Upload
nasapmc
View
13.144
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Citation preview
Panel ChairKathleen Symons, Associate Director, CxP PP&C, NASA JSC
Panel MembersTom Coonce, Director, Cost Analysis Division, NASA HQJames Ortiz, Director, Independent Program Assessment Office (IPAO), NASA HQMark Saunders, Consultant, Dell Services (Retired NASA)
PM Challenge 2011 Panel: Getting Successfully Through Implementation KDP C
PM Challenge 2011: Informational Briefing Pre-Decisional 1
Panel Overview: Getting Successfully through Implementation KDP C
• KDP C is the “moment of truth” when the Agency decides whether a project will move forward to implementation, and makes cost and schedule commitments to its external stakeholders
• This panel will address updated Agency processes incorporated in NPR 7120.5E that are designed to more effectively ensure that a project is on track to accomplish its technical mission within its cost and schedule estimate at KDP C, and will discuss how these processes work together to help the Project Manager– Project development of the Integrated Technical, Cost, Schedule and Risk
Baseline for KDP C– Definition of Expected Maturity States to guide development and assessment
of the integrated baseline– Utilization of the JCL at KDP C to provide evidence of an executable,
integrated baseline– Independent SRB Checks and Balances– Utilization of the Decision Memorandum to document the approved
integrated baseline, formalize management approval and agreement to support the project, and establish external commitments
2PM Challenge 2011: Informational Briefing Pre-Decisional
Getting Successfully through KDP C
KDP B KDP CApproval for
Implementation
PDR
≤30 days
An integration of Project Baseline Development, Independent Checks and Balances, Approval to Proceed, and
Commitments
Prog
ram
mati
c Re
view
s Ap
prov
al &
Com
mitm
ent
3PM Challenge 2011: Informational Briefing Pre-Decisional
Development of the Integrated Technical, Cost, Schedule and Risk Baseline for KDP C
KDP B KDP CApproval for
Implementation
PDR
≤30 days
KDP B•System design•Risks and constraints
• Estimated cost (range)• Estimated schedule
(range)• Phased funding
requirements
Project Develops Integrated Baseline
KDP C•Preliminary design•Updated risks and constraints•Estimated cost and schedule•Phased funding requirements•Unallocated Future Expenses
Review Element Categories• Budget & Schedule• Resources other than Budget• Risk Management
• Agency Strategic Goals , Outcomes• Management Approach• Technical Approach PD
R Ex
pect
ed
Mat
urity
SDR
Expe
cted
M
atur
ity
Proj
ect P
rodu
cts
Prog
ram
mati
c Re
view
s Ap
prov
al &
Com
mitm
ent
Expe
cted
Mat
urity
Sta
te
4PM Challenge 2011: Informational Briefing Pre-Decisional
JCL Provides Evidence of Executable, Integrated Baseline
KDP B KDP CApproval for
Implementation
PDR
≤30 days
Review Element CategoriesPD
R Ex
pect
ed
Mat
urity
SDR
Expe
cted
M
atur
ity
Prog
ram
mati
c Re
view
s A
ppro
val &
Com
mitm
ent
Expe
cted
Mat
urity
Sta
te
• Budget & Schedule• Resources other than Budget• Risk Management
• Agency Strategic Goals , Outcomes• Management Approach• Technical Approach
Project Develops Integrated Baseline
KDP C•Preliminary design•Updated risks and constraints•Estimated cost and schedule•Phased funding requirements•Unallocated future expenses
JCL
Proj
ect P
rodu
cts
KDP B•System design•Risks and constraints
• Estimated cost (range)• Estimated schedule
(range)• Phased funding
requirements
5PM Challenge 2011: Informational Briefing Pre-Decisional
SRB Assesses Integrated Baseline and JCL
KDP B KDP CApproval for
Implementation
PDR
≤30 days30-90 days
Readiness Assessment
Project Develops Integrated Baseline
KDP C•Preliminary design•Updated risks and constraints•Estimated cost and schedule•Phased funding requirements•Unallocated future expenses
JCL
Inde
pend
ent
Chec
ks &
Bal
ance
s
Review Element CategoriesPD
R Ex
pect
ed
Mat
urity
SDR
Expe
cted
M
atur
ity
Proj
ect P
rodu
cts
Prog
ram
mati
c Re
view
s A
ppro
val &
Com
mitm
ent
Expe
cted
Mat
urity
Sta
te
• Budget & Schedule• Resources other than Budget• Risk Management
