CONSTRUCTION PROJECTS
DEPARTMENT OF AVIATION
DESIGN AND CONSTRUCTION
MONTHLY MAYORAL INFRASTRUCTURE PRESENTATION
� TERMINAL 5 PEDESTRIAN WALKWAYS (Project No. H2008)
� TERMINAL 5 UPPER LEVEL GROUT POCKETS (Project No. H3061.05)
� TAXIWAY WT REHABILITATION (Project No. H6157.08-01)
� ORD RUNWAY 4R/22L ARRESTOR BED (Project No. H6157.07-01)
� ORD ARFF TRAINING FACILITY BURN PIT REHABILITATION(Project No. H6164.07)
� ORD TERMINAL APRON PAVEMENT (Project No. H6166.08)
� HTW SYSTEM PUMP UPGRADE – SOUTH PUMPS (Project No. H7085.06)
� MDW EMPLOYEE PARKING LOT “A” EXPANSION (Project No. M5026.02)
� MDW RUNWAY 4R/22L REHABILITATION (Project No. M6090.07)
3
TERMINAL 5 PEDESTRIAN WALKWAYS O’Hare International Airport
DOA Project No. H2008
Construction Contract Amount: $1,358,230Contractor: F.H. Paschen / S.N. Nielsen
Substantial Completion: 9/10/08Notice To Proceed: 3/18/08
PM (Construction): Ron TamasonPM (Design): Larry Pianto
Design Contract Amount: $132,478Designer: H.W. Lochner, Inc.
� Status Summary– Site investigation of existing fascia material
completed. Fascia materials on order.
– Site investigation of corroded structural members complete.
� Progress– Schedules affected by unforeseen conditions
– corroded structural members and structural connections of handrails.
– Final design solution to drainage and structural issues.
– Building permit received.
� Attention Areas– Continued coordination with Airport Transit
System and Landside Operations.
– Review revised schedule to project new completion dates caused by design changes.
The scope includes Design/Construction to rehabilitate the six pedestrian walkways at O’Hare Terminal 5 to prevent drainage into the vestibules and replace deteriorated fascia panels.
Structural corrosion repairs MMIP-0801084
TERMINAL 5 UPPER LEVEL GROUT POCKETS O’Hare International Airport
DOA Project No. H3061.05
� Status Summary– Revised repairs underway.
– Concrete placement started 5/22/08.
� Progress– Type V Fascia repair completed.
– 45 degree patches near completion.
– Scaffolding for guardrail sandblast and paint.
– Time extension of 10 days granted to accommodate revised Type V repairs.
– Overall project is 95% complete.
� Attention Areas– Coordination continues with Airport Transit
System and Landside Operations.
– Construction schedule: 04/21/08 – 08/28/08.
The scope includes the removal, replacement and repair of existing post-tension grout pockets on the O’Hare Terminal 5 upper level bridge.
Type V Fascia Repair in Upper
Construction Contract Amount: $2,278,528Contractor: McHugh/Riteway Joint Venture
Substantial Completion: 8/28/08Notice To Proceed: 3/11/08
PM (Construction): Ron TamasonPM (Design): Larry Pianto
Design Contract Amount: $84,810Designer: H.W. Lochner
MMIP-0801085
REHABILITATION OF TAXIWAY WT O’Hare International Airport
DOA Project No. H6157.08-01
Construction Contract Amount: $12,793,200Contractor: Rossi Contractors
Substantial Completion: 9/30/08Construction Notice To Proceed: 4/30/08
PM (Construction): R. David HerroldPM (Design): Kenneth Lee
Design Contract Amount: $1,650,442Designer: A. Epstein & Sons International
Improvements to the previous runway 18/36, (current temporary taxiway GG) pavement for use as a taxiway, including pavement removal, pavement scarilay, new concrete taxiway pavement, new shoulder pavement, grading, drainage, pavement markings, new taxiway edge lighting, new runway guard lights and landscaping.
Taxiway WT Concrete Replacement MMIP-080108
� Status Summary– Phase 1 electrical work and PCC concrete
pavement nearing completion.
– Fine grading shoulder stone started.
� Progress– Phase 2 electrical work in progress.
– P-401 test strip in place as of 7/24/08. Awaiting test results on test strip prior to further paving.
– Scarification, overlay and electrical work in progress.
– Phase 3 subbase, ATPB and binder course nearing completion.
� Attention Areas– No current issues.
6
RUNWAY 4R/22L ARRESTOR BED SYSTEM O’Hare International Airport
DOA Project No. H6159.07-01
� Status Summary– Block installation nearing completion.
� Progress– Current schedule completion was
06/20/08, but delay due to FAA changes, weather (rain) and utility locations will impact the date (possible 6 weeks).
– FAA changes received.
� Attention Areas– Coordinating with FAA on design issues
pertaining to FAA lights and Navaids.
