1EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
WRONSKI MEDICAL DEVICESBI REPORTING
PERMISSION TO DEPLOY
TEAM B-RED
2EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
MEET THE TEAM
Corey Horohoe Niamh Crowley
Michelle Ly Peter Shipman
3EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
• The Business - Corey• Problem and Solution - Michelle• Business Needs - Michelle• Process Maps - Peter• Project Timeline/Status Update - Peter• Demo• Status Against Plan – Michelle/Corey• Risk Analysis - Niamh• Roll-Out Plan – Niamh• Wrap Up - Niamh
AGENDA
4EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
THE BUSINESSBACKGROUND, PROBLEMS, SOLUTIONS
5EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
• Produces products used by health care professionals
• Main customers• Hospitals• Patient Clinics• Dental Surgical Centers• Medical Emergency Centers
WRONSKI MEDICAL DEVICESBUSINESS BACKGROUND
Corey
6EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
PROBLEM AND SOLUTIONUnusable reports
Non Value
Adding Reports
5% Error Rate
Long Cycle Time
Reports are
Costly
Reports that addresses current business problems
One dashboard with standard reports for entire company
Reports are refreshed daily
Resources are redistributed to value adding roles
Predictive modeling and forecasting reports
Michelle
7EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
BUSINESS NEEDS
Increase percentage of
SLA met
Equipment Services
Increase inventory turnover
Inventory
Profitability by Product
Sales
Collect $80m owed
Finance
8EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
AS-IS ANDTO-BE PROCESS
MAPS
9EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
AS-IS PROCESSIdentify
problem
Determine report
requirements
Request report
Gather data from recording systems
Manual data reconciliation Formatting Email
Business system
data
Review
Is itAccurate?
End
No
YesMan
agem
ent
Anal
ysts
Busin
ess S
yste
ms
2 day 7 day 10 day 1 day
20 days
Peter
10EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
TO-BE PROCESS
Manager identifies needs
Check report catalog for required
information
Use report catalog to
analyze dataEnd
Analysts Generate New
Report
Update report catalog
Report not
available
1 day
Report not
available
*Generating new reports may take a maximum of 2 days
11EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
PROJECT TIMELINE
12EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
PROJECT TIMELINEMarch April May June July Aug Sep Oct
Sprint 3
Sprint 4
Sprint 5
Sprint 6
Sprint 7
InitiationPlanning Data Staging
Development
Sprint 2
Star Schema Build for Departments
Deploy
Deploy
Deploy
Deploy
Deploy
Deploy
KeySprint 2: Mission CriticalSprint 3: HighSprint 4: Above AverageSprint 5: NormalSprint 6: Below NormalSprint 7: Low
2014 Calendar Year
Peter
13EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
BI REPORTING TOOLEquipment Services Inventory Sales Finance
Inventory Turnover
Service Order Demand Estimate
Target ListSLA
Percentage Globally
Yearly Equipment
Failure
Engineer surplus/deficit
Future Failing Devices
Order to Pipeline
A/R Collection Period
Products Returned
Sales Profitability
Order to Remittance
Orders Fulfilled
Order to Ship Profitability by Region
Profitability by Modality
14EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
STATUS AGAINST PLANUPDATE ON FINANCIALS
15EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
Project Expense Capital Expenditure Allocated Spent
Hardware $ 648,000 $ 648,000 Staff $ 374,125 $ 357,666
PM*, Business/Finance Manager*, Development Programmers, Testers*, IT Analysts, DBA
One-Time ExpenseStaff $ 110,833 $ 110,833
PM, Business/Finance Manager, Development Programmers, Training
Total Expense $ 1,132,958 $ 1,116,499
PROJECT INVESTMENT STATUS
Key AssumptionsProject Manager, Financial/Business Manager, and Testers will still be place 2 weeks after final deploymentDesign, construct, validate phase is 4.5 months and can be capitalizedInitiation and definition phase is 2 months and is a one-time expense90% of allocated funding has been used
Michelle
16EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
OPERATING COSTS
Key AssumptionsProject lead is owner of system after complete deployment, decreases year-over-year due to user adoptionHelp desk is offshore and contracted at a cap of $15,000 a year, available internationally, 24/7 around the clockUsers will gradually adopt system
Corey
17EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
COST BENEFIT ANALYSIS
Key AssumptionsRate of adoption are assumedProject benefits are delta of old system
NPV(@15% WACC): $21,605,903 IRR: 227%
18EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
RISK ANALYSIS
19EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
Deliverable/Event Potential RiskAnd Impact Actions Recommended
Users stop using product
No value add, wasted resources
Highlight key benefits, Communication plan, system champion
Users don't understand product
Produce faulty data, reduce value impact
Demo and training
System crashes System unavailable
Backup servers, Uninterruptable power supply (UPS)
Loss of connectivity to data providers (i.e. Oracle changed to SAP)
Unusable data, unavailability from systems
Change management, ETL response team
RISK ANALYSIS (FMEA)
*Failure Mode Effect Analysis
Niamh
20EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
ROLL-OUT STRATEGY
21EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
Change Management•Change agent for each department•Weekly Status Meetings
Documentation•ETL/Migration Plan •Operation Data•User documentation
UAT•Testing Groups•Provide a test plan (Bugs Found – Defect Resolution)
Training and Support•Three one hour live sessions – Beginner – Intermediate –Advanced•Recordings of training sessions (For new employees joining organization)
ROLL-OUT STRATEGYNiamh
22EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
WRAP UP
Quicker Process
Reduction in error
rate
Customer satisfactio
n
Cumulative benefits
$40 million
23EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
APPENDIXCOSTS, MILESTONE ETC.
24EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
Data Staging
areaEMC Oracle
Server
SAP
Sales
Finance
Services
ETL
ETL
ETL
ETL
ETL
Star Schema
EMC Oracle Server
Tableau
EMC BI Server
Equipment Vitals, SLA response time,
Inventory Turnover…
Hadoop
TECHNICAL SOLUTION
25EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
CAPITAL EXPENDITURES
Key AssumptionsProject duration is approximately 6.5 months10 Servers –4 Development, 3 Testing, 3 Production and BackupProject Manager and Business Analyst are working full time on projectDesign, construct, validate phase is 4.5 monthsInitiation and definition phase is 2 months
Capital Basis Year 1 Year 2 Year 3 Year 4 Year 5 TotalHardware
BI Server $4000/month, 3 servers 28,800$ 28,800$ 28,800$ 28,800$ 28,800$ 144,000$ Oracle Server $6000/month, 7 servers 100,800$ 100,800$ 100,800$ 100,800$ 100,800$ 504,000$
StaffProject Manager $100,000, 4.5 months 7,500$ 7,500$ 7,500$ 7,500$ 7,500$ 37,500$ Business/Financial Analysts $70,000, 4.5 months 5,250$ 5,250$ 5,250$ 5,250$ 5,250$ 26,250$
Development Programmers1 Programmer, $35/hr x 4.5 months 7,280$ 7,280$ 7,280$ 7,280$ 7,280$ 36,400$
Testers3 testers x $75,000 salary, 4.5 months 16,875$ 16,875$ 16,875$ 16,875$ 16,875$ 84,375$
IT Analysts2 analysts x $80,000 salary, 4.5 months 12,000$ 12,000$ 12,000$ 12,000$ 12,000$ 60,000$
Database Admin 4 admin, $45/hr, 4.5 months 25,920$ 25,920$ 25,920$ 25,920$ 25,920$ 129,600$ Total Capital Costs 1,022,125$
26EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
ONE TIME COSTSProject Expense (One-time Expense)Staff
Project Manager $100,000, 2 months 16,667$ Business/Financial Analysts $70,000, 2 months 11,667$ Development Programmers 5 programmers, $35/hr, 2 months 56,000$ Training Implementation, marketing, rollout 26,500$
Total Expense 110,833$
27EMC CONFIDENTIAL—INTERNAL USE ONLYEMC CONFIDENTIAL—INTERNAL USE ONLY
RISK REGISTER (FULL)Deliverable/Event Potential Risk and Impact I L D R (I*L*D) Actions Recommended I L D RBusiness
Lack of support from stakeholders
Failure to complete project, failure to change current process, no-value added solution to fix current process 8 2 5 80
Consistent communication, highlight benefits 5 1 2 10
Users stop using product No value add, wasted resources 8 4 7 224
Highlight key benefits ,Communication plan, system champion 8 2 4 64
Users don't understand product Produce faulty data, reduce value impact 5 7 7 245Demo and training 4 3 4 48Change/added requirements Impact delieverables , delay rollout 6 6 3 108Clear project scope 2 2 2 8
Project Reduction of funding Impact delieverables 8 5 4 160Adjust delieverable date 3 5 2 30
Loss of SMEs Project stall, delay rollout 7 4 3 84
Cross train and select team so we don't rely on a single SME 4 4 3 48
Produce reports with no value Negatively impact decisions 7 4 7 196Training, retain analysts for validation 7 2 3 42
Overbudget (scheduling and resources) Project failure/reassess 8 5 5 200Project management tools 6 2 3 36Enhancements/Changes to system
Reallocation of resources, downtime, miscommunication 7 7 6 294Change management 5 4 5 100
Technology
System crashes System unavailable 9 3 3 81
Backup servers, Uninerruptable power supply (UPS) 9 2 2 36
System providers change (i.e. update to data input)
Unusable data, unavailability from systems 9 5 7 315
Change management, ETL response team 5 4 4 80
Security ThreatLoss of intellectual property, company reputation, data tampering 5 3 7 105
server hardening, data validation, security audit 5 1 4 20
Outages Inaccurate reports 7 3 7 147Change management 7 1 4 28TOTAL 2239 TOTAL 550