Agenda
• Life Before Continuous Delivery • Discovering and Implementing Continuous
Delivery • Refining the Flow • Working with Continuous Integration/Delivery • Evolving Continuous Delivery
2
Engineering
• About 15-18 engineering teams each with an average size of 8-12 engineers
• Typical ratio of 1 Quality Engineer per 2-3 Software Engineers
• Teams function as either Feature teams, Platform teams or a combination of both
4
Engineering
• Distribution includes: • Waltham, MA (Head Office) • Tribeca, NY • Battery Park, NY • San Francisco, CA • Boca Raton, FL • Loveland, CO
5
Life Before CD
• Weekly deploys • Build pipelines owned and operated by
Engineering Services • All deploys had to go through a request and
queue process • Progressing through 5 different environments
• Development, Functional, Load, Stage, Production
7
Life Before CD
• Engineers coding large units of work in the Development Environment
• Code was then deployed to the Functional environment
• Testing implemented and executed by the Quality Engineers in the Functional testing Environment
• Integration testing may happen in the Functional or Load Testing Environment
• Once all tested code progressed to the Stage Environment
8
10
Development LoadFunctional Stage Production
30% Stable
80% Stable
90% Stable
99% Stable
99% Stable
Life Before CD
• Visibility on what was being deployed was very general
• We knew work was going out but troubleshooting issues tended to be tricky due to large commits
• Kanban SDLC • Multitasking was a big thing
11
We set goals!
• Development teams own their applications • Build and deploy through to production
• Deliver quality code minimising defects through improved test coverage
• Increase velocity by 20% by the end of 2013, another 50% by the end of 2014
• Direct to production deploys by the end of 2014
17
We formed a CD Team
• Main body of governance for CD • Core development and assistance of integrations • Goto team for anything CD • Consisted of:
• Product Owner • Dev Manager • Architect • QE
• Engineering was utilised form the team adopting CD
18
Planning
• Key to success in implementing CD • Where are you deploying? • What are the steps to a successful deploy? • What are the effects of one event to another? • How will engineers engage with CD? • How will this affect existing product work? • What are the milestones you want to deliver to
a team? • Comes even before thinking of tooling
19
The Approach
• Convert to a single-branch model • Hard version all artefacts (produced and
consumed) • Harden test coverage • Set up the skeleton build jobs
• Simple Checkout -> Build -> Unit Test -> Publish -> Deploy Pipeline
• Deploy to 1 environment only then backfill
20
The Approach
• We didn’t want to manage multiple environments any more just 1 environment!
• Implement the practice of Feature Switches • Coach the Product owners how to write User
Stories
21
Integration Testing
• Whole environment configured to execute Integration testing
• Separate Jenkins Server • Separate OpenStack Group • Owned by the QE team
27
28
Development LoadFunctional Stage Production
CD Deploy Manual Deploy
Manual Deploy
Manual Deploy
Manual Deploy
29
Development LoadFunctional Stage Production
CD Deploy
Backfill
Manual Deploy
Manual Deploy
Manual Deploy
1 OS VM
30
Development LoadFunctional Stage Production
CD Deploy
Backfill
Manual Deploy
Manual Deploy
Backfill
1 OS VM 2 OS VMs
31
Development LoadFunctional Stage Production
CD Deploy
Backfill
Push Button Deploy
Backfill Backfill
30% Stable
80% Stable
90% Stable
99% Stable
99% Stable
1 OS VM 2 OS VMs
4 OS VMs
32
Development LoadFunctional Stage Production
CD Deploy
Backfill
Push Button Deploy
Backfill Backfill
30% Stable
80% Stable
90% Stable
99% Stable
99% Stable
1 OS VM 2 OS VMs
4 OS VMs
6 OS VMs
Automating Servers
• Ensure that domains are properly configured • Setting up and pulling down instances in a
coordinated fashion • Attaching to the correct environment
34
Monitoring & Alerts
• Jenkins Job health plugin • Healthcheck dashboard • Splunk Logging • Nagios
35
Results of First Deliverable
• We had direct to Load deploys happening with backfill
• Test coverage up • New SDLC with QEs engaging at the beginning
of the flow, not waiting for engineers to complete work
• New way to view the health of the system through monitoring
• Base skeleton workflow that would be used to build new pipelines
36
Discoveries
• There is no main entry point when starting CD • Planning is crucial • Your SDLC will most likely change • Monitoring is key to knowing your progress • Educating the users of the system is also
paramount • Everyone is involved with CD
37
Discoveries
• CD is evolutionary • It will become part of your projects, not a
separate project • It will help your velocity just not right away • Don’t be afraid to innovate
38
SDLC
• Scaled Agile Framework • Initially taken from v1.0 • More recently v3.0
• Had to change • Epics -> Features -> Stories (-> Tasks)
40
SDLC
• Needed better tracking of what was happening now
• Velocity increased • A new development programme had to be put
together • Moved from Kanban to Scrum
41