TEAM DAREDEVILQCC Kaizen Workshop – SS12
Theme : Reduce Wrinkle Defect in C2B 2B Model : Classic leather Ripple III FamilyLocation : 2BPeriod : 7 Nov-7 Des 2011Update :
Team Member :M.Taufik (CI Dept.)Aka FAuza (CI Dept.)Eni Rohaeni (C2B Dept.)Anwarudin (M2B Dept)
Timan (QIP Dept.)Suharno (RM WH.)Reni (QIP Dept)
Contents
Project Overview QCC Team Organization ChartGantt Chart Activities Progress
Activities Pictures Best Practice
Current Result Result
Project overviewProject Theme : Reduce Wrinkle Defect in C2B 2B Model : Classic Leather Ripple III Family
Baseline (august – october)Defect Rate : 120,5/1.973
: 6,1 %Target : 3 %
Estimate saving money /order /9000 pears.From base line : 6,1% x 9000
: 549 pearsTarget 50% : 549 x 50%
: 274 pearsin USD : 274 x 13.85 USD
: 3.795 USD x 40%(downprice)
:1.518 USD
Team Charter Johnny Huang (PYI OM) Hardy Lai (Prod Mgr) Yang Shang Mei (B5 Mgr)
John Chou (CI&IE) Liu Yao ping (QIP) Yang (Development) Yayat P (Reebok OC) Adia R (Reebok OC)
Miss Huang (1B -5B)
Eni Rohaeni (2B C2B)
Yeni S (Cutting 2B), Ela (Stitching 2B), Susilawati (Assembly 2B)
Steering Committee
Sponsor/Advisor
Facilitator
QCC Leader
Theme Leader
Problem Solving - CEDAC
Gantt Chart
Gantt Chart
Activities Progress
11/04/2011
All member cooperate to solving problem And calculating benefit, achievement.
Group Picture
Remark: Specific group picture not available yet
11/04/2011