20
Schneider Electric - Ata Center Solutions – October 2013 Schneider Electric Modulariseret container løsning - Fast track data center alternativ Version 2 Jørgen Bjerg, Schneider Electric Marts 2014 Foundational SMALL DATA CENTER - Rev 1

Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Embed Size (px)

DESCRIPTION

Modulariseret Container løsning - Fast Track Data alternativ Har du begrænset plads, en bygning med begrænset infrastruktur, og ønsker du at 'grow as you go'? Så kan de nye Modulariserede Containere være det rette valg for dig. Det er løsninger, der både kan indeholde Køl, UPS og Racks, alternativt være dedikeret til en af tingene og sættes sammen, så det passer netop til dit behov.

Citation preview

Page 1: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric - Ata Center Solutions – October 2013

Schneider ElectricModulariseret container løsning- Fast track data center alternativVersion 2

Jørgen Bjerg, Schneider Electric

Marts 2014

Foundational SMALL DATA CENTER - Rev 1

Page 2: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 2- Data Center Solutions – October 2013

What we’ve learned from our customers

More efficientMore reliableHigher densityMore predicableMore cost effectiveMore understandableSimpler experience

We can’t get this…

…by just making better components

(UPS, switchgear, controls, air conditioners, power distribution, etc)

Page 3: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 3- Data Center Solutions – October 2013

Prefabricated Data Centres the Answer?

Traditional design-build method• Different vendors for infrastructure components and systems• One time engineering and construction.• Complicated build schedules• Long design process

Modular Data Centre Components• Improved reliability• Decreased installation time and design effort.• Created the “system” approach to design.• Grow infrastructure in whitespace with demand

Prefabricated Data Centre Systems• Modularity in larger building blocks. • Pre-assembled systems, delivered on-site, factory tested. • System-optimized designs with onboard management systems.• Grow entire infrastructure with demand• Quick installation, reduced commissioning time

Page 4: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 4- Data Center Solutions – October 2013

Data center components delivered as prefabricated functional building blocks

IT

Power

Cooling

Page 5: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 5- Data Center Solutions – October 2013

Prefabricated Data Center advantages . . .

Predictable Performance

• The density, availability

and efficiency you

expected

• The cost you were

promised

• Project timing as you

planned

Faster Deployment

• Less decisions necessary

for planning and design

• Up to 60% less time for

deployment

• Delivery in 12 weeks or

less: PO to ship

Flexibility and Scalability

• Defer capital expenses

and maximize cash flow

• Adjust for changing

requirements

• Deploy in various

configurations of density

and availability

. . . vs. traditional data centers

Page 6: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 7- Data Center Solutions – October 2013

Common Applications for Prefabrication

Large/Multi-tenant data centerScalable growth - improve cash flow

Factory environmentHarsh/corrosive conditions

Data center with dynamic growthFlexibility to build in phases

Building retrofit Existing building infrastructure

cannot support future growth

Small/Medium data center IT manager lacks staff to

support infrastructure design

Industrial and remote Standalone data center anywhere

Page 7: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 8- Data Center Solutions – October 2013

Power Equipment Centers

Power ZoneCenters

Power and Cooling Centers

Electrical DistributionCenters

PackagedChillers

1950

20032006

2012

2009

InfrastruXureEcoBreeze

Power & Chilled Water Proof of Concepts

InfrastruXure Express

ETO Power ModulesPrefabricated

Reference Designs

2011

Evolution of PrefabricationSince 1950

Acquire AST Modular – 14years of Prefab DC

Experience

2013 2014

Page 8: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 9- Data Center Solutions – October 2013

• 12 years’ experience in prefabricated DCs with over 80 reference designs

• Proven ability to design and execute on modular projects worldwide (over 30 countries)

• Improved support to EMEA, Latin America, and APJ

• Complementary product offer with minimal overlap

• Efficient cooling options specific to Prefabricated construction

• Headquarters: Barcelona, Spain - Manufacturing & Engineering in Barcelona & Miami

• Founded in 1999 by Daunert brothers as spin-off of family machine-tool distribution business.

• Pioneered the first data center in an ISO shipping container in 2001

• First Company to build a Tier III certified multi-module data center.