– Pricing FAA requested changes.
– Discussion of funding for those changes.
– Repair of EMAS areas destroyed by aircraft involvement on 7/18/08.
This project is for the design and rehabilitation of Runway 4R/22L Arrestor Bed System at O’Hare Airport.
Runway 4R/22L Arrestor Bed System MMIP-080108
Construction Contract Amount: $8,944,630Contractor: Walsh Construction Co.
Substantial Completion: 07/12/08Construction Notice To Proceed: 09/24/07
PM (Construction): R. David HerroldPM (Design): Kenneth Lee
Design Contract Amount: $1,178,358Designer: Patrick Engineering
7
AIRCRAFT RESCUE FIRE FIGHTING TRAINING FACILITY BURN PIT REHABILITATION
O’Hare International AirportDOA Project No. H6164.07
� Status Summary– New concrete footing completed.
– Concrete slab to close the 30’x30’ opening completed.
� Progress– Form work for new concrete curb
started.
– Rebar installation.
� Attention Areas– No current issues.
Limited demolition and replacement of elements in the existing ARFF Training Facility Burn Pit. Scope also includes replacement of piping, equipment, steel bridge grating and supply lines.
MMIP-080108
Construction Contract Amount: $3,857,660Contractor: Kidde Fire Trainers
Substantial Completion: 11/25/08Construction Notice To Proceed: 3/31/08
PM (Construction): Roussos AvgoustakisPM (Design): Larry Pianto
Design Contract Amount: $222,350Designer: Kidde Fire Trainers
11
TERMINAL APRON PAVEMENT O’Hare International Airport
DOA Project No. H6166.08
Construction Contract Amount: $17,725,000Contractor: Rossi Contractors, Inc.
Substantial Completion: 11/15/2008Construction Notice To Proceed: 04/01/08
PM (Construction): R.D. HerroldPM (Design): Kenneth Lee
Design Contract Amount: $145,000Designer: HNTB, Inc.
Scope includes the construction and associated services necessary to remove and replace existing apron pavement and improve the drainage at the Domestic and International Terminal and concourses during the 2008 construction season.
MMIP-080108
� Status Summary– Gate F6 completed 6/01/08.
– GateL3 completed 6/27/08.
� Progress– Work to continue until Mid-November
(Funding and weather permitting).
� Attention Areas– Planning for work at Gates K and L.
– Funding for continued work on Apron is needed.
– City/Airlines to meet for T5 Apron planning and schedule.
12
RUNWAY 4R/22L REHABILITATION Midway International Airport
DOA Project No. M6090.07
� Status Summary– Variable depth asphalt pavement
operation underway.
– Asphalt pavement and drainage improvements in the Bullseye underway.
� Progress– Removal and replacement for Phase I
bituminous inlay complete.
– Variable depth milling and replacement with bituminous base material for runway 4R mainline pavement 90% complete.
– Detention basin excavation started 7/14/08.
– Bullseye pavement, electrical work and drainage work continues.
� Attention Areas– Maintain scheduling and phasing with
Midway Operations, Airlines and FAA.
This project is for the design and rehabilitation of Runway 4R/22L at Midway Airport.
Midway Runway 4R/22L Rehabilitation MMIP-080108
Construction Contract Amount: $13,360,298Contractor: Central Blacktop
Substantial Completion: 10/26/08Construction Notice To Proceed: 4/28/08
PM (Construction): Robert RupertPM (Design): Kenneth Lee
Design Contract Amount: $1,148,718Designer: Earth-Tech
15
ELEVATED PARKING STRUCTURE GREEN ROOF Midway International Airport
DOA Project No. JM5047
� Status Summary– Work is 100% Complete.
– Project completed on time.
– Construction Schedule: 5/12/08-6/30/08.
This project is for the design and rehabilitation of Runway 4R/22L at Midway Airport.
MMIP-080108
Construction Contract Amount: $127,411Contractor: Meccor Industries, Ltd.
Substantial Completion: 06/12/08Construction Notice To Proceed: 4/16/08
PM (JOC Construction): Thomas McFallPM (Design): Robert Dawson
Design Contract Amount: $145,784Designer: Muller & Muller
17 Completed Green Roof Project
ELEVATED PARKING STRUCTURE GREEN ROOF Midway International Airport
DOA Project No. JM5047
Additional Photos – Completed Green Roof Project
MMIP-08010818
2008 Residential Lighting
1253Underground 100%
120Underground 25%
5695ISSUED
90120ENG. COMP.
164243REQUESTED
MAYOR’S ALD. MENU# of Blocks
08/21/2008 13
2008 BOE- PBC Projects� CFD E18 1360 S. Blue Island- Complete
� CFD E70 6030 N. Clark- Complete
� CFD E102 7340 N. Clark- Active
� Skinner School 1260 W. Adams-Anticipated Start Sept. 2008
� Work with PBC to install new street lighting and Traffic Signal priority system for Fire Houses if necessary.
