Upload
ippai
View
1.386
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Mr. Ramesh Narayanan Chief Executive Officer BSES Yamuna Power Ltd. at RPR 2012, 23-26 August, Goa, India
Citation preview
Experiences in Distribution Privatization
Ramesh Narayanan Chief Executive Officer BSES Yamuna Power Ltd.
The 13th Regulators & Policymakers Retreat
Aug’ 2012, Goa
Presentation Flow
Demand Supply Mismatch
Generation
Reforms
12th Five Year plan
Distribution Reforms
A Glimpse
Challenges
Finance
Technology
Manpower
Strategy
Innovation
For Distribution Turnaround
2 BSES Yamuna Power Ltd.
DEMAND SUPPLY MISMATCH
3 BSES Yamuna Power Ltd.
4
Installed Capacity : 2,06,456 MW
Grid Demand : 1,25,000 MW
PROBLEM : Power Demand Constraints
BSES Yamuna Power Ltd.
HUGE Suppressed & Unaddressed Demand
Suppressed Demand in the form of
Huge piling of the New connection pendency (other than private utilities)
More than 30% of the 2 Crs pumpset run on DG Sets
Majority of the un-electrified railway corridors (other than main trunk lines)
Unavailability of efficient Public transport system : Metro, Monorail etc.
Demand Growth : 5 TIMES
5
Installed Capacity : 2,06,456 MW
Grid Demand : 1,25,000 MW
India Vs China [ Yr 1991 to Yr 2012]
BSES Yamuna Power Ltd.
Installed Capacity : 950,000 MW
Grid Demand : 7,40,000 MW
YEAR 1991
YEAR 2012
Installed Capacity : 1,50,000 MW
Grid Demand : 1,25,000 MW
Installed Capacity : 66,000 MW
Grid Demand : 57,000 MW
Demand DOUBLED
CHINA INDIA
Economic Development
* Data Source : www.wikipedia.org & other reports
GENERATION REFORMS
6 BSES Yamuna Power Ltd.
GENERATION : accelerated growth
7
Installed capacity as on Jul’12 : 2,06,456 MW
YEAR 1991-92: Liberalization Policy by Govt. of India
New Policy Framework to foster Accelerated Growth in Power.
Private / FDI participation for the Generation Sector
BSES Yamuna Power Ltd.
So
u r
ce :
CE
A
GENERATION Reforms : Enablers
8
2012: Installed capacity: 2,06,456 MW
1991: Installed Capacity: 66,00 MW
ADMINISTRATIVE FRAMEWORK
Statutory clearances sized up & streamlined.
Investment Promotion Cell in MoP.
Time bound clearances
LEGAL FRAMEWORK
Standardization of Indian Arbitration & Conciliation
Act, 1996 in line with UNCITRAL, 1976
Ease in Foreign Direct Investments
FINANCE FRAMEWORK
Concept of SPV / JV / Project based Financing
Assured Return on Equity
Cost reflective Two Part Tariff
Incentives - tax holiday, duties & taxes waivers
OBJECTIVE : Impetus to the Power GENERATION
BSES Yamuna Power Ltd.
GENERATION : Global Ranking
9 BSES Yamuna Power Ltd.
India to Rank No 3 by 2017
205
12TH FIVE YEAR PLAN [ 2012-2017 ]
10
Generation
Sector 8th plan 9th Plan 10th Plan 11th Plan 12th Plan
Central 50% 24% 57% 34% 28%
State 42% 50% 30% 34% 15%
Private 8% 26% 13% 32% 57%
TOTAL 100% 100% 100% 100% 100%
Transmission 1,36,000 CKm of Transmission Lines
2,95,000 MVA of Transformation Capacity
Distribution Cater to additional demand for : 88,000 MW
2.1 times the generation capacity ; Cost: 2.3 Crs / MW
Over 4,50,000 Crs of Investment
Over 2,50,000 Crs of Investment
Over 4,30,000 Crs of Investment
~88,000 MW addition
BSES Yamuna Power Ltd.
Over Rs 11,00,000 Crs
DISTRIBUTION : A GLIMPSE
11 BSES Yamuna Power Ltd.
DISTRIBUTION Sector : Status
Distribution Reform Area Segregation
*Including Delhi
Major Private Player engaged as Distribution Licensee
Kolkata, Mumbai, Delhi, Ahmedabad, Surat, Greater Noida, Orissa (3/4th of the state)
Major Private Player engaged as Distribution Franchisee
Agra, Bhiwandi, Kanpur, Nagpur, Aurangabad, Gwalior, Sagar etc.
Private Sector Participation a meager 4%
BSES Yamuna Power Ltd. 12
Distribution Losses @ All India Level [FY09]
13
The average AT&C losses (%) National Level for FY 09 : 28.44% (Source : PFC report)
National
Average
BSES Yamuna Power Ltd.