• Over 450 data center projects successfully executed

Key Facts Benefits to Schneider

AST Modular at a glance

Page 9: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 12- Data Center Solutions – October 2013

Pow

erIT

Spa

ceC

oolin

gCombined AST/Schneider Offer

Page 10: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 13- Data Center Solutions – October 2013

• 250kW 20ft Enclosure with UPS, Switchgear, cooling, DCIM

• 500kW 40ft Enclosure with UPS, Switchgear, cooling, DCIM

Power Modules

Power Modules

Page 11: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 14- Data Center Solutions – October 2013

Critical Switchboards

500kW Symmetra PX

Fire Suppression

System

Symmetra N+1 UPS(250/500kW) 5 min Runtime Switchboard w/ integrated ATS Power monitoring, management

and controls Environmental cooling Fire Suppression UL Listed

500kW Module 250kW Module

Power Module Detail

Page 12: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 15- Data Center Solutions – October 2013

• 90kW All-in-One (40ft Enclosure,10 Racks, UPS, PDU, In-Row DX Cooling, DCIM)

• 110kW Single Module (40ft Enclosure, 10 racks, PDU, In-Row CW cooling, DCIM)

• 205kW Single Module (53ft Enclosure,14 racks, PDU, In-Row CW cooling, DCIM)

• 240kW Dual Module (20 x 45ft Enclosure 22 Racks, PDU,

In-Row CW cooling, DCIM)

• 240kW Dual Module (20 x 45ft Enclosure,24 Racks, PDU, 3 Perimeter CRACs CW cooling, DCIM)

IT Room Modules

IT Modules

Page 13: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 16- Data Center Solutions – October 2013

11 Racks

90kW N+1 cooling capacity

8kW per rack capacity with 2N 400V power distribution

Power monitoring, management and controls

Fire detection and suppression

Staging lobby for outside isolation

APC InRow™ Coolers Hot Aisle

Containment

96kW Symmetra PX UPS and 415V Modular Power

Distribution

Staging Lobby and Electrical Room

90kW All-in-one shown

IT Module Detail

Page 14: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 17- Data Center Solutions – October 2013

24 Racks (EMEA)

240kW cooling capacity 400V distribution

@11kW per rack (2N) Power monitoring,

management and controls

Fire detection and suppression

Staging lobby for outside isolation

APC InRow™ Coolers

Hot Aisle Containment

Modular Power Distribution

Staging Lobby and Electrical Room

2 bay, In-Row, 240kW shown

IT Module Detail

Page 15: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 18- Data Center Solutions – October 2013

• 500kW Hydronics Modules

(Pumps, VFDs, DCIM and controls, connections for 3-250kW Chillers)

• 1000kW Hydronics Modules

(Pumps, VFDs, DCIM and controls, connections for 3-600kW Chillers)

• 250kW – 1.2 MW Packaged Air Cooled Chillers - Options with and without free cooling

• Ecobreeze ISO frame 50kW increments up to 400kW

of total cooling capacity (DCIM)

Cooling Modules

Cooling Modules

Page 16: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 19- Data Center Solutions – October 2013

• Chillers (install in field)• Enable Greater Flexibility to handle

Varying load and ambient conditions• Utilize 3rd party chillers as required

• Hydronics Module• Mechanical Packaging designed to

handle flow rates based on design loads based on pipe size

• Pumps and Electrical will be configured based on specific customer Requirements

• Thermal Storage Option• Provides flexibility to offer as required

•Adaptable to different ride through requirements•Initial design based on 5min

Hydronics ModuleAvailable in Tier II and Tier III

Page 17: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 25- Data Center Solutions – October 2013

StruxureWare DCIMIntegrated in each Prefabricated Building Block

Page 18: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 26- Data Center Solutions – October 2013

StruxureWare DCIMDashboard for Prefabricated Data Centers

Page 19: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric 39- Data Center Solutions – October 2013

Prefabricated Data Center advantages . . .

Predictable Performance

• The density, availability

and efficiency you

expected

• The cost you were

promised

• Project timing as you

planned

Faster Deployment

• Less decisions necessary

for planning and design

• Up to 60% less time for

deployment

• Delivery in 12 weeks or

less: PO to ship

Flexibility and Scalability

• Defer capital expenses

and maximize cash flow

• Adjust for changing

requirements

• Deploy in various

configurations of density

and availability

. . . vs. traditional data centers

Page 20: Datacenter 2014: Schneider Electric A/S - Jørgen Bjerg

Schneider Electric - Ata Center Solutions – October 2013

Make the most of your energy™