08/21/2008 14
2008 CHA Projects
� Madden Wells Phase 2 – Active 3700-3900 S. Vincennes
� Stateway Gardens Phase 1 – Active 3600 S. Federal
� Phillip Murray Homes – August 08 13300 S. Dobson
� Francis Cabrini Homes – Fall 2008
� Working with other city agencies and CHA contractors to install new Lighting
08/21/2008 15
2008 WPA – CDOT
� South Area Project 4 – Active 108th St. Burley to State Line Road
� North Area Project 5 – Complete New England-Newcastle-Balmoral-Altgeld
� 3300 S. Oakley- Start Aug. 2008� South Area Project 5- Start Aug. 15
7500 to 7600 S. Halsted-Racine � 117th to 118th Longwood-Hale; Sept. 15
� Working with CDOT and installing new Residential Lighting Systems.
Chris Bushell
Director, Power & Way Maintenance, Construction and Engineering
August 1, 2008
City of Chicago Infrastructure Meeting
Patricia Taylor
Vice President, Facilities Maintenance, Construction and Engineering
Presented by Chicago Transit Authority
Infrastructure PresentationFriday, August 1, 2008 17
Today’s Presentation
Project Reports To
1. Brown Line Capacity Expansion Project Patricia Taylor
2. Howard Station Patricia Taylor
3. Subway Escalator Replacement Project Patricia Taylor
4. State Street Tie Renewal Project Chris Bushell
5. Ravenswood and North Mainline Tie Renewal Chris Bushell
6. Blue Line Signals Chris Bushell
7. Blue Line O’Hare Slow Zone Removal Chris Bushell
8. Loop Signals Chris Bushell
Infrastructure PresentationFriday, August 1, 2008 18
Facilities Construction
Project Update: Brown Line RehabilitationWittmann/ Titzer/ Hurtado
Project Value/Total Budget $529.9M
Earned to Date $374.8M
Percent Earned to Date 70.7%
Percent Time Used to Date 69%
Brown Line Schedule Status & Project Update as of 8/1/08
Station Updates
� Fullerton (Completion: December 2009)
� Construction requiring 3-track operation to be complete by 12/31/08. Work to install the permanent stairs at the station house to be complete by August 1, 2008. Caissons north of Fullerton are complete and the contractor continues with installation of remaining caissons. Installation of the struts and caisson caps continues.
� Belmont (Completion: December 2009)
� Construction requiring 3-track operation to be complete by 12/31/08. Track 2R and half of new SB platform placed into service on July 11, 2008. Installation of stairway walls and slab on grade is on-going. Demolition south of the old stairways at Belmont completed. Demolition continues north of Belmont. Caisson installation on the south side of Belmont continues.
� Armitage (Open)
� Removal of temp station, installation of rotogates, structure painting, installation of new landscape planters and ornamental fencing completed. Installation of drip pan and lighting ongoing.
Infrastructure PresentationFriday, August 1, 2008 19
Brown Line Capacity Expansion ProjectProject Update
Facilities Construction
Station Updates
� Chicago (Completion: September 2008)
� Work continues on historic station house, electrical room, elevators and platform railings. Installation of station house roof and curtain wall ongoing. New sidewalks on the south side of Chicago Ave and two-way traffic on Franklin opened on July 18, 2008. Temporary stairs on Franklin to be removed by August 1, 2008.
� Diversey (Station Opening: August 4, 2008)
� Contractor continues with painting, signage installation, and station detail work. New station to open for service on August 4, 2008.
� Damen (Completion: December 2008)
� Detailing of new platform structural steel, historic stationhouse rehabilitation, and new station house build out continues. Installation of platform decking, guardrails, tactile edging, and electrical work ongoing. Elevator installation has begun.
� Irving Park (Completion: January 2009)
� Detailing steel, bent foundations and platform conduit work continues. Stationhouse and elevator tower masonry and platform guardrail work has begun.
� Paulina (Completion: May 2009)
� Installation of bent foundations, platform decking, station masonry, painting of structural steel, platform conduit and guard rails is on-going.
� Wellington (Completion: August 2009)
� Bent foundation replacement and utility relocations are ongoing.
Infrastructure PresentationFriday, August 1, 2008 20
Facilities Construction
Total Project Budget $ 87.6M
Contract Value $ 56.7M
Earned to Date $ 45.5M
Percent Earned to Date 80 %
Percent Time Used to Date 76 %
Howard/Red Line Schedule Status & Project Update as of 8/1/08
Project Update
� New terminal station entrance opened June 9, 2008. Station is ADA compliant, has 4 elevators and 6 escalators and tactile edging and signage.
� Howard Street entrance scheduled to be closed at the end of July 2008 and will be closed until February 2009.
