1 Successful Implementation & Improved Operation Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Perth – 15th May 2013

Arasu Thanigai Commissioning Solutions

Embed Size (px)

DESCRIPTION

Pepperl+Fuchs Presentation on Installation and Commissioning

Citation preview

Page 1: Arasu Thanigai Commissioning Solutions

11 Successful Implementation & Improved Operation

Commissioning issues and solutions

Arasu ThanigaiPepperl+Fuchs Pte LtdSingapore

Fieldbus Foundation Seminar Perth – 15th May 2013

Page 2: Arasu Thanigai Commissioning Solutions

22 Successful Implementation & Improved Operation

Device Commissioning

Physical layer Commissioning

Commissioning Process

Page 3: Arasu Thanigai Commissioning Solutions

33 Successful Implementation & Improved Operation

Install the CablesCheck out the cable installationInstall the DevicesCheck the device installation

Install the DCSAssigning the I/OCalibration the SensorRangingCalibration the 4~20mASystem RangingSystem Calibration 4~20mAPhysical Parameters

Commissioning Process

Page 4: Arasu Thanigai Commissioning Solutions

44 Successful Implementation & Improved Operation

4~20mAInstall the CablesCheck out the cable installationInstall the DevicesCheck the device installation

Install the DCSAssigning the I/OCalibration the SensorRangingCalibration the 4~20mASystem RangingSystem Calibration 4~20mA

Foundation Fieldbus• Install the Cables• Check out the cable installation• Install the Devices• Check the device installation

• Install the DCS• Assigning the I/O• Calibration the Sensor• Ranging• Calibration the 4~20mA• System Ranging• System Calibration 4~20mA

Commissioning Process Comparison.

Page 5: Arasu Thanigai Commissioning Solutions

55 Successful Implementation & Improved Operation

4~20mA Foundation Fieldbus4-20mA

P.S.

fieldbus

P.S.

Distance and relevant issueArtificial hours and relevant costCable connection QuantityHidden trouble points

Cable installation

Page 6: Arasu Thanigai Commissioning Solutions

66 Successful Implementation & Improved Operation

4~20mAInstall the CablesCheck out the cable installationInstall the DevicesCheck the device installation

Install the DCSAssigning the I/OCalibration the SensorRangingCalibration the 4~20mASystem RangingSystem Calibration 4~20mA

Foundation Fieldbus• Install the Cables• Check out the cable installation• Install the Devices• Check the device installation

• Install the DCS• Assigning the I/O• Calibration the Sensor• Ranging• Calibration the 4~20mA• System Ranging• System Calibration 4~20mA

Commissioning Process Comparison.

Page 7: Arasu Thanigai Commissioning Solutions

77 Successful Implementation & Improved Operation

4~20mA Foundation Fieldbus4-20mA

P.S.

fieldbus

P.S.

Test Report

Distance and connection QuantityTools

Checking of cable installation.

Page 8: Arasu Thanigai Commissioning Solutions

88 Successful Implementation & Improved Operation

4~20mAInstall the CablesCheck out the cable installationInstall the DevicesCheck the device installation

Install the DCSAssigning the I/OCalibration the SensorRangingCalibration the 4~20mASystem RangingSystem Calibration 4~20mA

Foundation Fieldbus• Install the Cables• Check out the cable installation• Install the Devices• Check the device installation

• Install the DCS• Assigning the I/O• Calibration the Sensor• Ranging• Calibration the 4~20mA• System Ranging• System Calibration 4~20mA

Commissioning Process Comparison.

Page 9: Arasu Thanigai Commissioning Solutions

99 Successful Implementation & Improved Operation

4~20mAInstall the CablesCheck out the cable installationInstall the DevicesCheck the device installation

Install the DCSAssigning the I/OCalibration the SensorRangingCalibration the 4~20mASystem RangingSystem Calibration 4~20mA

Foundation Fieldbus• Install the Cables• Check out the cable installation• Install the Devices• Check the device installation

• Install the DCS• Assigning the I/O• Calibration the Sensor• Ranging• Calibration the 4~20mA• System Ranging• System Calibration 4~20mA

Commissioning Process Comparison.