• Agency Strategic Goals , Outcomes• Management Approach• Technical Approach
SRB Analyses, Assessments and Reports
KDP B•System design•Risks and constraints
• Estimated cost (range)• Estimated schedule
(range)• Phased funding
requirements
6PM Challenge 2011: Informational Briefing Pre-Decisional
Agency Commits to Project’s Integrated Baseline
Project Develops Integrated Baseline
KDP C•Preliminary design•Updated risks and constraints•Estimated cost and schedule•Phased funding requirements•Unallocated future expenses
JCLProject
Response
KDP B
KDP CPDR
≤30 days30-90 days
Readiness AssessmentABC
External Stakeholders
SRB Analyses, Assessments and Reports
Review Element CategoriesPD
R Ex
pect
ed
Mat
urity
SDR
Expe
cted
M
atur
ity
Inde
pend
ent
Chec
ks &
Bal
ance
s
Decision Memorandum
Management Agreement
Agency Baseline
Commitment (ABC)
Proj
ect P
rodu
cts
Prog
ram
mati
c Re
view
s A
ppro
val &
Com
mitm
ent
Expe
cted
Mat
urity
Sta
te
• Budget & Schedule• Resources other than Budget• Risk Management
• Agency Strategic Goals , Outcomes• Management Approach• Technical Approach
KDP B•System design•Risks and constraints
• Estimated cost (range)• Estimated schedule
(range)• Phased funding
requirements
7PM Challenge 2011: Informational Briefing Pre-Decisional
Backup
8PM Challenge 2011: Informational Briefing Pre-Decisional
One Step PDR Life Cycle Review (NPR 7120.5E)
KDP-C KDP-C
PDR Readiness Assessment PDR-LCR
Technical Baseline with C/S/R and Integrated Assessment of Technical and Programmatic
Baseline
KDP-B KDP-B
Periodic SRB Involvement as Appropriate
P/pBrief
CenterBrief
MDBrief
Not To Scale
(30 Days)
Snapshot Report
(30- 90 days)
-Required prior to LCR-Report to DA for life cycle reviews preceding KDP B&C and during any major replan or rebaseline (3)
Programmatic Data Drops to SRB (includes JCL Model)
(2)
FOOTNOTES:1. A One Step Review may be used for any LCR2. The SRB Handbook provides information on the readiness
assessment, quick-look reports and checkpoints associated with life cycle reviews
3. For all other life cycle reviews report to DA if significant unresolvable disagreements
(2)
CheckPoint if needed.(2)
9PM Challenge 2011: Informational Briefing Pre-Decisional
Two Step PDR Life Cycle Review (NPR 7120.5E)
Resolve Tech Issues/Risks, Update
Cost/Schedule Baseline
Independent Integrated PDR Assessment
PDR Readiness Assessment PDR
-Required prior to LCR-Report to DA for life cycle reviews preceding KDP B&C and during any major replan or rebaseline (3)
Technical Baseline with Cost,
Schedule, and Risk Information
Integrated Assessment of Technical and Programmatic
Baseline
KDP-B KDP-B
Periodic SRB Involvement as Appropriate
P/pBrief
CenterBrief
MDBrief
Not To Scale
(1-6 months) (30 Days)
Snapshot Report
(30-90 days)
PDR LCRKDP-C KDP-C
Snapshot Report
Programmatic Data Drops to SRB (includes JCL Model)
(2)
(2)(2)
FOOTNOTES:1. A Two Step Review may be used for any LCR2. The SRB Handbook provides information on the readiness
assessment, quick-look reports and checkpoints associated with life cycle reviews
3. For all other life cycle reviews report to DA if significant unresolvable disagreements
CheckPoint if needed.(2)
10PM Challenge 2011: Informational Briefing Pre-Decisional
Expected Maturity State through the Project Life Cycle Leading to KDP B (NPR 7120.5E)
11PM Challenge 2011: Informational Briefing Pre-Decisional
Expected Maturity StateExploded View (NPR 7120.5E)
12PM Challenge 2011: Informational Briefing Pre-Decisional
Expected Maturity State through the Project Life Cycle Leading to KDP C (NPR 7120.5E)
KDP ReviewAssociated
Lifecycle Review
LCR Objectives
Expected Maturity State by Review ElementOveralll Expected Maturity State @
Next KDPAgency Strategic
Goals & Outcomes
Management Approach
Technical Approach
Budget and Schedule
Resources Other than Budget
Risk Management
KDP A MCR SRR
KDP B MDR SDR
KDP C PDR
To evaluate the completeness/consistency of the planning, technical & cost/schedule baselines developed during formulation; to assess compliance of the preliminary design with applicable requirements; to determine if the project is sufficiently mature to begin Phase C.