� Howard Street closures will continue during this time as required for concrete restoration.
� Construction work scheduled for completion in February 2009.
Project Update: Howard/Red LineMascheri
Infrastructure PresentationFriday, August 1, 2008 21
Project Update: Howard/Red LineMascheri
South Terminal Entrance with High Canopy New Escalator to Platform Level
Facilities Construction
Infrastructure PresentationFriday, August 1, 2008 22
Project Update: Howard/Red LineMascheri
North Side of Howard Street - Historic Entrance (Future Tenant Space/Auxiliary Exit)
Facilities Construction
Infrastructure PresentationFriday, August 1, 2008 23
Facilities Construction
Project Update: Subway EscalatorsMascheri/ Herndobler
Total Project Budget $21,159,952
Construction Contract Value $16,581,000
Earned to Date $1,926,903
Percent Earned to Date 12%
Percent Time Used to Date 21%
Subway EscalatorsSchedule Status & Project Update as of 8/1/08
Project Update
� Work has begun to re-open the Polk Street exit at the Harrison Red Line Station. The Polk Street exit will be opened by the end of 2008.
�Construction on first three escalators begins at the end of July 2008 with:
� Monroe/Adams (platform to mezzanine) scheduled completion of January 2009
� Adams/Jackson (mezzanine to street) scheduled completion of December 2008
� Jackson/Van Buren (mezzanine to street) scheduled completion of December 2008
Infrastructure PresentationFriday, August 1, 2008 24
Power & Way Construction
Project Update
� Demolition began 2/15/08 and as of 6/16/08, 27,198 ties have been removed.
� The Installation of concrete half ties began April 5, 2008 and as of July 21, 2008, 23,973 ties were poured.
State Street Tie ReplacementSchedule Status & Project Update as of 8/1/08
Project Update: State Street Tie ReplacementMorey/Heard
Total Project Budget $38.1M
Contract Value $26.6M
Earned to Date $16.60M
Percent Earned to Date 60.6%
Percent Time Used to Date 60%
Infrastructure PresentationFriday, August 1, 2008 25
Power & Way Construction
Project Update: Ravenswood/ North Main TiesMorey/ Ohs
Total Project Budget $44,524,011
Contract Value $22,852,000
Earned to Date $3,864,590
Percent Earned to Date 17%
Percent Time Used to Date 44%
Ravenswood and North Main Tie Renewal ProjectSchedule Status & Project Update as of 8/1/08
Project Update
� Construction work started June 4, 2008. The following tie renewal has been completed as of 7/28/08:
� Track 1 = 2,700 feet
� Track 2 = 3,200 feet
� Western Center Track = 560 feet
�Milestone 1--furnish and deliver materials--is set for September 13, 2008.
�Ravenswood work is scheduled for completion in December 2008.
Infrastructure PresentationFriday, August 1, 2008 26
Power & Way Construction
Total Project Budget $243M
Contract Value $164.8M
Earned to Date $130.5M
Percent Earned to Date 79%
Percent Time Used to Date 74%
Blue Line SignalsSchedule Status & Project Update as of 8/1/08
Project Update
� Installed cab signals on the Congress Branch of the Blue Line from Forest Park to Loomis. Old equipment removal from the right-of-way is ongoing.
� Installed cab signals on the Kennedy Branch of the Blue Line from Jefferson Park to Damen. The cutover between Damen and Division was completed on July 27, 2008. During the week of July 12, 2008, two relay houses were delivered to Grand crossover. Wiring of the houses is ongoing.
Project Update: Blue Line SignalsGray/ Hampton
Infrastructure PresentationFriday, August 1, 2008 27
Total Project Budget $126M
Contract Value $99.7M
Earned to Date $59.5M
Percent Earned to Date 59.9%
Percent Time Used to Date 75.74%
Blue Line Slow Zone RemovalSchedule Status & Project Update as of 8/1/08
Project Update
� Phase 2 project construction began March 28, 2008. In this phase, approximately 58,939 feet of track have been replaced as of 7/24/08.
�Additional Track Footage has been added to the contract. This includes replacement of the direct fix fasteners in the O’Hare Subway.
Project Update: Blue Line Slow Zone RemovalGray/ Zinck
Power & Way Construction
Project Completion
Total track feet to complete 110,633
Percent track feet complete 77.4%
Infrastructure PresentationFriday, August 1, 2008 28
Power & Way Construction
Total Project Budget $103.8M
Contract Value $67.1M
Earned to Date $8.1M
Percent Earned to Date 12.1%
Percent Time Used to Date 56.6%
Loop SignalsSchedule Status & Project Update as of 8/1/08
Project Update
�The Loop track renewal work is currently scheduled to resume the weekend of September 5-7, 2008. Work will include the replacement of 1,100 track feet from Randolph/Wabash to 250 feet South of Madison.