Page 10: Arasu Thanigai Commissioning Solutions

1010 Successful Implementation & Improved Operation

Device Commissioning

Page 11: Arasu Thanigai Commissioning Solutions

1111 Successful Implementation & Improved Operation

Assigning the I/OFoundation fieldbus devices are recognized by three mechanisms: a traditional node address for communication, a human readable device tag corresponding to the project P&I diagram, and a unique identifier allowing the system to automatically resolve any tag or address conflicts. The system automatically assigns the address to all devices, avoiding human errors such as address duplication associated with manually managed protocols, and saving time. Therefore technicians work based on tag and need not be concerned with address. Thanks to the unique identifier, multiple devices can be connected and commissioned at the same time. It is plug-'n'-play.

Page 12: Arasu Thanigai Commissioning Solutions

1212 Successful Implementation & Improved Operation

4~20mAInstall the CablesCheck out the cable installationInstall the DevicesCheck the device installation

Install the DCSAssigning the I/OCalibration the SensorRangingCalibration the 4~20mASystem RangingSystem Calibration 4~20mA

Foundation Fieldbus• Install the Cables• Check out the cable installation• Install the Devices• Check the device installation

• Install the DCS• Assigning the I/O• Calibration the Sensor• N/A• N/A• N/A• N/A

Commissioning Process Comparison.

Page 13: Arasu Thanigai Commissioning Solutions

1313 Successful Implementation & Improved Operation

No range mismatchUnit downloaded when device is replaced

Transmitter PositionerFF FF

BUSFF

CTRL

CPU

CPU

CPUDigital DigitalDigital

TransmitterRange

0-800 kPa

SystemRange

0-400 kPa

8 mAProcess200 kPa

Reading100 kPa

...alarms and tripsnot working

AIUnit

Unit

AOUnit

Unit

Commissioning Process Comparison.

4~20mA

Foundation Fieldbus

Page 14: Arasu Thanigai Commissioning Solutions

1414 Successful Implementation & Improved Operation

Why Foundation Fieldbus

The global process industry loses $20billion, or five percent of annual production,due to unscheduled downtime and poorquality.

ARC estimates that almost 80 percent ofthese losses are preventable, with 40 percentlargely due to operator error.

Source ARC Insight June 10 2010

Page 15: Arasu Thanigai Commissioning Solutions

1515 Successful Implementation & Improved Operation

Common issues – Device Commissioning

Check DD file and integrate into Engineering systemCheck ITK versionCheck if HIST doneCheck if the device listed at www.fieldbus.org

Page 16: Arasu Thanigai Commissioning Solutions

1616 Successful Implementation & Improved Operation

How to Check

Page 17: Arasu Thanigai Commissioning Solutions

1717 Successful Implementation & Improved Operation

Collaboration with NAMUR

Using the power of FOUNDATION Fieldbus, and considering NAMUR requirements, the new standard diagnostic profile aim to:– Standardize the integration of diagnostic information– Guarantee valuable information to the user

Page 18: Arasu Thanigai Commissioning Solutions

1818 Successful Implementation & Improved Operation

Diagnosis results must be reliable

Diagnosis results must always be viewed in the context of the application.

Internal diagnosis must be categorized into 4 standard “status signals”

Configuration must be free, as reactions will depend on the user's requirements

Detailed information can be read out by the device specialist

NAMUR NE107: Self-Monitoring and Diagnosis of Field Devices

Page 19: Arasu Thanigai Commissioning Solutions

1919 Successful Implementation & Improved Operation

Namur - Diagnostic categories

Maintenance Required The output from the device is valid but the wear reserve is nearly exhausted or function will be restricted due to operational conditions

Out of Specification Measurement uncertainty, or output position deviation, is greater than expected due to deviations in ambient or process conditions.

