36
2012 End User Seminar Fieldbus Foundation © 1994 – 2012 Fieldbus Foundation 1 Field-based Control : Freedom to Choose the Ultimate DCS John Rezabek Process Control Specialist Ashland, Inc.

Benefits of foundation in the operational phase

Embed Size (px)

DESCRIPTION

John Rezabek Presentation from our North American Seminars

Citation preview

Page 1: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation1

Field-based Control : Freedom to Choose the Ultimate DCS

John Rezabek

Process Control Specialist

Ashland, Inc.

Page 2: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation2

What is Fieldbus Again?

• Fieldbus is a communication protocol, right?

• The “OSI Model”: Seven Layers for “Open Systems Interconnection”

• Foundation fieldbus uniquely adds the “User Layer” – why?

Physical Layer

Data Link Layer

Network Layer

Transport Layer

Session Layer

Presentation Layer

Application Layer

USER LAYER

Page 3: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation3

Why Have a “User Layer”?

• Analog In, Analog Out, Digital In, Digital Out• Do some scaling, linearization, filtering, configure fault

states & propagation, etc. outside the host / DCS• Devices are “peers” with the host’s interface

• ARTHM, ISEL, SGCR, INT• Relieve the HOST DCS of some compensation,

characterization, totalizers, etc.

• PID, CSEL, SPLTR• Configure CONTROL IN FIELD DEVICES, using the

world’s only vendor-independent totally distributed digital control system

Page 4: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation4

Why “Distributed” Control?

• 1980’s costs for CPU and memory meant many loops-per-controller for reasonable “cost per loop”

• Users of the day wanted “single loop integrity” = one fault > loose no more than one loop

• Controller, I/O, and Network Redundancy• Commercial model became “functionally”

distributed

Page 5: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation5

The Need For Reliability

ARC Insight

10th June 2010

The global process industry loses $20billion, or five percent of annual production, due

to unscheduled downtime and poor quality.

ARC estimates that almost 80 percent of these losses are preventable, with 40 percent largely

due to operator error.

Page 6: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation6

Fieldbus = Truly Distributed Control

• Foundation Fieldbus allows return to true single-loop integrity

• Robust control independent of DCS, needs only power, devices, and schedule (“LAS”)

• Intelligence of devices is exploited, employing signal status, diagnostics

• But – is it truly more reliable?

Page 7: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation7

Fewer Components = Longer MTBF

PSU

PSU

AND Foundation fieldbus also communicates signal status with every scan, which enables smart mode shedding, bumpless transfer and initialization.

Page 8: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation8

Digital All the Way- Digital Closed Loop Control

Fieldbus eliminates the analog signal

Validity:Good/Bad/Uncertain

Initiate Fault-State Command

Limited: High/LowBumpless TransferWindup ProtectionFault-state Status

Designed for process control

Default behavior on Bad or Uncertain PV is shed mode to MAN and hold last output – the same macrocycle the fault is detected.

Page 9: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation9

Process Variable Validity

Hardwired Device drives current <4

mA or >20 mA on device failure

– Looks like process problem PID counteracts thus

tripping the loop Operator cannot tell the

difference between a process alarm and a device alarm

Fieldbus Device health indicated by

associated status Controller holds last

position on device failure– Shutdown is optional

Operator can easily distinguish process problem from a device problem

Page 10: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation10

FF – A Standard for High Availability

Distributed Control, Speed, & Determinism Real-time value and status Status Propagation (CIF & CIC) Validated information

Quality and limits Windup protection Bumpless transfer for valves Fault-state for valves etc.

Page 11: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation11

SIL - Putting a Number on Reliability

• Ed Marszal, ISA 84.001 and IEC 61508 expert, author and president of Kenexis consultants

• Entered reliability numbers into reliability models for safety system calculations

• “ FF is significantly better – MTTF (mean time to fail) of 48.2 [years] versus MTTF of 15.9 [years]”

Page 12: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation12

Reliability

Analogue

With CIF

15.9y

48.2y

MTTF

Page 13: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation13

Customer Experience

CIF enabled

Page 14: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation14

Customer Experience

FOUNDATION FieldbusCIF with inherent backup capability

prevented 2 incorrect plant shutdowns, which would have resulted from communication

interruptions.

Page 15: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation15

But . . . Isn’t Fieldbus “Slow”?