�DBEC is installing train stops, signal platforms, and local signal cable in the Loop. DBEC is installing conduit in the LaSalle Street Trolley Tunnel. DBEC continued with switch machine replacement in the Loop. DBEC is performing prep work to prepare for the cutover of GRS1 to GRS2 audio circuits.
� Tower 18 work is currently scheduled for Fall 2009. DBEC is currently investigating ways to accelerate this work so that it can begin in Spring 2009.
Project Update: Loop SignalsGray/ Dyra
Montrose Sewer ProjectMontrose Sewer ProjectPhase I - General Contractor• Project Overview
– 820 feet of 36” & 48” sewer pipe– Estimated construction cost $950,000– Wolcott to Ravenswood to Hermitage– Contractor: Reliable Contracting &
Equipment Company
• Current Status
– Construction started July 28, 2008
– Scheduled end date October 6, 2008
Phase II In-House Crews
• Project Overview– 800 feet of 54” & 60” sewer pipe
– Estimated construction cost $1,100,000
– Damen to Wolcott
• Current Status
– Start March 2009
• Project Overview– Demolition and reconstruction of the last roadway
segment at Jardine– Completed all demolition– Scheduled completion October 1, 2008
• Current Status– Upper Roadway closed 4 months… May – August
– All roadway decking will be placed by August 31, 2008
– Sidewalk open to pedestrians August 13, 2008
• Contractor & Cost Summary– FHP Tectonics Corp– Current construction cost = $14 M– Total contract change order = $3 M
• Hydro Demolition – 320 LF• Conventional Demolition – 160 LF• Latex Modified Concrete• Asphalt credit of $200 K +/-
– Total estimated construction cost = $17 M
Jardine West Ramp Upper Jardine West Ramp Upper
Roadway ProjectRoadway Project
Lower Section of Roadway
Sidewalk
28th Ward Yard - 4211 W. Ferdinand .The project consists of Design and construct an
addition to the existing equipment storage facility.
Also an interior pre-fabricated office structure for
the Streets and Sanitation equipment supervisors
and truck drivers.
Current status: In punch, move in scheduled for
Aug.-08-08.
Project construction: started September-07
and completion is August-6-08.
Maxwell Street Market Permit
Center – 800 S Des PlainesThis is an existing building on the
new market property. This 2100 SF
building will be completely
renovated and registered LEED
with a goal of silver.
Current status: In construction. 75%
Project construction: started June
-08 and completion September-26-08.
Installation of filtered exhaust extraction
systems for 8 Fleet Maintenance Facilities.The project consists of individual exhaust
extraction systems for various repair areas
in Fleet facilities.
Current status: In construction.
Project construction: started March-17-08
and completion September-19-08.
Comfort Station Upgrades
Asbestos, lead paint and floor tile abated.
New concrete floor, interior plumbing &
heating and new tile roof being installed.
Current status: In construction.
Project construction: started March-24
-08 and completion August-29-08.
Photo of new windows installed.
Photo of boom arm type system completed
at 1685 N. Throop.
Merlo Library Façade, 644 W. BelmontHighlight original art-masonry facade and increase
identity as a library by replacing bronze mirrored
glass with clear, fritted glazing and new landscaping.
Existing entry will be passively cooled in summer
and provide passive solar heating in winter.
Current status: Test panels are installed. Frit glass
panels are being fabricated for installation in 3rd
Quarter 2008.
Streets & Sanitation Building
Renovation 2352 South AshlandOffice Building LEED-CI renovation.
Current status: North Garage – permit for
interior construction of one office, egress
correction and masonry repairs is in process.
Photo of Frit glass at night.
New 7th & 10th Ward Yards
9160 S. Harbor AveCurrent ward office being demolished for
IDOT, US 41project. This new facility will be
LEED silver.
Current status: Waiting for Procurement award
to Pacific Const..
1869 Pershing Building RenovationRenovate 6 firs (Approx 600,000 SF) of
Space for City warehouse. When
completed it will house over 14 City depts.
and consolidate 7 leases.
Current status: Phase II construction
80%.Drawings for next Phase completed.
Project construction: to finish end of 2011.
Photo of completed office area.
Department of Planning ImprovementRenovation of space includes new carpeting,
furniture, ceilings, HVAC, lighting and new
offices.
Current status: Phase 3 framing complete
drywall started.
Project construction: started July-14-07 and
end December-1-08.
Mayor’s Office for People with
Disabilities:Renovation of space includes new carpeting,
furniture, ceilings, lighting and new offices.
Painting of new and existing offices.
Current status: In Schematic Design.
Project construction: to start September-15-
08.
Chicago Cultural Center DomeThe project was to restore the art glass in the Preston Bradley Hall Dome and install a new
skylight above.
Current status: Project Completed.
Project construction: started December-17-07 ended July-1-08.
