Bathurst Station Preliminary Design Bathurst Station Preliminary Design Open House #1 11/28/2011 Open House #1 November 28, 2011

Bathurst Station Preliminary Design Consultation

Embed Size (px)

DESCRIPTION

Station design is one of the most exciting -- and most critical -- components of The Crosstown construction. There are a number of major considerations for station design, including: accessibility for people with disabilities, development potential, integration with surrounding communities, and minimizing construction impacts. Visit www.thecrosstown.ca for more information about The Crosstown.

Citation preview

Page 1: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Bathurst StationPreliminary Design

Open House #1November 28, 2011

11/28/2011

Open House #1November 28, 2011

Page 2: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

11/28/2011 2Bathurst Station - Preliminary Design Overview

Page 3: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Part 1• Introduction• Crosstown Update• Station Design 101 - Design Principles

Part 2•Bathurst Station Preliminary Design

*Our partners in City Planning are here if you have questionsabout existing development requirements in the Bathurst areaor the future Land Use Study around Crosstown Stations

Open House Overview

3

Part 1• Introduction• Crosstown Update• Station Design 101 - Design Principles

Part 2•Bathurst Station Preliminary Design

*Our partners in City Planning are here if you have questionsabout existing development requirements in the Bathurst areaor the future Land Use Study around Crosstown Stations

11/28/2011 3Bathurst Station - Preliminary Design Overview

Page 4: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

The Purpose of Tonight’s Open House• Provide a brief Crosstown project update• Present the Crosstown station design philosophy• Explain the anatomy of the station components and challenges• Display the preliminary design of Bathurst StationMost importantly:

*Get your input on the Preliminary Design early in this process.

• The architectural design will be prepared for Open House #2 inSpring 2012. Significant outreach will follow on construction.

• Walls at the future station box are scheduled to begin at Bathurst in2013 as part of the tunnelling process.

• Bathurst Station construction is scheduled to begin in 2014.

• Provide a brief Crosstown project update• Present the Crosstown station design philosophy• Explain the anatomy of the station components and challenges• Display the preliminary design of Bathurst StationMost importantly:

*Get your input on the Preliminary Design early in this process.

• The architectural design will be prepared for Open House #2 inSpring 2012. Significant outreach will follow on construction.

• Walls at the future station box are scheduled to begin at Bathurst in2013 as part of the tunnelling process.

• Bathurst Station construction is scheduled to begin in 2014.

11/28/2011 Bathurst Station - Preliminary Design Overview 4

Page 5: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

11/28/2011 5Bathurst Station - Preliminary Design Overview

Page 6: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Format for Feedback• Please speak with the project team at the displays, we’re here to answer your

questions

• There are tables to write comments and for group discussions

• Please submit a feedback form tonight if possible , or send us commentsvia e-mail, mail, or online at www.thecrosstown.ca by December 12, 2011

• A consultation report to inform the designers will be posted online at:www.thecrosstown.ca

• Please speak with the project team at the displays, we’re here to answer yourquestions

• There are tables to write comments and for group discussions

• Please submit a feedback form tonight if possible , or send us commentsvia e-mail, mail, or online at www.thecrosstown.ca by December 12, 2011

• A consultation report to inform the designers will be posted online at:www.thecrosstown.ca

11/28/2011 Bathurst Station - Preliminary Design Overview 6

Page 7: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

* Final number and location of stations subject to review

11/28/2011 Bathurst Station - Preliminary Design Overview 7

Page 8: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

The Eglinton-Scarborough Crosstown Plan• $8.4 billion transit investment from the Province of Ontario through Metrolinx

• 25 km east-west transit corridor between Black Creek Drive and ScarboroughCentre

• 60% faster than bus service today (e.g. only 15 minutes from Keele to Yonge)

• 19 km underground tunnel (Black Creek Drive to Kennedy Station)*

• 6km seamless service will replace the SRT from Kennedy Station to ScarboroughCentre

• Up to 26 stations

*Exact alignment west of Keele Street and east of Laird Drive TBD

11/28/2011 Bathurst Station - Preliminary Design Overview 8

• $8.4 billion transit investment from the Province of Ontario through Metrolinx

• 25 km east-west transit corridor between Black Creek Drive and ScarboroughCentre

• 60% faster than bus service today (e.g. only 15 minutes from Keele to Yonge)

• 19 km underground tunnel (Black Creek Drive to Kennedy Station)*

• 6km seamless service will replace the SRT from Kennedy Station to ScarboroughCentre

• Up to 26 stations

*Exact alignment west of Keele Street and east of Laird Drive TBD

Page 9: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

First Construction Contract• Tunnel launch site preparation is underway atKeelesdale Park (between Black Creek Drive and Keele Street)

• Tunnelling will start in summer 2012 and head east

11/28/2011 Bathurst Station - Preliminary Design Overview 9

Page 10: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Crosstown Construction Update

