37
Utility Plant Upgrade with Redundant, PlantPAx Platform Tom Brown – Program Manager, Banks Integration Group, Inc. June 8, 2016

Central Process Utility Plant controls upgrade required 100% uptime

Embed Size (px)

Citation preview

Page 1: Central Process Utility Plant controls upgrade required 100% uptime

Utility Plant Upgradewith Redundant, PlantPAx Platform

Tom Brown – Program Manager, Banks Integration Group, Inc.June 8, 2016

Page 2: Central Process Utility Plant controls upgrade required 100% uptime

Agenda

Lessons Learned

System Design

System Selection Process

Project Overview

Page 3: Central Process Utility Plant controls upgrade required 100% uptime

Banks Integration Group Background

Who is Banks Integration Group?

Rockwell Automation Solution Partner

Focus on Process Automation primarily in Life Sciences

Located in Northern California – Servicing the West Coast

Page 4: Central Process Utility Plant controls upgrade required 100% uptime

Project Overview

Central Process Utility Plant – CPUP

Refrigerated Water(5) Chillers

(6) Cooling TowersCompressed Air

(4) 300 HP Compressors

Page 5: Central Process Utility Plant controls upgrade required 100% uptime

Control System Upgrade Justification Mixed I/O between RW and CA systems

Obsolete PLC and HMI Hardware with numerous code issues Winview HMI platform on desktop PCs with PLC-5® controllers Dead code and legacy configuration still on system due to difficulty of

making changes to existing system

No remote access or individual user logins

DH+ communication bandwidth issues

Controllers/Racks in with 480V power on compressors or MCC’s

Page 6: Central Process Utility Plant controls upgrade required 100% uptime

Original Control System Architecture

Hardware 2 Allen-Bradley ® 5/80 PLC’s shared between the RW/CA systems 4 Allen-Bradley SLC PLC’s, one per compressor 2 HMI Stations shared between buildings

Software RSLogix™ 5, RSLogix 500 Winview HMI Software

Network 3 DH+ networks spanning several buildings

1 SCADA and Inter-Processor Communications Network 2 Remote I/O Networks with a Modbus Interface

NO

REDUNDANCY

Page 7: Central Process Utility Plant controls upgrade required 100% uptime

Project Challenges

The control system is large and spread across many buildings Project impacted 22 control panels (either new or existing) required

the upgrade of 7 VFDs

100% uptime on all utilities throughout the upgrade

Existing process equipment had a large number of existing failures

Large number of drawings and documents

Page 8: Central Process Utility Plant controls upgrade required 100% uptime

Project Challenges

Desire to use new technologies Server Virtualization Pre- tested control modules – Process Objects for Life Science Ethernet/IP (DLR) instead of existing campus ControlNet standard

Page 9: Central Process Utility Plant controls upgrade required 100% uptime

Agenda

Lessons Learned

System Design

System Selection Process

Project Overview

Page 10: Central Process Utility Plant controls upgrade required 100% uptime

System Selection

Client specified a Rockwell Automation Control System

Two Pre-design studies were completed to select the best approach for the upgrade

PlantPAx® for Life Science Study Network Comparison Study

Page 11: Central Process Utility Plant controls upgrade required 100% uptime

PlantPAx for Life Science Study

Study Objective Evaluate if PlantPAx Process Objects were a “good fit” for the utilities

upgrade Are they robust? Are they modular? Do they increase visibility and ease of troubleshooting?

Banks Integration Group gave an interactive presentation discussing the advantages and disadvantages of the Process Objects

Page 12: Central Process Utility Plant controls upgrade required 100% uptime

PlantPax for Life Science

Rockwell Automation Library – “Out of the Box”

Page 13: Central Process Utility Plant controls upgrade required 100% uptime

Advantages of PlantPAx for Life Science Solution

Aligned with S88.01 Batch Control Standard Able to divide equipment by Area and Unit

Decreased programming and validation cost Modules are preprogrammed and customized for the life sciences Modules are pre-tested by Rockwell