Project selected to receive 2008 “Chicago Landmark Award for Preservation Excellence”
Photos show the restored Tiffany dome with cornice leaf painting, natural lighting
from new skylight, LED cornice lighting & restored decorative lighting.
Rehabilitation and Replacement of the
Exterior Wall System at Area 2
Police Facility. 727 East 111th Street.The proposed exterior wall system
modifications required to resolve water
infiltration issues currently existing at this facility.
Current status: Permit approved. Awaiting Shop
drawings.
Project construction: to start 4th quarter.
Install new Canopy for the
Mixing Station at Millennium Park.Current status: Awaiting Funding
Project construction: to start October-
13-08 and end November-26-08.
08/21/2008
39
CDOT
Infrastructure Presentation
Grand and State CTA Red Line Subway Station Renovation
08/21/2008 41
Phase 1 Excavation
AMA State St
Phase 6
Rock
Bottom
Grand Av
Pedestrian Tunnel WorkPhase 2 Earth Retention Soldier Piles
08/21/2008 42
Project Scope and Highlights
� Current phase – Stage 1 (SW and SE Corner of intersection)
� Includes the full renovation and expansion of the Grand/State Red Line Station, along with lighting, signage, electrical, communications, new stairs, escalators, elevators, & granite flooring.
� This phase of the project will require an intricate underpinning foundation system utilizing easements in the commercial property on the SW Quadrant of the intersection.
� Constant utility coordination will be required during all phases of construction.
08/21/2008 43
Status Summary
� Completion Date: Spring 2010
� April 1, 2008 – Started Stage 1 construction.
� Stage 1: Includes the construction of the southeast and southwest quadrants – 4 excavation phases (8 month duration).
� All 4 phases are completely contained with 8’high security fence and cloth tarps.
� Temporary signals have been installed for traffic and pedestrians specific to the movement of this traffic stage.
� Original Bid Amount: $67,254,000
08/21/2008
44
CDOT Infrastructure
presentation
Wabash Avenue
Harrison to Roosevelt
Renovation Project
08/21/2008 45
Partial sidewalk on grade removal in progressTraffic control devices installed for closure of east side
curb lane of Wabash as construction zone
Partial sidewalk on grade removal in progress with
existing trees to remain in placeMaintaining access to residential building
throughout construction zone
Project Description
The Wabash Avenue Renovation Project includes reconstruction or abandonment of selected vaults, installation of new street lighting, sidewalk, decorative planters, ornamental fence, irrigation system, and repaving of Wabash Avenue from Harrison to Roosevelt.
08/21/2008 47
Status Summary
�Stage 1 operations were started on July 8, 2008, on the east side of Wabash from Roosevelt to Harrison
�Project is scheduled to reach substantial completion by July 2008.
�The current projected cost of the project is $8.0 million.
08/21/2008 48
Progress
�Sidewalk on grade removal in progress.
�Removal and replacement of sewer catch basins in progress.
� Installation of electrical conduit runs in progress.
�Preparation of vault spaces to be reconstructed with utilities supported in place or adjusted.
08/21/2008 50
Installation of retaining wall footing at East
Benton Place to abandon vault spacePartially abandoned vaulted space found at East Benton
Place will be backfilled.
Vaulted sidewalk structural slab reconstruction at 55
East Washington - Pittsfield Building Concrete driveway placement at 171 North
Wabash
Project Description
The Wabash Avenue Renovation Project includes reconstruction or abandonment of selected vaults, installation of new street lighting, sidewalk, decorative planters, ornamental fence, irrigation system, community identifiers, and repaving of Wabash Avenue from Wacker Place to Harrison Street.
08/21/2008 52
Status Summary
�Stage 2A operations were started on May 19, 2008, on the east side of Wabash from Wacker Place to Monroe Street.
�Project schedule revised to reflect substantial completion by November 2008.
�The current projected cost of the project is $20.0 million.
08/21/2008 53
Progress
�Vaulted sidewalk reconstruction being completed from Washington Street to Madison Street - east side.
�Sidewalk topping replacement in progress from Lake Street to Randolph Street - east side.
�CTA structure painting in progress - Van Buren to Congress- east side
08/21/2008
54
CDOT Infrastructure
presentation
US Route 41 Relocation
Harbor Avenue to 79th Street
Grading and Underground
08/21/2008 55
Water Main Pressure TestingPlacement of Cofferdam #4 Seal Coat
Concrete
CDS Treatment Structure Installation Cofferdam #4 Excavation
Project Description
The US Route 41 Relocation Project Underground Contract includes all earthwork, utilities, and demolition of old foundations required to facilitate a mile-long reroute of the existing roadway from Harbor Avenue to 79th Street along the Lake Michigan shoreline over the old United States Steel property.
08/21/2008 57
Status Summary
�Work commenced on October 19, 2007.
