AMBIENT AIR MONITORING NEAR
MOSAIC’S PHOSPHOGYPSUM STACK
EPC Board Meeting
August 18, 2011
DEVELOPMENT OF REGIONAL IMPACT (DRI) #242
DRI is a development having a
widespread impact on the community
Development Order Specific Condition
A.8.a.
Two ambient air dust samplers were
placed at Progress Village Middle
School and Gibsonton Elementary
DUST MONITORING SITE MAP
Existing
Monitoring
Stations
Additional
Monitoring
Stations
INSERT DUST CHARTPM 10 Air Quality Trend 2003-2007
Based on Annual 2nd Maximum 24-hour Average
0
20
40
60
80
100
120
140
160
2003 2004 2005 2006 2007
Co
ncen
trati
on
(u
g/m
3)
Causeway Davis Island Gardinier Gibsonton
Progress SADS National
National Standard
The dust monitoring showed no statistically
significant difference in dust concentrations
RADON MONITORING
Phosphogypsum is stacked near the
chemical processing plants
The radioactivity of the stacked
phosphogypsum is considered low level
Radon gas is a colorless, odorless gas
that emanates from the ground
In 2010, EPC entered into a contract
with the Florida Department of Health
RADON MONITORING SITE MAP
Two rounds of monitoring were conducted
16 sites around the gypstack were selected along
with the subject schools and a control site
MEASUREMENTS
Radon study looked at alpha particles and gamma
rays
Measurements were taken for 90 days
Gamma readings were taken at the time of
deployment
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
Gypstack
Average
Gibsonton
Elementary
School
Ippolito
Elementary
School
Progress
Village Middle
School
Control Site
pC
i/L
Winter 2010 Deployment Radon Levels
Measured
Radon Levels
EPA Action
Level
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
Gypstack
Average
Gibsonton
Elementary
School
Ippolito
Elementary
School
Progress
Village Middle
School
Control Site
pC
i/L
Summer 2010 Deployment Radon Levels
Measured
Radon Levels
EPA Action
Level
0
500
1000
1500
2000
2500
3000
3500
4000
Flight from NY
to LA
Dental X-ray Eating a banana Gypstack Avg School Avg
μR
/hr
Measured Gamma
Gamma Comparison Levels
CONCLUSIONS
The average for both the first and
second deployment at the gypstack is
0.68 pCi/L
Based on the initial study, the results
do not indicate any elevated readings at
any of the schools
Overall, the sampling periods showed
some differences