Function Check Output invalid due to ongoing work on the device

Failure Output is invalid due to a malfunction in the field device

Page 20: Arasu Thanigai Commissioning Solutions

2020 Successful Implementation & Improved Operation

Distribution of information

Maintenance Required

Out of Specification

Function Check

Failure

Output is valid

Measurement is uncertain

Ongoing work on the device, output invalid

Wear reserve is exhausted

due to deviations in ambient conditions.

Output is invalid malfunction in the field device

OPERATORINSTRUMENT TECH

Page 21: Arasu Thanigai Commissioning Solutions

2121 Successful Implementation & Improved Operation

Mapping to FF Quality Status & Block Error bits

Maintenance Required

Out of Specification

Function Check

Failure

Output is valid

Measurement is uncertain

Ongoing work on the device, output invalid

Wear reserve is exhausted

due to deviations in ambient conditions.

Output is invalidmalfunction in the field device

INSTRUMENT TECH

GOOD

UNCERTAIN

OUT OF SERVICE

BAD

NEEDS MAINT SOON

NEEDS MAINT SOON

NEEDS MAINT NOW

QUALITY STATUS BLOCK ERROR

OPERATOR

Page 22: Arasu Thanigai Commissioning Solutions

2222 Successful Implementation & Improved Operation

Commissioning Issues

Physical Layer commissioning.

Page 23: Arasu Thanigai Commissioning Solutions

2323 Successful Implementation & Improved Operation

AG 181

Page 24: Arasu Thanigai Commissioning Solutions

2424 Successful Implementation & Improved Operation

Typical problems

Improperly closed housing

Loose wire

Internally modified

Error log showingintermittent faults

Interoperability testingby end user

Electro-magnetic interferenceFaulty field deviceCable degradationWrong termination

Page 25: Arasu Thanigai Commissioning Solutions

2525 Successful Implementation & Improved Operation

Need for diagnostics

• Field study by installation and commissioning Engineers around the world shows that more than 80% of the plant disturbances come from the physical layer level be it conventional 4-20mA applications or Fieldbus applications.

• Unless the engineers sufficiently trained for Fieldbus applications the most common mistakes are made at the physical layer level such as wiring faults, wrong termination etc.

Page 26: Arasu Thanigai Commissioning Solutions

2626 Successful Implementation & Improved Operation

Asset/Resource System Influencers

• Maintenance Cost Reduction Drives End Users• 40% of Mfg. Cost is Maintenance• 50% of Maintenance Is Corrective

– 10 times More Costly Than Preventative Maintenance

• Preventative Maintenance is Done 25% of Time– 5 Times More costly Than Predictive Maintenance

• 60% of Preventative Maintenance is Unnecessary• What has been largely missing up to now is timely,

relevant, and accurate information

From ARC Independent Research

Page 27: Arasu Thanigai Commissioning Solutions

2727 Successful Implementation & Improved Operation

Zone1Device Coupler

IS Device Coupler

Fiel

d De

vice

s

Fiel

d De

vice

s

Fiel

d De

vice

s

Zone2Device coupler TerminatorSurge

Protect.

SurgeProtect.

Fiel

d De

vice

s FieldbusProcess

Interfaces

Complete Interface

PowerSupplies

Page 28: Arasu Thanigai Commissioning Solutions

2828 Successful Implementation & Improved Operation

Hazardous safety rules not followed

– Ground faults– Fieldbus and power

cables tied together

Page 29: Arasu Thanigai Commissioning Solutions

2929 Successful Implementation & Improved Operation

Poor cable installation

Page 30: Arasu Thanigai Commissioning Solutions

3030 Successful Implementation & Improved Operation

ANSI recommendation

CommunicationCables(Fieldbus)

Shielded/UnshieldedCables Carrying>60 VDC or>25 VAC but<= 400 V

Shielded/UnshieldedCables Carrying> 400 V

Any Cables at risk ofLighting

Communication

Cables

(Fieldbus)