Increased system visibility PlantPAx built-in displays give operations the ability to more easily

troubleshoot abnormal conditions

Page 14: Central Process Utility Plant controls upgrade required 100% uptime

Process Objects for Life Science Benefits

Pre-programmed modules

Page 15: Central Process Utility Plant controls upgrade required 100% uptime

Process Objects for Life Science Benefits

Pre-validated following GAMP Life Cycle Model

Page 16: Central Process Utility Plant controls upgrade required 100% uptime

Process Objects for Life Science Benefits

Increased visibility

Page 17: Central Process Utility Plant controls upgrade required 100% uptime

Process Objects for Life Science Benefits

Reusable Global Object Library

Page 18: Central Process Utility Plant controls upgrade required 100% uptime

Process Objects for Life Science Benefits

Page 19: Central Process Utility Plant controls upgrade required 100% uptime

Disadvantages of PlantPAx for Life Science Solution

With flexibility comes increased complexity Each module is designed to accommodate several device

configurations, which leads to a more complicated configuration

Module PLC code is locked

PlantPAx Process Objects for Life Science is licensed per PLC

Faceplates were more complicated than existing design

Page 20: Central Process Utility Plant controls upgrade required 100% uptime

Network Comparison Study

Collaborated with Rockwell Automation Network & Security Services

Network Study Objective Evaluate control system network technologies for:

Peer-to-peer communications I/O Communications

Scope Deliverables Merits and disadvantages of EtherNet/IP and ControlNet Network diagrams and design Network Calculations Summary and recommendation

Page 21: Central Process Utility Plant controls upgrade required 100% uptime

Network Calculations – ControlNet

Network Bandwidth Calculation – 16.5% Utilization

Page 22: Central Process Utility Plant controls upgrade required 100% uptime

Network Calculations – EtherNet/IP

Network Bridge Module is the bottleneck – 17.9% Utilization

Page 23: Central Process Utility Plant controls upgrade required 100% uptime

Ultimately Chose EtherNet/IP

EtherNet/IP with a Device Level Ring topology

Three networks created based on equipment Refrigerated Water Compressed Air Shared Equipment

Fiber media used in segments connecting buildings or distances greater than 300 ft.

Page 24: Central Process Utility Plant controls upgrade required 100% uptime

DLR Design

Page 25: Central Process Utility Plant controls upgrade required 100% uptime

DLR Diagnostics

Status screen created for each network

Page 26: Central Process Utility Plant controls upgrade required 100% uptime

Agenda

Lessons Learned

System Design

System Selection Process

Project Overview

Page 27: Central Process Utility Plant controls upgrade required 100% uptime

System Design

Page 28: Central Process Utility Plant controls upgrade required 100% uptime

System Design

Page 29: Central Process Utility Plant controls upgrade required 100% uptime

SCADA Architecture

Page 30: Central Process Utility Plant controls upgrade required 100% uptime

SCADA Components

Virtual servers hosted on an HP blade server system

Wyse Thin Clients Wyse ThinOS, based on Linux

platform Touch screen OIT’s

Page 31: Central Process Utility Plant controls upgrade required 100% uptime

New Control System Architecture

Hardware 2 Redundant ControlLogix® L73 processors for the RW system 1 ControlLogix L72 processor for the CA Supervisor system 4 ControlLogix L72 processors, one per compressor 6 HMI Client Stations distributed between 3 buildings RW and CA I/O is completely segregated

Software RSLogix 5000, v20.03 FactoryTalk View SE, v7.00.00

Network All PLC’s now on Automation Network 3 Device Level Rings (DLR’s) used for Remote I/O and VFD’s

Page 32: Central Process Utility Plant controls upgrade required 100% uptime

PlantPAx Simplified the System

Existing System PLC code - 5000 rungs HMI - 1050 graphics Electrical Drawings - 400

Updated System PLC code – 2000 rungs HMI – 143 graphics

77 Process Object graphics 66 Custom graphics

Electrical Drawings - 450

Page 33: Central Process Utility Plant controls upgrade required 100% uptime

System Features

Remote Interface Remote connections via Terminal Server View only connection via FactoryTalk® Viewpoint

System Redundancy SCADA Servers, PLC’s, Network Power Supplies

Network and Power Supply Diagnostics

Node Based Security

Ethernet VFD’s providing increased visibility for troubleshooting

Page 34: Central Process Utility Plant controls upgrade required 100% uptime

Agenda

Lessons Learned

System Design

System Selection Process

Project Overview

Page 35: Central Process Utility Plant controls upgrade required 100% uptime

Lessons Learned

As-Built existing design documents prior to starting detailed design

Graphic Standards for Common Plant Interface

VM’s allowed for easy “on-site” migration

Working with local Electrical Subcontractor eased installation

Page 36: Central Process Utility Plant controls upgrade required 100% uptime

Lessons Learned

Executing a DLR Hardware FAT reduced startup time

Page 37: Central Process Utility Plant controls upgrade required 100% uptime

Questions

Tom Brown – Program Manager, Banks Integration Group, Inc.June 8, 2016