42
Page 1 Program and Project Management Policy Development Overview and Rationale Sandra Smalley Office of the Chief Engineer Used with permission

Sandra smalley

  • Upload
    nasapmc

  • View
    13.633

  • Download
    4

Embed Size (px)

Citation preview

Page 1: Sandra smalley

Page 1

Program and Project Management

Policy Development

Overview and Rationale

Sandra Smalley

Office of the Chief Engineer

Used with permission

Page 2: Sandra smalley

Page 2

Objectives of Session

Provide: • A high-level overview of recent policy

developments• An understanding of the purpose of

the selected developments• A preview of some upcoming policy

developments

Page 3: Sandra smalley

Page 3

Recent Policy Developments

Overview

Pre-

Page 4: Sandra smalley

Page 4

Policy Developments2007

• NPR 7120.5 D - NASA Space Flight Program and Project Management Requirements

“This revision of NPR 7120.5 is part of a realignment of governing documents within NASA designed to increase accountability and general clarity in the flow-down of management process requirements.”

• NPR 7123.1A - NASA Systems Engineering Processes and Requirements

Page 5: Sandra smalley

Page 5

Policy Developments2008

• NPD 1000.0A - Governance and Strategic Management

• NPR 7120.7 - NASA Information Technology and Institutional Infrastructure Program and Project Management Requirements

• NPR 7120.8 - NASA Research and Technology Program and Project Management Requirements

• NPR 8000.4 - Agency Risk Management Procedural Requirements

Page 6: Sandra smalley

Page 6

Policy Developments2009

• NPD 1000.5 - Policy for NASA Acquisition

• NPR 7120.5D - NID

• NPD 7120.4 - Program/Project Management

Page 7: Sandra smalley

Page 7

Policy DevelopmentOther Supporting Work

Handbook development • The SRB Handbook • The Risk Management Handbook • NPR 7120.5 Handbook • WBS Handbook • Cost Estimating Handbook • Schedule Management Handbook

Page 8: Sandra smalley

Page 8

Policy Development Why all the activity?

• Improve program/project performance against external commitments (real and perceived)

• More effectively support programs and projects by improving and tailoring policy, processes, and requirements– Recognize the multi-center environment in many

programs and projects. This includes giving more attention to common principles, terminology, and practices while recognizing the differences that exist in Center processes and historic practices.

Page 9: Sandra smalley

Page 9

Improving Agency PerformanceApproach

• Employ a sound approach to Acquisition – NPD 1000.5

• Ensure early and continuing alignment of program project planning and budget process– Strategic planning meetings – NPR 7120.5D NID

– PPBE process with annual portfolio review

• Establish the proper set of requirements

• Establish a life cycle process that keeps the program/project on track

Page 10: Sandra smalley

Page 10

Selected Policy Developments

• Acquisition• Establishing the proper set of requirements• Space Flight and IT

Baseline PolicyJoint Confidence Level (JCL) Policy

• Preview of NPR 7120.5 Rev E

Page 11: Sandra smalley

Page 11

Selected Policy DevelopmentsAcquisition – Definition (NPD 1000.5)

Acquisition is the process for obtaining the systems, service, construction, and supplies the Agency needs to fulfill its mission.

Acquisition, which may include procurement (contracting for products and services), beginswith an idea or proposal that aligns with the NASA Strategic Plan and fulfills an identified need and ends with the completion of the program or project or the final disposition of the product or service.

Page 12: Sandra smalley

Page 12

Selected Acquisition Policy (NPD 1000.5)

• Meet programmatic, institutional, technical, cost, and schedule commitments

• Base acquisition on realistic cost estimates and achievable schedules

• For space flight and IT, Agency commitments are to be based on the budgeted cost and schedule associated with the confidence level approved by the decision authority.

• Programs and projects are to be annually reviewed by the responsible Mission Directorate or Mission Support Office to confirm to the decision authority that their current baseline life cycle cost estimates, funding strategy, and the annual NASA budget submissions are consistent.

Page 13: Sandra smalley

Page 13

Selected Policy Developments

• Acquisition• Establishing the proper set of requirements• Space Flight and IT

Baseline PolicyJoint Confidence Level (JCL) Policy

• Preview of NPR 7120.5 Rev E

Page 14: Sandra smalley

Page 14

Establishing the proper set of requirements

• Good requirements that are properly managed are essential to any successful undertaking.

• 7120 Series NPRs focus programmanagement requirements on specific product lines.