Project requirements and preliminary designs satisfy program requirements and constraints, mission needs and mission success criteria.
Project Plan is complete; external agreements and infrastructure business case are in place; and execution plans for the remaining phases are appropriate.
The preliminary design satisfactorily meets requirements and constraints with acceptable risk.
The integrated cost/schedule baseline has a sound basis and is consistent with driving assumptions; reflects risks; is fully supported by a documented BOE; fits within the available funding and schedule profile; and cost/schedule management tools/processes are in place.
Adequate agreements exist for staffing, essential infrastructure and additional resources, as appropriate, for remaining lifecycle phases.
Mission, development and safety risks are addressed in designs and operating concepts, a process and resources exist to effectively manage or mitigate them.
Overall KDP C Expected Maturity:
Preliminary design and
programmatic plans enable
Agency Baseline Commitment.
13PM Challenge 2011: Informational Briefing Pre-Decisional
Project – Simplified Cost Agreements at KDP C (NPR 7120.5E)
Agency Baseline Commitment• External Commitments
This UFE is managed above the Project.
Management Agreement • Managed by Project Manager
UFE
Not to scale.
At KDP C and subsequent ABC rebaselines the ABC and the life cycle cost estimate are equal.
14PM Challenge 2011: Informational Briefing Pre-Decisional
Project Life Cycle Cost Agreements and Commitments (NPR 7120.5E)
Management Agreements
LCC RangeUFE managed
above the project
Notional and Not to Scale
During ImplementationDuring Formulation KDP C
UFEActual Formulation
Costs
UFE managed by Project
Authorized Formulation
Cost
Life cycle cost estimate
At KDP C and subsequent Agency Baseline Commitment rebaselines the ABC and the life cycle cost estimate are equal
High Estimate
Low Estimate
15PM Challenge 2011: Informational Briefing Pre-Decisional
Figure 2-3a The NASA Program Life Cycle (Uncoupled and Loosely Coupled) (NPR 7120.5E)
ACRONYMSASP—Acquisition Strategy Planning meetingASM—Acquisition Strategy MeetingFAD—Formulation Authorization DocumentKDP—Key Decision PointPCA—Program Commitment AgreementPIR—Program Implementation Review P/SDR—Program/System Definition ReviewP/SRR—Program/System Requirements ReviewSRB—Standing Review Board
Changes from original shown in red
NASA Life Cycle Phases
Approval for Implementation FORMULATION IMPLEMENTATION
KDP IIProgram Life Cycle Gates
KDP n
SRR
Program Life Cycle Reviews5&6
FAD
KDP 03
PCA1
Program Plan1
SDR
Start Project2
1, 2, 3, … Project m, m+1Project Starts
ProgramUpdates
Updated Program Plan
Updated PCA Start process again4
KDP I KDP III
PIR
PIRs are conducted as required by Decision Authority
FOOTNOTES1. Program Plans are baselined at SDR, and PCAs are baselined at KDP I. These are reviewed and
updated, as required, to ensure program content, cost, and budget remain consistent.
