citation preview

Page 1: The Construction of the I-40/I-77 Interchange August 9, 2012

N.C. Department of TransportationThe Construction of I40/I77 Interchange

August 9, 2012

Page 2: The Construction of the I-40/I-77 Interchange August 9, 2012

I-40/ I-77 Need for Project

Very Important Crossroad of North Carolina

Built and opened in Late 1960’s

Has outlived its service life

Current configuration does not meet todays design guidelines, i.e. weave distances, size of radiuses

Original Traffic Projections were 5000vpd, today the traffic on both interstates is about 70,000vpd, this is projected to be about 110,000vpd in 2035

Page 3: The Construction of the I-40/I-77 Interchange August 9, 2012

I-40/I-77 Interchange

Project to Be Built in Three Phases

A I-40/US 21 Interchange and work along I-40 with

Ramps from I77 NB to I40 WB and ramp from I-40

WB to collector Dist.

B The I-40/I77 Interchange Proper

C Peripheral ends of Interstates

Page 4: The Construction of the I-40/I-77 Interchange August 9, 2012

I-40/I-77 Interchange

Time Lines

I-3819A Let to contract June 19 2012

I-3819B Let to contract March 2016

I-3819C Post Year

R/W is being secured for entire corridor at this time

Page 5: The Construction of the I-40/I-77 Interchange August 9, 2012

What is being Built

I-40

Widen to six lanes from NC 115 to Old Mocksville Rd with collector distributors at 21 (EB and WB)

I-77

Widen to six lanes from South of Broad St. to Jane Sowers

Construct Multi Level Interchange of the two

Interstates

I-40/I-77 Interchange

Page 6: The Construction of the I-40/I-77 Interchange August 9, 2012

I-40/I-77 Interchange

What is being Built

US 21

Reconstruct from just north of Glenway Dr. to BB&T south of the interstate with a Double Diverging Interchange at I-40

Broad Steet

Widen from just past Lower Mall Entrance to just

past Cynthia Street

New Bridge at Radio Rd and Davie Ave.

Page 7: The Construction of the I-40/I-77 Interchange August 9, 2012

I-40/I-77 Interchange

New Bridge at Radio Rd.

New Bridge Davie Ave.

Broad Street Bridge will be reconstructed

Existing Interchange at Old US 64 will be closed

I-40/Old Mocksville Rd will be upgraded

Page 8: The Construction of the I-40/I-77 Interchange August 9, 2012

I-40/I-77 Interchange

How Much will it cost?

Construction of entire project will cost approx.

$251,000,000.00

Page 9: The Construction of the I-40/I-77 Interchange August 9, 2012

I-40/I-77 Interchange

Final Configuration of Interchange

Final Configuration of Interchange

N

Page 10: The Construction of the I-40/I-77 Interchange August 9, 2012

I-3819 AWhat is being Constructed

I-40 WB Collector Distributor

I-40 WB complete to final configuration (Minus one lane)

Reconstruct Radio Rd Bridge

New Bridge over US 21 and 4th Creek

DDI Interchange at I-40 and US 21

I 77 NB ramp to I 40 WB

I 40 WB to I 77 NB and to Collector Dist.

Reconnection to Gaither Rd.

Noise Walls and Retaining Walls

Page 11: The Construction of the I-40/I-77 Interchange August 9, 2012

I-40 at Old Movie Theater

N

Page 12: The Construction of the I-40/I-77 Interchange August 9, 2012

I-40/I-77 Initial Interchange

N

Page 13: The Construction of the I-40/I-77 Interchange August 9, 2012

I3819 A

Time Line and Cost

Construction to begin August 2012

Project Completion Date March 2017

Cost approximately $90 million

Bridges being built to accommodate future projects

Page 14: The Construction of the I-40/I-77 Interchange August 9, 2012

I-3819A… US 21 DDI

What is DDI1.DDI is Double Diverging Interchange

2.Will require traffic to cross over onto opposite side

3.Eliminated the need for conflicting left turn movements…thus eliminating conflicts and congestion

4.Will allow US 21 to flow freely

5.Median Island will prevent left turns out

Page 15: The Construction of the I-40/I-77 Interchange August 9, 2012
Page 16: The Construction of the I-40/I-77 Interchange August 9, 2012

US 21

Reconstruct US 21 to 4 lanes with a median island

Sidewalks will be constructed on both sides

Median Island from 4th Creek Bridge south thru DDI to the south end of construction, this will prevent left turns

Full access will be allowed at Carolina Ave. via a signal

Page 17: The Construction of the I-40/I-77 Interchange August 9, 2012

Gaither Rd

The two way traffic on the existing interstate ramp will be closed off

Gaither will access US 21 via a new Rd from just beside the Furniture Store and will intersect US 21 at a Signal at Glenway Dr, between Chili’s and Wendy’s.

Page 18: The Construction of the I-40/I-77 Interchange August 9, 2012

US 21 Gaither Rd Connection

Page 19: The Construction of the I-40/I-77 Interchange August 9, 2012

Noise and Retaining Walls

Both Noise and Retaining Walls will be built:

Retaining Walls will be a combination of MSEs (Segmental Precast Units) and Soil Nails with a shotcreate facades.

Noise walls will be precast modules with concrete piles, the facade will be a simulated stone masonry pattern on both sides.

Page 20: The Construction of the I-40/I-77 Interchange August 9, 2012

Noise WallsNoise Wall Locations:

I-40 Westbound

Begins directly across from Western Ave. Baptist Church

(just west of Radio Rd Bridge) and runs to where

Museum Rd. moves away from I-40

I-40 Eastbound

Begins at east side of Radio Rd and continues

down interstate and down ramp at US 21 to

behind the Highway Patrol Station.

Page 21: The Construction of the I-40/I-77 Interchange August 9, 2012

Noise Walls

I-77 Southbound

Begins just south of Davie Ave and runs southward and up ramp to Broad St.

Begins again at the Creek just south of Broad St and runs southward to behind the Catholic Church

Page 22: The Construction of the I-40/I-77 Interchange August 9, 2012

I-40/I-77 Interchange

NCDOT will do significant Public Relations as the project nears and during the life of the project

The project will have its own dedicated Website where up to date information will be posted

Page 23: The Construction of the I-40/I-77 Interchange August 9, 2012

Contact Info

Contractor

Zachary Construction Corp. www.zachryconstructioncorp.com

12625 Wetmore Road, Suite 301

San Antonio, Texas 78347

(210) 871-2700

Page 24: The Construction of the I-40/I-77 Interchange August 9, 2012

Contact Info

NCDOT

John Cook, Resident Engineer

124 Prison Camp Road

Statesville, NC 28625Email: [email protected]

Phone: (704) 876-3543

Page 25: The Construction of the I-40/I-77 Interchange August 9, 2012

Questions?

Feel Free to contact any of the NCDOT Personnel in attendance tonight.