17
v Brussels Conference 12-13 March 2014 -1- CIGRE BELGIUM 2014 Conference ACTIVELY MANAGING DISTRIBUTION CONNECTED GENERATION FEEDING INTO DISTRIBUTION AND TRANSMISSION CONTRAINTS Session 1B / R Anderson & A Gooding / United Kingdom

CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

Embed Size (px)

DESCRIPTION

Joint presentation with SP Energy Networks (SPEN) at CIGRE conference, Belgium, with the full title, "Actively Managing Distribution Connected Generation Feeding Into Distribution and Transmission Constraints". The presentation used SPEN's Accelerating Renewable Connections project as a case study and looked at the implementation of an Active Network Management scheme supplied by Smarter Grid Solutions. The conference theme was "Innovation for secure and efficient transmission grids".

Citation preview

Page 1: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 1 -

CIG

RE B

ELG

IUM

20

14

Confe

rence

ACTIVELY MANAGING

DISTRIBUTION CONNECTED

GENERATION FEEDING INTO

DISTRIBUTION AND

TRANSMISSION CONTRAINTS

Session 1B / R Anderson & A Gooding /

United Kingdom

Page 2: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 2 -

CIG

RE B

ELG

IUM

20

14

Confe

rence Iberdrola at a Glance

Presence in 40 countries worldwide

Page 3: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 3 -

CIG

RE B

ELG

IUM

20

14

Confe

rence SP Energy Networks Overview

• Distribution Assets

- 3.5m connected customers

- 16% of annual electricity bill

- Host 28% of UK’s distributed

renewable generation but

only 14% of customer base

• Transmission Assets

(Scotland)

- 4% of annual electricity bill

- 56% of Scotland’s

transmission connected

renewable generation

Page 4: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 4 -

CIG

RE B

ELG

IUM

20

14

Confe

rence Agenda

• Background

• The Problem

• The Solution

Page 6: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 6 -

CIG

RE B

ELG

IUM

20

14

Confe

rence Problem

Page 7: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 7 -

CIG

RE B

ELG

IUM

20

14

Confe

rence The Problem

• Exporting Grid Supply Point

• Multiple issues during N-1 Contingencies

• High cost connection charges as a consequence of thermal

constraints

• High cost connection charges as a consequence of voltage

rise constraints

• The impact of Small Scale Generation on the Exporting GSP

Page 8: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 8 -

CIG

RE B

ELG

IUM

20

14

Confe

rence

60 MVA

Limit

Firm Capacity Calculated based upon Maximum Generation / Minimum Demand

Managing Constraints at GSP

120 MVA

Limit

62 MW

Unconstrained

Grid Supply

Point

132kV

33kV

Transmission

Network

Distribution

Network

Demand

Min 10 MW –

Max 36 MW

Max

Generation

Min Demand Network

Capacity

Available

Capacity

Fully Intact 110 MVA 10 MVA 120 MVA + 20 MVA

N-1 110 MVA 10 MVA 60 MVA - 40 MVA

48 MW

Constrained

9 MW

ANM

Controlled

27 MW

ANM

Controlled

Page 9: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 9 -

CIG

RE B

ELG

IUM

20

14

Confe

rence Managing Constraints at GSP

Connection Transmission Reinforcement Cost Estimate - £20M

Connection Date beyond 2020

Both New Sites Have Planning!

62 MW

Unconstrained

Transmission

Network

Demand

Min 10 MW – Max

36 MW

120 MVA

Limit90MVA90MVA

48 MW

Constrained

9 MW

ANM Controlled

27 MW

ANM Controlled

Page 10: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 10 -

CIG

RE B

ELG

IUM

20

14

Confe

rence The Solution

• Accelerating Renewable Connections

www.arc-project.com

• £8.4M project funded through the Low Carbon Network Fund

managed by OFGEM

• Project Partners

Page 11: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 11 -

CIG

RE B

ELG

IUM

20

14

Confe

rence The Solution

Page 12: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 12 -

CIG

RE B

ELG

IUM

20

14

Confe

rence The Solution

Requirements for an Actively Managed Network:

• Operate autonomously

• Hard real time

• End to end determinism

• State driven logic

• Constant idling rather then event initiated

• Predictable and repeatedly able to handle relationships

between multiple devices and multiple constraints

Page 13: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 13 -

CIG

RE B

ELG

IUM

20

14

Confe

rence The Solution – A New Layer

Page 14: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 14 -

CIG

RE B

ELG

IUM

20

14

Confe

rence The Solution – Top Down ANM

132/33kV

60MVA

132/33kV

60MVA

Wind Farm 1

62.5 MW

33/11kV

7.5MVA

33/11kV

7.5MVA

5 MW 22.5 MWWind Farm 2

48 MW 33/11kV33/11kV

Wind Farm 3

9 MW

Energy From Waste Plant

3 3

3

MP1 MP2

MP3

MP4 = MP1 + MP2

Existing Communications

8.5 MW

Page 15: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 15 -

CIG

RE B

ELG

IUM

20

14

Confe

rence The Solution

Commercial Arrangements:

• Non-Firm connection agreements

- Estimation of annual curtailment

- No compensation for curtailment (Up front benefit banked!)

• Managing constraints across boundaries

- Agreement with the TNO and TSO to manage constraints

created by distribution connected generation

• Investigating new community connection to encourage local

demand or storage interaction

Page 16: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 16 -

CIG

RE B

ELG

IUM

20

14

Confe

rence The Solution

Page 17: CIGRE Belgium presentation on Actively Managing Distribution Connected Generation

v

Brussels Conference 12-13 March 2014 - 17 -

CIG

RE B

ELG

IUM

20

14

Confe

rence The Solution

Thank You

Alan Gooding

Commercial Director, Smarter Grid Solutions

www.smartergridsolutions.com

Ross Anderson

Senior Design Engineer, SP Energy Networks

www.spenergynetworks.co.uk