�The CPM Schedule was submitted on time to meet the Milestone 1 requirement.
�The current projected cost is $17,361,878.00.
08/21/2008 58
Progress
� 6 of 11 components of the treatment structure have been installed.
� New water main from 87th Street to 85th
Street has been pressure tested.
� Concrete seal coat was placed in Cofferdam #4 July 22, 2008
� Construction of box culvert began on July 28, 2008.
� The project completion date remains December 1, 2008.
08/21/2008
59
CDOT Infrastructure
Presentation
Milwaukee Avenue Improvements – Section 1Montrose Avenue to Gale Street
08/21/2008 60
Detours
� Alternate routes include N. Cicero Avenue and N. Central Avenue.
� Northbound and Southbound traffic have been shifted to the east side of Milwaukee Avenue throughout each construction stage.
� Parking is stripped within the limits of each stage.
08/21/2008 61
Pedestrian Traffic Control Preparations
Telephone Manhole Removal at Montrose
Avenue
Gas Main Work at Sunnyside Avenue
Pavement and Street Car Track Removal
08/21/2008 62
Project Scope and Highlights
� The scope of work consists of pavement resurfacing, parking lane reconstruction, new sewer construction, lining of existing sewer to remain, and installation of new landscaping and streetscaping elements along Milwaukee Ave. between Montrose and Gale St. Included is new curb and gutter, new sidewalk with ADA ramps, replacement of existing lighting with Chicago 2000 street light system, modernization of six traffic signals, stamped pavement crosswalks, 120 new trees with cast iron tree grates, and decorative street furniture (such as benches, trash receptacles, and bike racks). The Higgins Avenue Triangle will also be improved with new granite pavers and lighting.
08/21/2008 63
Status Summary� Field work is still in early stages, with a Notice to Proceed
of June 30, 2008. This work is scheduled for completion in the summer of 2009.
� Currently working along the west side of Milwaukee Avenue between Montrose and Giddings St. Existing pavement and railroad track removal is complete.
� Upcoming work includes installation of sewer and drainage related items, followed by curb & gutter and pavement.
� Current Contract Amount: $8,043,226.54
08/21/2008
64
CDOT Infrastructure
Presentation
East Jackson Drive Over Metra RailroadBridge Reconstruction
08/21/2008 65
Traffic Control
The project is now open to both vehicular and pedestrian traffic. Concrete barriers are in place along both sidewalks on the bridge. These barriers will also be used for curb-lane and sidewalk closures to facilitate the construction of the architectural bridge railing and the Metra stairs.
08/21/2008 66
Reconstructed landing at the
Chicago Park District stairway
Sandblasted Pier 2
Metra Stair Construction Existing Traffic Control for stair
and railing construction
08/21/2008 67
Project Scope and Highlights
�Work includes reconstruction of the existing bridge over the Metra railroad tracks, vaulted approach slabs, adjacent roadways, sidewalks, and infrastructure from the east edge of the South Grant Park Garage and to the west at Columbus Drive.
08/21/2008 68
Status Summary� Field work is currently over 87%
complete. The project started in mid-November. The project is scheduled for completion in October of 2008.
� The bridge is now open to vehicular and pedestrian traffic. Most roadway and structure construction has been completed. Remaining items include architectural bridge railing, Metra stairs, electrical work, and bridge painting.
� Current Contract Amount: $11,301,608.67
7/30/2008
69
CDOT Infrastructure
Presentation
Lake Street Reconstruction – Western Avenue to Damen Avenue
08/21/2008 71
Traffic Control and Detour Route
� East of Western Avenue, Lake Street is reduced to one lane in the eastbound direction through the construction zone. Lake Street is currently closed on the west side of Western Avenue and traffic is detoured via Artesian Avenue and Fulton Street.
� Westbound Lake Street traffic is detoured south on Damen Avenue, west on Washington Street, and north on California Avenue.
� Western Avenue is reduced from two lanes in each direction to one lane in each direction at Lake Street.
08/21/2008 72
Sidewalk and paved parkway installation.
New lowered base pavement at Western Avenue.
Lake Street looking east showing the existing
removals and the new roadway and sidewalk.
Lake Street looking east showing the
completed Stage 1 roadway and sidewalk.
08/21/2008 73
Project Scope and Highlights
�The project scope includes the complete reconstruction and lowering of Lake Street to provide additional overhead clearance under the elevated CTA Green Line.
� Work includes the complete replacement of lighting, traffic signals, pavement, catch basins, sidewalks, curb and gutter, ADA ramps and landscaping.
08/21/2008 74
Status Summary� Field work is approximately 30%
complete. The project started in mid-March 2008.
� Stage 1 is generally complete. Roadway removals for the Stage 2 reconstruction of Lake Street have started and the Stage 2 construction on Western Avenue is anticipated to begin on July 31, 2008.