• Early devices had longer function block execution times

• Many early jobs used FF for IO only• Host PID to FF Macrocycle sync is not easily

addressed – oversample?• Variable latencies, overly busy segments• Add commissioning, diagnostics, downloads• = Many bogged down segments

Page 16: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation16

Control In The Field Study

Control in the Field:

Analysis of Performance Benefits

Page 17: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation17

Comparison

CIF enabled

No CIF

125

625

105

ms

Page 18: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation18

Settling Times: Fastest Process

50

54

58

62

Process output (%)

0 4 8 12 16 20Time (seconds)

60%

Setpoint Case 1 - CIFCase 3 - Control in DCS (async)

Page 19: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation19

Settling Times: Very Fast Process

50

54

58

62

Process output (%)

0 4 8 12 16 20Time (seconds)

Setpoint Case 1 - CIFCase 3 - Control in DCS (async)

55%

Page 20: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation20

Settling Times: Fast Process

50

54

58

62

Process output (%)

0 4 8 12 16 20Time (seconds)

Setpoint Case 1 - CIFCase 3 - Control in DCS (async)

66%

Page 21: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation21

Settling Times: Medium Process

50

54

58

62

Process output (%)

0 4 8 12 16 20Time (seconds)

Setpoint Case 1 - CIFCase 3 - Control in DCS (async)

39%

Page 22: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation22

Presence Of Disturbance: Fastest Process

Process output (%)

40 50 60 70 80 90 100Time (seconds)

Setpoint Case 1 - CIFCase 3 - Control in DCS (async)

56

58

60

66

62

64

Page 23: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation23

Presence Of Disturbance: Different Processes

Fastest1.811

2.132

0.517

0.82

0.642

1.058

0.231

0.53

65% better

50% better

55% better

35% better

Very Fast

Fast

Medium

Setpoint CIF1.811 control in

DCS (async)

Page 24: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation24

ISC Study on Control in the Field

“Control in the field: analysis of performance benefits” study from ISC (industrial systems and control)

40-60% faster settling time on setpoint change

30-50% better disturbance rejection

Most significant for fast processes (flow and pressure)

Page 25: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation25

Impact of Tighter Control Loop

Manual

PneumaticAnalogue

Digital

Control limit

Page 26: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation26

Recommended For Fast Loop Response

Control in the field usingFOUNDATION fieldbus technology is

recommended by SGSI for simple and cascading loops, not for complex loops.

Major benefits identified by SGSI are reduced process controller loading, reduced network traffic enabling more loops per segment, as

well as very fast loop response.

Page 27: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation27

Empirical Studies: CIF Fast as 4-20

Host

Host

Host

Host

Study by Daugherty, Coughran, and Ford, “Effects of Macrocycle Time and Sampling Rates on Control Loop Performance”

Page 28: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation28

8 simple loops, CIC

Study by Daugherty, Coughran, and Ford, “Effects of Macrocycle Time and Sampling Rates on Control Loop Performance”

Page 29: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation29

Same 8 loops, CIF (valve positioner)

Study by Daugherty, Coughran, and Ford, “Effects of Macrocycle Time and Sampling Rates on Control Loop Performance”

Page 30: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation32

Blower – Combustion Air to Boiler

• Keeping the Blower out of the surge region means a more stable flow

• More stable flow allows running closer to constraints

• Running closer to constraints means less fuel, CO2

AIR TO BOILER

AIR BLOWERPREHEATER

TO

BU

RN

ER

S

Page 31: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation33

Inside “peak pressure” line, flow is unstableInside “peak pressure” line, flow is unstable

Peak Pressure

Desired Flow fell here

Page 32: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation34

Field-based control of blow-off valveField-based control of blow-off valve

• Controls total flow• Allows operation

close to low-flow BMS trip point

• Saves fuel costs and reduces CO2 emissions

Page 33: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation35

Surge Control SchemeSurge Control Scheme

Blow-off Flow

Flow to Burner

FICInlet

Louvers

Σ FIC(Total Flow)

Blow-off Valve

Discharge Pressure SGCR SP

PT (Discharge)

FT1

FT2

Blow-off Valve Pos.

Inlet Louver Positioner

Page 34: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation36

Blower Anti-surge schemeBlower Anti-surge schemeFlow to Burner

Total Flow Setpoint

Total Flow Controller

Page 35: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation38

10,000 HP Turbine / Blower Anti-surge10,000 HP Turbine / Blower Anti-surge• Large critical

un-spared asset

• Typically runs at 5000 to 7000 RPM

• Expensive to repair; lost production even more expensive

Page 36: Benefits of foundation in the operational phase

2012 End User SeminarFieldbus Foundation

© 1994 – 2012 Fieldbus Foundation44

Summary• FF was specified & designed to deliver

robust control by default – STANDARDIZED across suppliers

• Control in Field Devices is being used in critical process applications with fast cycle time requirements

• Modern devices are executing function blocks faster than ever • (note: like cars, there are Yugos and Porches, so

choose according to your needs)