• Tailoring Principles provide a means to adjust prescribed requirements to a specific task (e.g., a program/project).

Page 15: Sandra smalley

Page 15

Tailoring - Definition

Tailoring - the process used to adjust or seek relief from a prescribed requirement to accommodate the needs of a specific task or activity (e.g., program/project)

The Tailoring process results in the generation of Deviations and Waivers depending on the timing of the request.

Page 16: Sandra smalley

Page 16

Tailoring Principles

• The organization at the level that established the requirement approves the request for tailoring of that requirement unless this authority has been formally delegated elsewhere.

• The involved management at the next higher level is informed in a timely manner of the request for tailoring of a prescribed requirement.

Page 17: Sandra smalley

Page 17

Policy Selected Developments

• Acquisition• Establishing the proper set of requirements• Space Flight and IT

Baseline PolicyJoint Confidence Level (JCL) Policy

• Preview of NPR 7120.5 Rev E

Page 18: Sandra smalley

Page 18

Space Flight and IT – Baseline and JCL

• SMC baseline and JCL policy discussions date back several years.

• The concept and details continue to evolve.

• A number of changes and implementation details are being considered for NPR 7120.5 Rev. E.

Perspective

Page 19: Sandra smalley

Page 19

Baseline PolicyGoal

Improve the cost and schedule performance of programs and projects by improved planning based on the integration of cost, schedule, and risk

Page 20: Sandra smalley

Page 20

Joint Cost and Schedule Confidence LevelDefinition (Simplified)

The probability that cost will be equal to or less than the targeted cost and theschedule will be equal to or less than the targeted schedule date.

Page 21: Sandra smalley

Page 21

Joint Bivariate Cumulative Probability Distribution of Cost and

Schedule

21Cost (x) ($M)

Schedule (y) (Months)

Probability

Page 22: Sandra smalley

Page 22

Current Policy

• Policy applies to Space Flight and IT programs and projects in implementation.

• Programs/projects are to be baselined or rebaselined based on a joint cost and schedule probabilistic analysis.

• Programs - Baselined or rebaselined at a confidence level of 70 percent or the level approved by the decision authority

• Projects are to be baselined or rebaselined at a confidence level consistent with the program's JCL.

• Projects - As a minimum, funded at a level that is equivalent to a confidence level of 50 percent or as approved by the decision authority

Page 23: Sandra smalley

Page 23

Current Policy (Cont.)

• Programs in extended operations generally are not required to develop a JCL, but new or upgraded capabilities while in ops will require a JCL.

• Program and project proposed cost and schedule baselines will be assessed by an independent review team.

• External commitments will be based on the JCL approved by the decision authority.

Page 24: Sandra smalley

Page 24

Baseline Policy

• Commitment Baseline – Basis for commitments to OMB and Congress

• Management Baseline – Basis for program/project execution and strategic management process reporting

Page 25: Sandra smalley

Page 25

Commitment BaselineKey Attributes

• It is an integrated set of project requirements, cost, schedule, technical content, and agreed to JCL that forms the basis for NASA’s commitment to OMB and Congress.

• It is established at the Key Decision Point (KDP) that initiates the Implementation Phase.

• The Commitment Baseline is the only officialNASA baseline for a project.

Page 26: Sandra smalley

Page 26

Unallocated Future Expenses (UFEs)Needed to understand Management Baseline

Unallocated Future Expenses -The portion of estimated cost required to meet specified JCL that cannot yet be allocated to the specific project WBS sub-elements because the estimate includes probabilistic risks and specific needs that are not known until these risks are realized.

Page 27: Sandra smalley

Page 27

Unallocated Future Expenses (UFEs) (Cont.)

• The term ‘UFE’ was established to make it clear that (based on experience) these funds are expected to be required to complete the projectbut cannot yet be allocated to a specific WBS activity.

(The UFE concept is consistent with the non-deterministic nature of joint cost and schedule estimates based on probabilistic analysis.)

• All UFE are included in the commitment baseline and the project’s budget.NOTE – The relationship of UFE to Commitment and Management Baselines is illustrated in an upcoming slide.

Page 28: Sandra smalley

Page 28

Management Baseline - Key Attributes

• An integrated baseline (set of requirements, cost, schedule, technical content, and associated JCL) that forms the foundation for program/project execution

• The Management Baseline is established at the Key Decision Point (KDP) that initiates the Implementation Phase as approved by the decision authority.

Page 29: Sandra smalley

Page 29

Management Baseline Key Attributes (cont.)

