Building the Future Current Activities this Week : Mass Excavation : Backfilling of on-grade seating is ongoing in Area 1, Area 2 and Area 3. Site Utilities : Storm Sewer installation (Line 6000) is ongoing on east side of France Family Drive. Sanitary Sewer Line E installation has started on east side of France Family Dive. Foundations : Area 2 Concourse Level – E-Line footing installation is ongoing and E-Line wall installation is ongoing. Area 3 Field Level – A-Line footing (to column line 1) and wall installation (to column line 4) is ongoing. Area 3 Field Level – Installation of Drilled Piers are complete. Area 4 Mezzanine Level – D-Line grade beam installation is ongoing and wall forms are being set. Concrete Flatwork : Area 1 Mezzanine – North slab on metal deck at VIP Entry concrete is placed. Area 1 Concourse – Structural Slab is placed from Column lines 33-23. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 6.9.2010 Re: Wizards Stadium Project Update – Week of 6.7.2010 Field Level Area 1 – Shallow Underground plumbing pipe installation has started at Mens Field Toilet 01.32.02. Mezzanine Level Area 1 – Concrete Slab on Metal Deck at VIP Entry is placed. Field Level Area 3 – A-Line footing and wall installation is ongoing up to Column Line 1.

Weekly Construction Update 06-14-10

Embed Size (px)

DESCRIPTION

KC Soccer Stadium construction update from Turner Construction.

Citation preview

Page 1: Weekly Construction Update 06-14-10

Building the Future

Current Activities this Week:

Mass Excavation:

Backfilling of on-grade seating is ongoing in Area 1,

Area 2 and Area 3.

Site Utilities:

Storm Sewer installation (Line 6000) is ongoing on

east side of France Family Drive.

Sanitary Sewer Line E installation has started on east

side of France Family Dive.

Foundations:

Area 2 Concourse Level – E-Line footing installation is

ongoing and E-Line wall installation is ongoing.

Area 3 Field Level – A-Line footing (to column line 1) and

wall installation (to column line 4) is ongoing.

Area 3 Field Level – Installation of Drilled Piers

are complete.

Area 4 Mezzanine Level – D-Line grade beam installation

is ongoing and wall forms are being set.

Concrete Flatwork:

Area 1 Mezzanine – North slab on metal deck at VIP

Entry concrete is placed.

Area 1 Concourse – Structural Slab is placed from

Column lines 33-23.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 6.9.2010

Re: Wizards Stadium Project

Update – Week of

6.7.2010

Field Level Area 1 – Shallow Underground

plumbing pipe installation has started at

Men’s Field Toilet 01.32.02.

Mezzanine Level Area 1 – Concrete Slab on

Metal Deck at VIP Entry is placed.

Field Level Area 3 – A-Line footing and wall

installation is ongoing up to Column Line 1.

Page 2: Weekly Construction Update 06-14-10

Building the Future

Structural Steel Erection:

Area 1 – Steel Erection in sequence 1-5 is nearly complete

is currently to Column Line 23. Seven raker pieced remain.

Decking/Detailing/Studs/Edge Angle is ongoing in

sequence 1-2, 1-4 and 1-5.

Underground MEP:

Deep Sanitary installation is ongoing in Area 3.

Electrical Secondary is ongoing in Area 2

MEP Rough-in:

Plumbing and Electrical rough-in for concrete decks are

ongoing Suite Level. Shallow plumbing rough-in has

started at Area 1 Field Level.

Projected Activities occurring next Week:

Mass Excavation:

Backfilling of on-grade seating areas will continue in Area

3.

Site Utilities:

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will continue. Storm Line 5000 and

4000 will begin. Installation of Sanitary Line E will continue.

Deep Underground Plumbing:

Deep Sanitary installation in Area 3 will continue.

Foundations:

Area 2 Concourse Level – Footing and wall installation

will continue.

Area 3 Field Level – A-Line wall placement will continue.

Area 4 Mezzanine Level – Foundation Wall installation will

continue.

Area 1 – Structural Steel Erection at West

Building is nearly complete from Column

Line 33 – 23.

Field Level Area 2 – Backfill of on-grade

seating area between column lines 21-18 is

ongoing.

Concourse Level Area 1 – Concrete

installation taking place from Column Lines

C – 33.

Page 3: Weekly Construction Update 06-14-10

Building the Future

Concrete Flatwork:

Area 1 Suite Level – Concrete placement will begin.

Structural Steel Erection:

Erection of Structural Steel in Sequence 1-3 will

begin.

Decking/Detailing/Studs/Edge Plates will continue in

Sequence 1-5.

Underground MEP:

Deep Sanitary installation will continue in Area 3.

Electrical Secondary will continue in Area 2

MEP Rough-in:

Plumbing and Electrical rough-in for concrete decks will

begin at Press Level. Shallow plumbing rough-in will

continue at Area 1 Field Level. Shallow electrical will

begin at Area 1 Field Level.

Field Level Area 2 – Isolated footing C12

reinforcing steel being installed.

Suite Level Area 1 – Concrete slab

reinforcing being installed in preparation for

upcoming pour.

Page 4: Weekly Construction Update 06-14-10

Building the Future

Additional Photos:

Field Level Area 2/3 – Shot looking northeast

showing foundations from column line 15-1.

Area 1 – Shot looking south showing the

field walls, foundations walls, rakers and

west building.

Field Level Area 1 – Secondary electrical

underground is ongoing near column line

21.

Concourse Level Area 2 – Footing excavation

for E-Line footing is ongoing.

Field Level Area 2 – Shot looking south

showing southeast vomitory, south on-grade

seating, stage and southwest vomitory.

Field Level Area 1 – Electrical manhole MH-1

is installed.