Distribution Challenges
14
Finance Technology Man Power
Strategy Innovation
BSES Yamuna Power Ltd.
Finance
Rs. 2.3 Cr is needed to create 1MW Distribution infrastructure
For 1,08,000 MW ( 12th Plan Demand + Existing Gap of 10%), sector requires Rs. 5,20,000 Crores
Debt: Rs. 3,65,000 Crs. (70%) ; Equity: Rs. 1,55,000 Crs. (30%)
BSES Yamuna Power Ltd. 15
Finance
• Fixed RoE (14%)
• Margin pressure Regulated Business
• Poor balance sheet
• Unpredictable revenue Difficult to raise funds
• Increased private participation
• Allowing reasonable profits Requirement
BSES Yamuna Power Ltd. 16
Dedicated Common Distribution Infrastructure Fund to be floated by government
Funds to be made available at attractive rates to Discoms
Easy access to funds like JNURM, R-APDRP, RGGVY etc
Finance
BSES Yamuna Power Ltd. 17
• 220/66 KV
• 66/11 KV
• 11/0.4 KV
Existing
• 220/33 KV
• 33/0.4 KV
Proposed
• Land
• CAPEX
• Manpower
• O&M
Advantages
Technology
BSES Yamuna Power Ltd. 18
Requirement
• 5 person /MW for urban areas
• 10-15 persons per MW for rural areas
Requirement for 12th plan
• For 88,000 MW ( Taking 7 persons per MW)
• 6,16,000 persons needed
Skill Requirement
• 70% skilled
• 4,30,000 skilled persons
Man Power
BSES Yamuna Power Ltd. 19
Training & Development
Distribution Specific
Special courses at ITIs, NPTI, IITs and IIMs
Skill Set
Knowledge
Attitude
Values/Culture
People interaction
Man Power
BSES Yamuna Power Ltd. 20
Raising the per capita consumption of power
Open & flexible
Energy Markets
Reduction of AT&C losses & Cost of supply
Improving supply Quality & Reliability
Strategy
BSES Yamuna Power Ltd. 21
Advanced Research
Remote metering
People less customer care
Money less transaction
Automation (SCADA etc.)
Safety
O&M practices
Research and Development
Dedicated centers Separate Fund Arrangement
Innovation
BSES Yamuna Power Ltd. 22
AN APPROACH
23 BSES Yamuna Power Ltd.
Comparison : Gen-Trans-Dist
Parameter Generation Transmission Distribution
Cost reflective Tariffs with timely revisions
Tax Holidays ; Excise / Import Duties waivers
Project Financing Based on
PPAs Based on
BPAs Based on
Balance Sheets
Transparency of cost/expenditure in tariff petition
Reduce Disparity Across the Power Chain
BSES Yamuna Power Ltd. 24
Supporting Framework
ADMINISTRATIVE FRAMEWORK
All statutory support to the discoms for schemes like RAPDRP etc
State government assistance for facilitating discoms network infrastructure
REGULATORY FRAMEWORK
Realistic approach towards Discom
Time bound discom cost amortization
Cost reflective tariffs & support schemes
FINANCE FRAMEWORK
Concept of SPV / JV/ Project based Financing
Assured Return on Equity
Low cost debt instruments for overall sectoral growth
Incentives in terms of tax holiday, duties & taxes
OBJECTIVE : Provide much needed Impetus to the Power DISTRIBUTION
LEGAL FRAMEWORK
Endorsement of the Electricity Act -2003
Theft / misuse of electricity
Mitigation of regulatory challenges
Discom standards of performance
BSES Yamuna Power Ltd. 25
26
Lender-Discom Partnership (LDP) Model
Indulge itself with HIGH OUTSTANDING DISCOMS
Discoms to FRANCHISE certain cities to SPV for loss reduction & reforms.
The EXISTING DEBT to be converted to EQUITY portion for that franchise
BPUs to bring in technical & business efficiencies for the franchisee
Approach towards Accelerated Distribution Reforms
BSES Yamuna Power Ltd.
Best Performing Utilities (BPU)
REC / PFC / other financial institutions SPV
Approach towards Accelerated Distribution Reforms
27
WIRE Business (EPC)
Centralized Monitoring (Inline with generation addition)
Centralized empanelment for EPC contractor (for discom network creation)
New n/w created to be leased to the state discom by the Central agency.
State Discom to pay Fixed Cost / Lease rental to the centralized agency
WIRE – CONTENT MODEL
CONTENT Business (State Discom)
Power procurement / management
Operations & Maintenance of the WIRE business
Much needed impetus to the Network Creation
BSES Yamuna Power Ltd.
Thank You
28