1 Durham-Orange Light Rail Transit Project Economic Development & Public Policy Committee Meeting Chapel Hill-Carrboro Chamber of Commerce

Update on Light Rail from Triangle Transit

Embed Size (px)

DESCRIPTION

Update on Light Rail from Triangle Transit

Citation preview

Page 1: Update on Light Rail from Triangle Transit

1

Durham-Orange Light Rail Transit Project

Economic Development & Public Policy Committee Meeting

Chapel Hill-Carrboro Chamber of Commerce

Page 2: Update on Light Rail from Triangle Transit

3

Page 4: Update on Light Rail from Triangle Transit

5

Page 5: Update on Light Rail from Triangle Transit

66

Travel Intensity High in Corridor2040 Trip Intensity Map

Page 6: Update on Light Rail from Triangle Transit

77

Goals of the Proposed Project

Expand Transit Options

Enhance Mobility

Serve populations likely to use transit

Foster compact development

255,000 trips by 2035

and

Page 7: Update on Light Rail from Triangle Transit

88

Alternative Routes

evaluated

Page 8: Update on Light Rail from Triangle Transit

99

November Public Workshops

Page 9: Update on Light Rail from Triangle Transit

10

Projected travel

patterns for 2035

Page 10: Update on Light Rail from Triangle Transit

1313

Every 10 minutes of additional

commuting time cuts all other forms of civic

engagement by 10%

Page 11: Update on Light Rail from Triangle Transit

14Courtesy of Charlotte Area Transit System

(CATS)

Page 12: Update on Light Rail from Triangle Transit

1515

Durham-Orange LRT Project

• 17 stations along 17 miles of exclusive tracks primarily at-grade with elevated sections at key locations

• Between UNC Hospitals and Alston Ave in East Durham• End-to-end travel time 39 minutes• Service:

7 days per week, 18 hours per day 10-min during peak hours 20-min off-peak and on weekends

• Average weekday ridership:23,000 boardings by 2035

Page 13: Update on Light Rail from Triangle Transit

16

Page 15: Update on Light Rail from Triangle Transit

18

EIS

Technical Analysis

Public Input

Social Impacts

Economic Impacts

Environmental Impacts

Page 16: Update on Light Rail from Triangle Transit

2222

Transit Oriented Development

The MillenniumBland Street Station Area

BEFORE AFTER

Page 17: Update on Light Rail from Triangle Transit

2323

Agency & Public Involvement

150 + public/community meetings

Page 18: Update on Light Rail from Triangle Transit

24

Let us know what you think!

(800) 816-7817

[email protected]

www.ourtransitfuture.com

PO Box 530, Morrisville, NC 27560