11/28/2011 Bathurst Station - Preliminary Design Overview 10

Crosstown tunnel preparation work at Black Creek and Eglinton in Keelesdale Park Piling rigs are building concrete support walls for the future tunnel launch shaft The shaft will enable tunnelling eastward in summer 2012 Soil testing for the tunnel and stations continues from Keele Street to Kennedy Station in Scarborough

Page 11: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Conceptual Design of a Crosstown Station

Urban Design and Architectural Guidelineshave been developed:

• ensure positive change along thecorridor

• guide individual station designs andachieve consistency

• guide configuration of surfaceelements

• integrate surface elements withexisting and future development

11/28/2011 11Bathurst Station - Preliminary Design Overview

Page 12: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

• Main Entrance• Secondary Entrance• Passenger Transportation (elevators, escalators)• Mechanical and Electrical Systems• Ventilation Shafts and Ventilation Fan Rooms• Traction Power Substations

Guiding Principle:Consolidate Surface Elements to enhance design & minimize impacts

•Reduce construction impacts (traffic, staging area, noise, dust )•Preserve public space and development potential•Save $

Stations 101What’s needed to make a Station Work?• Main Entrance• Secondary Entrance• Passenger Transportation (elevators, escalators)• Mechanical and Electrical Systems• Ventilation Shafts and Ventilation Fan Rooms• Traction Power Substations

Guiding Principle:Consolidate Surface Elements to enhance design & minimize impacts

•Reduce construction impacts (traffic, staging area, noise, dust )•Preserve public space and development potential•Save $

11/28/2011 12Bathurst Station - Preliminary Design Overview

Page 13: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

• Integrate with surrounding neighbourhood

• Safe and enjoyable user experience

• Full accessibility

• Preserve space for future re-development

• Enhance the local “sense of place”

• Long-term sustainability

• Reduce Construction Footprint & Impacts

• Reduce Costs

Design Philosophy

Accessibility for all users

13

• Integrate with surrounding neighbourhood

• Safe and enjoyable user experience

• Full accessibility

• Preserve space for future re-development

• Enhance the local “sense of place”

• Long-term sustainability

• Reduce Construction Footprint & Impacts

• Reduce CostsCompatible scale

11/28/2011 13Bathurst Station - Preliminary Design Overview

Page 14: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Accessibility Principles & Features• Access for persons with all levels of mobility

• Elevators

• Escalators

• Low-Floor Access

14

• Access for persons with all levels of mobility

• Elevators

• Escalators

• Low-Floor Access

11/28/2011 Bathurst Station - Preliminary Design Overview 14

Page 15: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Safety and Security Features• Monitored CCTV Security Cameras

• Urban Braille

• High Quality Lighting

1511/28/2011 15Bathurst Station - Preliminary Design Overview

Page 16: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

11/28/2011 Bathurst Station - Preliminary Design Overview 16

Page 17: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Architectural Design Approach• Excellence in architectural/urban

design treatments• Cost effective and maintainable

structures• Standard station box configurations• Creative use of materials, color,

textures, artwork, light• Brand identification with graphics• Use standard elements whenever

possible

• Excellence in architectural/urbandesign treatments

• Cost effective and maintainablestructures

• Standard station box configurations• Creative use of materials, color,

textures, artwork, light• Brand identification with graphics• Use standard elements whenever

possible

11/28/2011 17Bathurst Station - Preliminary Design Overview

Page 18: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Surface Elements – Guiding Principles

• Surface elements aremost visible to public

• Integrate into localcommunity

• Minimize propertyimplications

• High quality design• Major focus on

consolidating:– Entrances– Vent Shafts– Substations

• Surface elements aremost visible to public

• Integrate into localcommunity

• Minimize propertyimplications

• High quality design• Major focus on

consolidating:– Entrances– Vent Shafts– Substations

11/28/2011 18Bathurst Station - Preliminary Design Overview

Page 19: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

The Approach to GuideDetailed Design

11/28/2011 19Bathurst Station - Preliminary Design Overview

Page 20: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

• Any architectural finish can containintegrated artwork, including:

• walls• floors• ceilings• glazing

Integrated Artwork

• Any architectural finish can containintegrated artwork, including:

• walls• floors• ceilings• glazing

11/28/2011 20Bathurst Station - Preliminary Design Overview

Page 21: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Cross-Section

11/28/2011 21Bathurst Station - Preliminary Design Overview

Page 22: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Station Entrances• Public spaces which fit into the

community• Main & Secondary Entrance• Main Entrance is fully accessible

• Use of height/massing to createunique structure

• Highly visible, transparent,sophisticated

• Promote Transit-OrientedDevelopment

• Maximize daylight opportunities• Well lit at night• Connect with Buses on street

• Public spaces which fit into thecommunity

• Main & Secondary Entrance• Main Entrance is fully accessible

• Use of height/massing to createunique structure

• Highly visible, transparent,sophisticated

• Promote Transit-OrientedDevelopment

• Maximize daylight opportunities• Well lit at night• Connect with Buses on street

11/28/2011 22Bathurst Station - Preliminary Design Overview

Page 23: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Traction Power SubstationsWhat and Why?