2. Projects, in some instances, may be approved for formulation prior to KDP I. Initial project pre-formulation generally occurs during program Formulation.
3. KDP 0 may be required by the Decision Authority to ensure major issues are understood and resolved prior to formal program approval at KDP I.
4. When programs evolve and/or require upgrades (e.g., new program capabilities), the life-cycle process will be restarted when warranted, i.e., the program’s upgrade will go through formulation and implementation steps.
5. Single-project programs will follow the Project lifecycle, but will include draft/ final PCAs at KDPs B & C respectively and draft/final Program Plans at SRR & SDR respectively.
6. Life Cycle Review (LCR) objectives and expected maturity states for these reviews and the attendant KDPs are contained in Table 2-6a.
ASMASPAgency Reviews
Approval forFormulation
16PM Challenge 2011: Informational Briefing Pre-Decisional
Figure 2-3b The NASA Program Life Cycle (Tightly Coupled) (NPR 7120.5E)
NASA Life Cycle Phases
Approval for Implementation FORMULATION IMPLEMENTATION
KDP IProgram Life Cycle Gates
KDP IV KDP III
Program Life Cycle Reviews 3&7
FADDraft PCA
Draft Program
Plan Start Project2
1, 2, 3, … Project m, m+1Project Starts
ProgramUpdates
Updated Program Plan
Updated PCA Start process again6
KDP 05 KDP II
ASMASPAgency Reviews
SRR SDR FRR/MRB9 CDR SIR CERR PLARORR PIR4 DR
PCA1
Program Plan1
PDR
Project reviews/KDPs accompany Program reviews/KDPs4
PDR—Preliminary Design ReviewPFAR—Post-Flight Assessment ReviewPIR—Program Implementation Review PLAR—Post-Launch Assessment ReviewP/SDR—Program/System Definition ReviewP/SRR—Program/System Requirements ReviewSAR—System Acceptance ReviewSIR—System Integration ReviewSRB—Standing Review BoardSMSR—Safety and Mission Success Review
Update Program documentation and re-conduct lifecycle reviews with new capabilities6
LRR,SMSROther Reviews
PFAR
SAR8
KDP n
Approval forFormulation
Changes from original shown in red
7. Life Cycle Review (LCR) objectives and expected maturity states for these reviews and the attendant KDPs are contained in Table 2-6b.
8. SAR only applies to Human Space Flight.9. The KDP E decision is made at the FRR for Human Space Flight and the MRB for Robotic Space Flight. The
FRR/MRB are part of a series of events shown in Appendix K leading to approval to launch.
ACRONYMSASP—Acquisition Strategy Planning meetingASM—Acquisition Strategy MeetingCDR—Critical Design ReviewCERR—Critical Events Readiness ReviewDR—Decommissioning ReviewFAD—Formulation Authorization DocumentFRR—Flight Readiness ReviewKDP—Key Decision PointLRR—Launch Readiness ReviewORR—Operational Readiness ReviewPCA—Program Commitment Agreement
FOOTNOTES1. Program Plans are baselined at SDR, and PCAs are baselined at KDP I. These are reviewed and
updated, as required, to ensure program content, cost, and budget remain consistent.
2. Projects are usually approved for formulation prior to KDP I.
3. Single-project programs will follow the Project lifecycle, but will include draft/ final PCAs at KDPs B & C respectively and draft/final Program Plans at SRR & SDR respectively.
4. Tightly-coupled program reviews generally differ from other program types because they are conducted to ensure the overall integration of all program elements (i.e., projects). Once in operations, PIRs are conducted as required by the Decision Authority.
5. KDP 0 may be required by the Decision Authority to ensure major issues are understood and resolved prior to formal program approval at KDP I.
6. When programs evolve and/or require upgrades (e.g., new program capabilities), the life-cycle process will be restarted when warranted, i.e., the program’s upgrade will go through formulation and implementation steps.
