Brandon Flood Protection Plan

• Funding Agreement

• Improvements

• Schedule

• Cost

Page 2: Flood mitigation council presentation 2 july 2013

Brandon Flood Protection Plan

• Funding Agreement

– $20M

– 90% Province 10% City

• Technical Review Committee

• Management Committee

Page 3: Flood mitigation council presentation 2 july 2013

Brandon Flood Protection Plan

• Improvements

– North Side of the Assiniboine

– South Side of the Assiniboine

– 17th St East Dike

– Land Drainage Sewer Upgrades (North Side)

– Wastewater Sewer Upgrades (North Side)

Page 4: Flood mitigation council presentation 2 july 2013

Brandon Flood Protection Plan

• Improvements North Side

– Create new dike west of 18th St N

– Raise dikes Kirkcaldy Drive

– Land Drainage Sewer Improvements

– Permanent Pumping Station

– New Wastewater Lift Station

• Discovery Center

• Kasiurak Bay

• Experimental Farm

• Brandon Youth Soccer

Page 5: Flood mitigation council presentation 2 july 2013

Brandon Flood Protection Plan

• Improvement South Side

– Raise dikes

– Permanent Pumping Stations

• Cattle Auction Mart

• Co-op Feeds

• Eleanor Kidd Park

• Brandon Softball

Page 6: Flood mitigation council presentation 2 july 2013

Brandon Flood Protection Plan

• Improvements 17th St East Dike

– Primary Dike on 17th St E

– Secondary CPR access

• Residents Primary Dike

• Green Spot

• CPR

• MB Hydro

Page 7: Flood mitigation council presentation 2 july 2013

Brandon Flood Protection Plan

• Improvement Discussion

• First Street will be allowed to be breached at 100+

year flood

– Economics

– Upstream impact

• PTH 110 (Eastern Access) will be raised

Page 8: Flood mitigation council presentation 2 july 2013
Page 9: Flood mitigation council presentation 2 july 2013
Page 10: Flood mitigation council presentation 2 july 2013

Brandon Flood Protection Plan

• Schedule

– 2013

• 18th St North Dike

• Kirkcaldy Dr Land Drainage Sewer

– 2014

• North, South and 17th St E Dikes

– 2015

• North, South and 17th St E Dikes

Page 11: Flood mitigation council presentation 2 july 2013

Brandon Flood Protection Plan

• Cost

– $32M reduced to $24M

– Further cost reduction through the detailed

design process.

• Revised pricing

• Tender strategy

– Future Funding 2014 and beyond

Page 12: Flood mitigation council presentation 2 july 2013

Brandon Flood Protection Plan

• Questions / Comments