• The program Management Baseline is the aggregate of the project Commitment Baselines plus program operating expenses.

Similarly, the project Management Baselineequals the Commitment Baseline less any portion of UFE not released to the project for project execution.

Page 30: Sandra smalley

Page 30

Project Management Baseline(Project Execution)

Project Commitment Baseline(External commitments)

This UFE is controlled by the Program/MD

ProjectManager Control

UFE

Not to scale.

Relationship of UFE to ProjectCommitment and Management Baselines

Page 31: Sandra smalley

Page 31

Project -1 Project -2 Program

ProgramOperatingExpense

Project Management Baseline

UFE Held by Program

Program Management Baseline

Program and Project BaselinesTotal Baseline Cost

Project -2

UFE Held by Project 1

UFE Held by Project 2

UFE Held by Project 1

UFE Held by Project 2

Project -1

Project Commitment Baseline

Page 32: Sandra smalley

Page 32

Selected Policy Developments

• Acquisition• Establishing the proper set of requirements• Space Flight and IT

Baseline PolicyJoint Confidence Level (JCL) Policy

• Preview of NPR 7120.5 Rev E

The Rev E development is in its early stages.This preview should be viewed as both notional and pre-decisional.

Page 33: Sandra smalley

Page 33

Rev. E Development Charter

• Build on the NID• Issue Rev. E before the expiration of the NID• Fully vet and resolve policy issues raised but not

resolved during the NID development• Incorporate:

– Any additional changes in NASA policy and practice,

– Findings from OCE survey process and other audits

– Lessons learned

Page 34: Sandra smalley

Page 34

Rev. E Development Charter (Cont.)

• Ensure proper flow down from NPD1000.0A, and NPD 1000.5

• Address inconsistencies among fundamental OCE documents. The primary focus will be on NPR 7120.5, NPD 7120.4, NPD 1000.5, and NPR 7123.1A.

Page 35: Sandra smalley

Page 35

Rev. E Development Working Groups

• Life Cycle Review• Baseline Policy• JCL Clarify • Highly Specialized IT - Cover from PM’s perspective• NPR 7123 – NPR 7120.5 – Inconsistencies and review

criteria• Requirements Relief – e.g., Batch processing• Ops and Program and Project Reviews – Streamline

reviews• OSMA Issues – Misc.

Page 36: Sandra smalley

Page 36

Rev. E Development Life Cycle Review

KDP B to KDP CPhase B

(Preliminary Design and Technology Completion)

Page 37: Sandra smalley

Page 37

Current Project Life CycleArea of Focus - KDP B to KDP C

Page 38: Sandra smalley

Page 38

KDP B to KDP COverview

Conduct IBRsand update JCL

ILCR

KDP C

PDR Readiness Assessment

PDR

Phase A Phase B

Checkpoint to DA(If a significant

change occurs or the interval from the ILCR

exceeds 6 months )

Prerequisite for locking down the date of the PDR

and ILCR

Technical baseline with

cost, schedule, and risk

information

Integrated review of programmatic

baselines integrated with technical

baseline updates

Implementation

KDP B

Formulation

Periodic SRB Involvement as Appropriate

P/pBrief

CenterBrief

MDBrief

Not To Scale

Phase C

This preview should be viewed as both notional and pre-decisional.

Post Review Reporting to DA

PDR-Based

Page 39: Sandra smalley

Page 39

Single Project and Tightly Coupled Programs

ILCR

KDP IIAssessment of

plan to take projects to KDP C

PDR

Program

Implementation

KDP 1

Post Review Reporting to DA

Not To Scale

Start of projects

Projects

PDR ILCR

ILCRPDR

ILCRPDR

Readiness assessment

Readiness assessment

Readiness assessment

Post Review Reporting to DA

Checkpoint if significant changeor 6 months

KDP C

Assessments and Checkpoints

This preview should be viewed as both notional and pre-decisional.

Page 40: Sandra smalley

Page 40

Rev. E DevelopmentSchedule

First Rev E development meeting – 10/09

NID Expiration – 9/10

Page 41: Sandra smalley

Page 41

Concluding Remarks

• The intent of policy developments is to improveAgency performance.

• If you view that the resulting processes do not add value … don’t just tolerate it… or worse yet ignore it…provide feedback to the office responsible. They want your feedback.

• Get involved in your office/Center’s process for providing input during the policy development process. This input is highly valued.

Page 42: Sandra smalley

Page 42

Backup

Pre-