17PM Challenge 2011: Informational Briefing Pre-Decisional
Figure 2-4 Project Life Cycle (NPR 7120.5E)
Project Pre - Phase A: Phase A: Phase B: Phase C:
KDP CProject
-
Phase E:
KDP A
Phase D:
KDP B
Phase F:
KDP F
SMSR, LRR (LV), FRR (LV)
KDP E
Peer Reviews, Sub - system PDRs, Sub - system CDRs, and System Reviews
DRPLARMDR 4
Robotic Mission Project Reviews 1
MCR SRR PDR CERR 3SIR FRRLaunch Readiness Reviews
SDR CDR / PRR 2
PDRMCR FRRSRR SIR CERR 3PLARSAR
Re - flights
DR(NAR )(PNAR )
Supporting Reviews
ORRInspections and Refurbishment
Re-enters appropriate life cycle phase if modifications are needed between flights
End of Flight
PFAR
ASP
ORR
ASM
ASM (NAR )(PNAR )
CDR / PRR 2
NASA Life Cycle Phases
ProjectLife Cycle Phases
Pre-Phase A:Concept Studies
Phase A:Concept & Technology
Development
Phase B:Preliminary Design &
Technology Completion
Phase C:Final Design & Fabrication
Approval for Implementation FORMULATION IMPLEMENTATION
KDP CProject Life Cycle Gates & Major Events
Phase E:Operations & Sustainment
KDP A
Launch
KDP D
Phase D:System Assembly, Int & Test, Launch & Checkout
KDP B
Phase F:Closeout
End of MissionFinal Archival
of Data
KDP F
SMSR, LRR (LV), FRR (LV)
KDP E7
Peer Reviews, Sub - system PDRs, Sub - system CDRs, and System Reviews
DRPLARMDR 4MCR SRR PDR CERR 3SIR MRB7
FADDraft Project Requirements
Other Reviews
SDR CDR / PRR 2
PDRMCR FRR7SRR SIR CERR 3PLAR
SAR8
-Re flights
DR
Supporting Reviews
ORRInspections and Refurbishment
Re-enters appropriate life cycle phase if modifications are needed between flights
End of Flight
PFAR
Preliminary Project Plan
Baseline Project
Plan
ASP
ORR
ASM
CDR / PRR 2
Agency Reviews
Human Space Flight Project Life Cycle Reviews 1,5&6
Robotic Mission Project Life Cycle Reviews 1,5&6
FOOTNOTES1. Flexibility is allowed to the timing, number and content of reviews as long as the equivalent information
is provided at each KDP and the approach is fully documented in the Project Plan.2. PRR needed for multiple system copies. Timing is notional.3. CERRs are established at the discretion of Program Offices.4. For robotic missions the SRR and the MDR may be combined.5. Single-project programs will follow the Project lifecycle, but will include draft/ final PCAs at KDPs B & C
respectively and draft/final Program Plans at SRR & SDR respectively.6. Life Cycle Review (LCR) objectives and expected maturity states for these reviews and the attendant
KDPs are contained in Table 2-7.7. The KDP E decision is made at the FRR for Human Space Flight and the MRB for Robotic Space Flight.
The FRR/MRB are part of a series of events shown in Appendix K leading to approval to launch.8. SAR only applies to Human Space Flight.
Approval forFormulation
DRR
DRR
ACRONYMSASP - Acquisition Strategy Planning MeetingASM - Acquisition Strategy MeetingCDR - Critical Design ReviewCERR - Critical Events Readiness ReviewDR - Decommissioning ReviewDRR - Disposal Readiness ReviewFAD - Formulation Authorization DocumentFRR - Flight Readiness ReviewKDP - Key Decision PointLRR - Launch Readiness ReviewMCR - Mission Concept ReviewMDR - Mission Definition ReviewMRB - Mission Readiness Briefing
ORR - Operational Readiness ReviewPDR - Preliminary Design ReviewPFAR - Post-Flight Assessment ReviewPLAR - Post-Launch Assessment ReviewPRR - Production Readiness ReviewSAR - System Acceptance ReviewSDR - System Definition ReviewSIR - System Integration ReviewSMSR - Safety and Mission Success ReviewSRR - System Requirements Review
18PM Challenge 2011: Informational Briefing Pre-Decisional