� Current Contract Amount: $4,586,642.80
08/21/2008
75
CDOT Infrastructure
presentation
Michigan Avenue StreetscapeRoosevelt Road to 24th Place
9th Street StreetscapeState Street to Michigan Avenue
08/21/2008 76
Traffic Control
�Michigan Avenue and 9th Street are both fully open to vehicular and pedestrian traffic. There will be isolated closures of the parking lanes over the next month for completion of textured crosswalks, striping and punch list items.
08/21/2008 77
Resurfacing on 24th Street, west of Michigan
Avenue
Resurfacing at Michigan Avenue and
Roosevelt Road
Color application on the textured sidewalk at
14th Street and Michigan Avenue
Imprint of textured sidewalk
08/21/2008 78
Project Scope and Highlights
�Work includes sidewalk replacement, planters with irrigation systems, plantings, trees, reconstruction of vaulted sidewalks, street furnishings, ornamental light poles, resurfacing, striping, textured crosswalks and traffic signal installation at 13th
Street.
08/21/2008 79
Status Summary
�Field work is 95% complete. All paving and bus pad construction is complete. Punch list work will be complete by mid-September 2008.
�Current Estimated Contract Value:
$14.0 million.
08/21/2008 81
Traffic Control
�Michigan Avenue is fully open to vehicular and pedestrian traffic.
�Night closures of the Michigan Avenue Bridge will take place for a three-week period to install steel sheet piles below the bridge in late August.
�Access will be maintained to the cafes, boat tours and Bridge House Museum.
08/21/2008 82
Riverwalk on the west side of the Michigan
Avenue Bridge in front of Bridge House Museum
(Looking east)
Riverwalk on the west side of the Michigan
Avenue Bridge (Looking south)
Boat docks on the east side of the Michigan
Avenue Bridge (Looking east)Riverwalk on the east side of the Michigan
Avenue Bridge (Looking southeast)
08/21/2008 83
Project Scope and Highlights
� The primary task is the construction a 17-foot underbridge to connect the east and west sides of the riverwalk beneath the south end of the Michigan Avenue Bridge.
� Work includes complete reconstruction of the dock wall along the south end of the Chicago River, installation of a steel-frame canopy below the bridge structure, sidewalk construction, new boat ramps, decorative lighting and landscaping.
08/21/2008 84
Status Summary
�Field work has begun with the removal of trees within the project limits and the installation of temporary fence. Construction of the new boat docks will begin the week of August 4th.
�Current Estimated Contract Value:
$8.1 million.
08/21/2008 86
Installation of window frames & tile at west towerInstallation of precast panels at east tower
Painting of west tower structural steel Pouring concrete for warming house floor slab
08/21/2008 87
Project Scope and Highlights
� This project will make the station fully accessible to people with disabilities, and entails many new improvements and amenities including two new elevators to the inbound and outbound platforms connected to the 11th Street Bridge.
� The existing 12th Street Metra Station will remain open to passengers throughout construction. Most work will occur during non-rush hour periods. The existing station and bridge will be removed once the new station is completed.
� All platform foundation, decking, and steel work for Phase 3 work is complete. The west tower steel, walkway, and precast work is complete. The east tower work is ongoing, and installation of the steel windows is 25% complete.
08/21/2008 88
Status Summary
�Field work is 70% complete. The new station will be open to Metra passengers in the late Summer of 2008. All work will be completed in the late Fall of 2008.
�Current Estimated Contract Value: $11.2 million.
08/21/2008
89
CDOT Infrastructure
Presentation
Solidarity Drive Underpass and Museum Campus Circle Drive
08/21/2008 90
Detours
�The existing north bound lanes of Museum Campus Drive and the east bound lanes of Solidarity Drive are closed. All traffic is currently using the south bound and west bound lanes of Museum Campus Drive and Solidarity Drive. There is one traffic lane in each direction and a west bound lane for busses.
08/21/2008 92
Initial excavation for the underpass on the
south side of Solidarity Drive.
Driving H-piles for the footings of the underpass
and retaining walls.
Recycling existing concrete for use as backfill.
Preparation for base course on Museum
Campus Drive.
08/21/2008 93
Project Scope and Highlights
�Work includes the widening and reconstruction of the Burnham Harbor Parking Lot, storm sewer installation and partial reconstruction of Museum Campus Drive and the installation of an underpass under Solidarity Drive. The underpass will allow pedestrians and bikers to safely cross Solidarity Drive without crossing or impeding traffic.
08/21/2008 94
Status Summary� Field work is approximately 23% complete. The
excavation for the first phase of the underpass installation is complete. The installation of the piling has begun and it is scheduled to be complete during the week of August 4, 2008. The construction of the retaining walls and the installation of the 3-sided precast underpass structure will follow.
� Current Contract Amount: $13,440,034.14