• Required to provide power to the station system• Every two kilometres, at stations• Many different configurations• Above ground, surface, below-ground• Guidelines to integrate substations

• Required to provide power to the station system• Every two kilometres, at stations• Many different configurations• Above ground, surface, below-ground• Guidelines to integrate substations

11/28/2011 23Bathurst Station - Preliminary Design Overview

Page 24: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

PresentationPart 2:Bathurst Station

24

PresentationPart 2:Bathurst Station

11/28/2011 24Bathurst Station - Preliminary Design Overview

Page 25: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Bathurst Station Preliminary Design

Preliminary Design by:

Crosstown ConsortiumIBI GroupLEA ConsultingSNC Lavalin

Preliminary Design by:

Crosstown ConsortiumIBI GroupLEA ConsultingSNC Lavalin

11/28/2011 Bathurst Station - Preliminary Design Overview 25

Page 26: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

Local ContextPopulation Density within a 10 minute walk to Bathurst Station

11/28/2011 Bathurst Station - Preliminary Design Overview 26

Page 27: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Bathurst Station – Existing Uses &Proposed Development

11/28/2011 Bathurst Station - Preliminary Design Overview 27

Page 28: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

11/28/2011 Bathurst Station - Preliminary Design Overview 28

Page 29: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Bathurst Station – Local ContextUpper Village Business Improvement Area (BIA)•www.uppervillagetoronto.ca

•Represents merchants, venues and services from Allen Road to Bathurst Street

•Wide selection of shops, restaurants & services

11/28/2011 Bathurst Station - Preliminary Design Overview 29

•www.uppervillagetoronto.ca

•Represents merchants, venues and services from Allen Road to Bathurst Street

•Wide selection of shops, restaurants & services

Page 30: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Bathurst Station – EA (2010)(add property numbers)

11/28/2011 Bathurst Station - Preliminary Design Overview 30

Page 31: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

GenericRendering OnlyArchitectureConcept TBD

11/28/2011 Bathurst Station - Preliminary Design Overview 31

Potential FutureSecondary Entrance

Page 32: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

Key Advantages of New Consolidated Design

Reduces construction footprint, cost & impacts(roadway construction reduced by 21.5 metres)

Improves look and feel from street for community

Reduces number of properties affected

Preserves potential for investment and development withmore public space

11/28/2011 Bathurst Station - Preliminary Design Overview 32

Key Advantages of New Consolidated Design

Reduces construction footprint, cost & impacts(roadway construction reduced by 21.5 metres)

Improves look and feel from street for community

Reduces number of properties affected

Preserves potential for investment and development withmore public space

Page 33: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

11/28/2011 33Bathurst Station - Preliminary Design Overview

NORTH/EAST CORNER OFBATHURST AND EGLINTON

Page 34: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

11/28/2011 34Bathurst Station - Preliminary Design Overview

NORTH/EAST CORNER OFBATHURST AND EGLINTON

Page 35: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

11/28/2011 35Bathurst Station - Preliminary Design Overview

Rear Laneway

Page 36: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

11/28/2011 36Bathurst Station - Preliminary Design Overview

• Setbacks TBD

Page 37: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

11/28/2011 37Bathurst Station - Preliminary Design Overview

Page 38: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

11/28/2011 Bathurst Station - Preliminary Design Overview 38

Page 39: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

11/28/2011 Bathurst Station - Preliminary Design Overview 39

Page 40: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

11/28/2011 Bathurst Station - Preliminary Design Overview 40

Page 41: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary Design

11/28/2011 Bathurst Station - Preliminary Design Overview 41

Page 42: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

11/28/2011 42Bathurst Station - Preliminary Design Overview

Page 43: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

11/28/2011 43Bathurst Station - Preliminary Design Overview

Page 44: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

11/28/2011 44Bathurst Station - Preliminary Design Overview

Page 45: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

11/28/2011 45Bathurst Station - Preliminary Design Overview

Page 46: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

Passenger Circulation

11/28/2011 46Bathurst Station - Preliminary Design Overview

ISOMETRIC

Page 47: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

Architectural Concept:PreliminaryRepresentation•subject to change

11/28/2011 47Bathurst Station - Preliminary Design Overview

Page 48: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

PreliminaryRepresentation•subject to change

11/28/2011 48Bathurst Station - Preliminary Design Overview

Page 49: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

PreliminaryRepresentation•subject to change

11/28/2011 49Bathurst Station - Preliminary Design Overview

Page 50: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

11/28/2011 Bathurst Station - Preliminary Design Overview 50

Page 51: Bathurst Station Preliminary Design Consultation

Bathurst Station Preliminary DesignBathurst Station Preliminary Design

11/28/2011 Bathurst Station - Preliminary Design Overview 51