10 cm 20 cm 50 cm

Shielded/Unshielded

Cables Carrying

>60 VDC or

>25 VAC but

<= 400 V

10 cm 10 cm 50 cm

Shielded/Unshielded

Cables Carrying

> 400 V

20 cm 10 cm 50 cm

Any Cables at

risk of Lighting 50 cm 50 cm 50 cm

Page 31: Arasu Thanigai Commissioning Solutions

3131 Successful Implementation & Improved Operation

Poor cable installations– Cable gland not tight– Seal missing

Page 32: Arasu Thanigai Commissioning Solutions

3232 Successful Implementation & Improved Operation

And corrosion as a consequence

– Water ingress or worse: – Aggressive media

Page 33: Arasu Thanigai Commissioning Solutions

3333 Successful Implementation & Improved Operation

Poor Device Instalation

Page 34: Arasu Thanigai Commissioning Solutions

3434 Successful Implementation & Improved Operation

Poor maintenance

Page 35: Arasu Thanigai Commissioning Solutions

3535 Successful Implementation & Improved Operation

Typical locations and Fieldbus issues

Page 36: Arasu Thanigai Commissioning Solutions

3636 Successful Implementation & Improved Operation

– Always on the critical path– Manual, step-by-step procedure– Labor intensive– Requires

• Screw driver• Check sheet• Pencil• Multimeter• Battery Powered Oscilloscope

– Connect one device at a time– Disconnect after testing

Test Report

Commissioning in the Past.

Page 37: Arasu Thanigai Commissioning Solutions

3737 Successful Implementation & Improved Operation

A portable tool for commissioning, monitoring, troubleshooting and printout.

Portable Commissioning Tools

Page 38: Arasu Thanigai Commissioning Solutions

3838 Successful Implementation & Improved Operation

Online Commissioning Tools

Page 39: Arasu Thanigai Commissioning Solutions

3939 Successful Implementation & Improved Operation

Online Commissioning Tools

Page 40: Arasu Thanigai Commissioning Solutions

4040 Successful Implementation & Improved Operation

Online Commissioning Tools

Page 41: Arasu Thanigai Commissioning Solutions

4141 Successful Implementation & Improved Operation

Online Commissioning Tools

Page 42: Arasu Thanigai Commissioning Solutions

4242 Successful Implementation & Improved Operation

What parameters to look for– External power supply– Fieldbus Output Power– Fieldbus Segment current– Grounding and shielding– Communicaiton quality ( jitter) of segment and

devices– Signal amplitude– Noise at segment and deivces– FF Signal Waveform of the semgent– Terminators– Surge protection– Water / Moisutre

Page 43: Arasu Thanigai Commissioning Solutions

4343 Successful Implementation & Improved Operation

Simple Commissioning Steps with ADM

– Verify address setting– Wire up devices in the right location– Check shielding– Activate communication– Use automated work procedures

• Testing • Documentation

– All devices at once– Wiring remains undisturbed! Commissioning Wizard

Test Reportx

Page 44: Arasu Thanigai Commissioning Solutions

4444 Successful Implementation & Improved Operation

One Plant Asset Management – Includes fieldbus now as asset– Customary look and feel– Reduces required training – Reduces potential for errors

Open Architecture Integration:– AMS Suite– PRM– FieldCare – FieldMate– PACTware– OPC Interface– Experion– Many More

Commissioning now via DCS

Page 45: Arasu Thanigai Commissioning Solutions

4545 Successful Implementation & Improved Operation

Commissioning done from control room

Spurs

Field Instruments

Power Supply

Advanced Diagnostic Module

Device coupler

Trunk

Surge Protector

Terminator

Host

Page 46: Arasu Thanigai Commissioning Solutions

4646 Successful Implementation & Improved Operation

Just an Example - ADM via DCS Asset Management

Diagnostics atDCS Station

Rela

y co

ntac

top

tiona

l)

RS485

Industrial Switch

Ethernet or

FF H1

Address switches

Page 47: Arasu Thanigai Commissioning Solutions

4747 Successful Implementation & Improved Operation

Just an Example - Commissioning via DCS Asset management

PRM Alarm window view

PRM Network view

Segment-specific status of the physical layer ADM status view with PRM TAG

FF-Segment

FF-Host

Page 48: Arasu Thanigai Commissioning Solutions

4848 Successful Implementation & Improved Operation

Commissioning Wizard

With Expert System Support– Takes snapshot– Identifies wiring errors– Ensures compliance with

AG181 and IEC 61158-2– Recommends limits for ADM

messages– Stores limits in non-volatile memory

Automatic Tag ReadoutCreates baseline report: – Snapshot of all measurements – Complete documentation

Saves pre-commissioning time significantly

Page 49: Arasu Thanigai Commissioning Solutions

4949 Successful Implementation & Improved Operation

Online monitoringClean layout shows boundaries– Displays measurement values – Highlights violations with color coding: – Issues diagnostic messages

Good value

Maintenance required

Out of specification

Page 50: Arasu Thanigai Commissioning Solutions

5050 Successful Implementation & Improved Operation

Diagnostic MenuExpert System delivers

clear text information for fast fault finding

1 Active messages2 Actionable information

with solution guideance based on expert system

3 History with timestampsWhen the failure…

… occured… disappeared

– Export function for external analysis and storage

11

222

33

Page 51: Arasu Thanigai Commissioning Solutions

5151 Successful Implementation & Improved Operation

Built-in fieldbus oscilloscope Feature

ADM provides expert tools for fast fault finding– For diagnosing complex scenarios– For the fieldbus expert– With fieldbus specific triggers– Captures up to 10 shots in a row

Page 52: Arasu Thanigai Commissioning Solutions

5252 Successful Implementation & Improved Operation

Wiring issues

Page 53: Arasu Thanigai Commissioning Solutions

5353 Successful Implementation & Improved Operation53

Bad wiring technique

Welding, variable frequency drives (VFD), Motors, machinery:Increase of HF noiseIncreasing number of retransmissionsCan be a combination of both

Page 54: Arasu Thanigai Commissioning Solutions

5454 Successful Implementation & Improved Operation

Practical Example – Line frequency coupled

In this example the frequency of noise was approx. 150Hz

7 ms

Page 55: Arasu Thanigai Commissioning Solutions

5555 Successful Implementation & Improved Operation

Not a good device location

FF Device Moved away from Drive

Page 56: Arasu Thanigai Commissioning Solutions

5656 Successful Implementation & Improved Operation

Loose wiring issues

“Make” Disturbance

"Break" disturbance

Vibration frequency

FF signal

Failed telegram

Telegram

Page 57: Arasu Thanigai Commissioning Solutions

5757 Successful Implementation & Improved Operation

Does Surge Protection works?

FIELDBUS TERMINATOR

SEGMENT PROTECTORS

HOST

FIELDBARRIERS

PROCESSINTERFACE

POWER SUPPLY

CONVENTIONAL FIELD DEVICES

FIELDBUS DEVICES

JUNCTION BOX

But Practically this setup is not possible due to cost reasons.Protection at both trunk ends is more feasible

During commissioning or normal operation, surge protection devices can be check if it works

Page 58: Arasu Thanigai Commissioning Solutions

5858 Successful Implementation & Improved Operation

Conclusion – Advanced Diagnostics tools for for physical layer

reduced physical layer commissiong time and provided online monitoring and reporting system that saves CAPEX and OPEX

– Most problems at early bus installations were due to poor installation. However, simple, user-friendly, Fieldbus testers are now available, allowing the installation crew to easily check the wiring, and the device commissioning crew to check network operation, spotting any problems early

– Many contractors and Technicians are trained and are skilled in Fieldbus installation and commissioning, and have the test equipment and in-house procedures to ensure reliable operation